SlideShare a Scribd company logo
1 of 44
Download to read offline
 Original Design of Rehabilitation of existing RC drinking
water reservoir considered cleaning of the reservoir,
removal of old plaster and “ironing” of the walls, plastering
of inner roof slab surface.
 After the entry to washed reservoir where deposited sludge
has been removed, disturbing existing conditions have been
revealed. What came immediately to attention is bunch of
roof slab reinforcement hanging like spaghetti from the roof
slab, deteriorated from corrosion during constant exposure
to high humidity where no concrete cover was provided
during original reservoir construction. Roof slab
reinforcement was ~70% exposed, visible. Previous attempt
of exposed reinforcement protection was visible where
plastic foil tapes were applied directly over the
reinforcement. Holes present in roof slab concrete from
where rain, bugs, small animals could easily enter the
reservoir. Multiple orange stains on the inner walls
indicating serious leaking of the reservoir walls where high
level of underground water managed to enter the reservoir.
Walls were multiple times coated by all types of hydro-
plaster, failing to seal the walls, concrete deteriorated on
water entry points. Columns made of oversized aggregate
concrete with exposed reinforcement on some sections.
Uneven, unlevelled base slab surface with spilled concrete
from previous “rehabilitation projects”.
 With coordination of Employer and Designer, scope of works
has been changed and extended where a New Design
consisted of removal of existing roof slab and part of walls –
so that new reservoir could be built inside of the existing
reservoir shell. Considering doubtful structural stability of
vibrating roof slab, no-entry has been declared due to H&S
reasons. Demolition of the reservoir’s roof slab exposed that
roof slab thickness was 8-10cm with deteriorated & corroded
reinforcement (only 1 layer), bars were not even lapped and
those which were attempted to over-lap had no contact with
each other. Only plain bars were used, no ribbed bars! During
walls plaster removal - 5-6 layers of plaster were detected
whose removal exposed that during original construction
some 20yrs ago – no water stop was used between
horizontal 1.0m high layers of concrete installed in walls, next
wall-layer of concrete installed directly over the joint from
previous layer without any water-stop used. Water has easily
found its path throughthese cold-joints. By revised Design,
reservoir has been demolished (roof slab & part of walls), its
shell used as a "lost formwork" for construction of new
reservoirs inside of existing reservoirs.
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation

More Related Content

What's hot

A New Look at Pervious Concrete
A New Look at Pervious Concrete A New Look at Pervious Concrete
A New Look at Pervious Concrete Dale Fisher
 
Permeable materials
Permeable materialsPermeable materials
Permeable materialscrownswear
 
Basement tanking
Basement tankingBasement tanking
Basement tankingchazza1234
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESPrabhu Saran
 
3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membrane3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membraneroaron
 
Some Maintenance Issues in Civil Engineering Works
Some Maintenance Issues in Civil Engineering WorksSome Maintenance Issues in Civil Engineering Works
Some Maintenance Issues in Civil Engineering WorksDr K M SONI
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs biharVaishnav Mishra
 
Freeze and Thaw and Seismicity Geotechnical presentation
Freeze and Thaw and Seismicity Geotechnical presentationFreeze and Thaw and Seismicity Geotechnical presentation
Freeze and Thaw and Seismicity Geotechnical presentationKamran Ahmed
 
Basement Foundation Waterproofing
Basement Foundation WaterproofingBasement Foundation Waterproofing
Basement Foundation Waterproofingbwnwaterproofing
 
Basement Waterproofing for Homeowners
Basement Waterproofing for HomeownersBasement Waterproofing for Homeowners
Basement Waterproofing for HomeownersMichael Razeghi
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water ConcretingSanjan Banerjee
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundationABIRAMI G
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of buildingtoshi gupta
 
Kryton Concrete Waterproofing and Durability Solutions Guide
Kryton Concrete Waterproofing and Durability Solutions GuideKryton Concrete Waterproofing and Durability Solutions Guide
Kryton Concrete Waterproofing and Durability Solutions GuideKryton International Inc.
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwaterAJITA PANDEY
 
Understanding waterproofing
Understanding waterproofingUnderstanding waterproofing
Understanding waterproofingGraceAPAC
 

What's hot (19)

A New Look at Pervious Concrete
A New Look at Pervious Concrete A New Look at Pervious Concrete
A New Look at Pervious Concrete
 
Transportation of concrete
Transportation of concreteTransportation of concrete
Transportation of concrete
 
Permeable materials
Permeable materialsPermeable materials
Permeable materials
 
Basement tanking
Basement tankingBasement tanking
Basement tanking
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
 
3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membrane3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membrane
 
Some Maintenance Issues in Civil Engineering Works
Some Maintenance Issues in Civil Engineering WorksSome Maintenance Issues in Civil Engineering Works
Some Maintenance Issues in Civil Engineering Works
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs bihar
 
Freeze and Thaw and Seismicity Geotechnical presentation
Freeze and Thaw and Seismicity Geotechnical presentationFreeze and Thaw and Seismicity Geotechnical presentation
Freeze and Thaw and Seismicity Geotechnical presentation
 
Basement Foundation Waterproofing
Basement Foundation WaterproofingBasement Foundation Waterproofing
Basement Foundation Waterproofing
 
Basement Waterproofing for Homeowners
Basement Waterproofing for HomeownersBasement Waterproofing for Homeowners
Basement Waterproofing for Homeowners
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water Concreting
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundation
 
Water leakage problem
Water leakage problem Water leakage problem
Water leakage problem
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Kryton Concrete Waterproofing and Durability Solutions Guide
Kryton Concrete Waterproofing and Durability Solutions GuideKryton Concrete Waterproofing and Durability Solutions Guide
Kryton Concrete Waterproofing and Durability Solutions Guide
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
 
Understanding waterproofing
Understanding waterproofingUnderstanding waterproofing
Understanding waterproofing
 

Similar to Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation

Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Vladimir Popovic
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro  Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro ALI HYDER GADHI
 
Water proofing in islamabad
Water proofing in islamabadWater proofing in islamabad
Water proofing in islamabadtayyab94
 
Basement waterproofing
Basement waterproofingBasement waterproofing
Basement waterproofingUnion, Nj
 
Manoj bk (water proofing)
Manoj bk (water proofing)Manoj bk (water proofing)
Manoj bk (water proofing)Manojkarader
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2Deepayan Mazumder
 
Carbon Fiber - FRP
Carbon Fiber - FRPCarbon Fiber - FRP
Carbon Fiber - FRPdewcraig
 
Carbon Fiber
Carbon FiberCarbon Fiber
Carbon Fiberjamieram
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREchintandomadiya
 
Defects in construction
Defects in constructionDefects in construction
Defects in constructionShivangi Saini
 
Defects in construction
Defects in construction Defects in construction
Defects in construction Aditya Sanyal
 
Repair and strengthening of concrete structures
Repair and strengthening of concrete structuresRepair and strengthening of concrete structures
Repair and strengthening of concrete structuresAbdallah Shaheen
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopVladimir Popovic
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Luke D'Arcy
 
Crack in Structure Report
Crack in Structure Report Crack in Structure Report
Crack in Structure Report Ryan Blessing
 

Similar to Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation (20)

Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro  Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 
Water proofing in islamabad
Water proofing in islamabadWater proofing in islamabad
Water proofing in islamabad
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
 
Basement waterproofing
Basement waterproofingBasement waterproofing
Basement waterproofing
 
Manoj bk (water proofing)
Manoj bk (water proofing)Manoj bk (water proofing)
Manoj bk (water proofing)
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Carbon Fiber - FRP
Carbon Fiber - FRPCarbon Fiber - FRP
Carbon Fiber - FRP
 
Carbon Fiber
Carbon FiberCarbon Fiber
Carbon Fiber
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
 
Defects in construction
Defects in construction Defects in construction
Defects in construction
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Repair and strengthening of concrete structures
Repair and strengthening of concrete structuresRepair and strengthening of concrete structures
Repair and strengthening of concrete structures
 
Construction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-StopConstruction Joints Sealing - Dual Seal Swellable Water-Stop
Construction Joints Sealing - Dual Seal Swellable Water-Stop
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
 
Crack in Structure Report
Crack in Structure Report Crack in Structure Report
Crack in Structure Report
 

More from Vladimir Popovic

Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgiaVladimir Popovic
 
Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosniaVladimir Popovic
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaVladimir Popovic
 
Rehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaRehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaVladimir Popovic
 
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Vladimir Popovic
 
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionLanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionVladimir Popovic
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww projectVladimir Popovic
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater projectVladimir Popovic
 
Ghadames project, minor structures
Ghadames project, minor structuresGhadames project, minor structures
Ghadames project, minor structuresVladimir Popovic
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipelineVladimir Popovic
 
Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Vladimir Popovic
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply ProjectVladimir Popovic
 
Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3Vladimir Popovic
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3Vladimir Popovic
 

More from Vladimir Popovic (14)

Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
 
Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
 
Rehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaRehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgia
 
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3
 
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionLanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater project
 
Ghadames project, minor structures
Ghadames project, minor structuresGhadames project, minor structures
Ghadames project, minor structures
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
 
Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
 
Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3Debeljaca WS Reservoir 700m3
Debeljaca WS Reservoir 700m3
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3
 

Recently uploaded

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 

Recently uploaded (20)

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 

Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation

  • 1.
  • 2.  Original Design of Rehabilitation of existing RC drinking water reservoir considered cleaning of the reservoir, removal of old plaster and “ironing” of the walls, plastering of inner roof slab surface.  After the entry to washed reservoir where deposited sludge has been removed, disturbing existing conditions have been revealed. What came immediately to attention is bunch of roof slab reinforcement hanging like spaghetti from the roof slab, deteriorated from corrosion during constant exposure to high humidity where no concrete cover was provided during original reservoir construction. Roof slab reinforcement was ~70% exposed, visible. Previous attempt of exposed reinforcement protection was visible where plastic foil tapes were applied directly over the reinforcement. Holes present in roof slab concrete from where rain, bugs, small animals could easily enter the reservoir. Multiple orange stains on the inner walls indicating serious leaking of the reservoir walls where high level of underground water managed to enter the reservoir. Walls were multiple times coated by all types of hydro- plaster, failing to seal the walls, concrete deteriorated on water entry points. Columns made of oversized aggregate concrete with exposed reinforcement on some sections. Uneven, unlevelled base slab surface with spilled concrete from previous “rehabilitation projects”.  With coordination of Employer and Designer, scope of works has been changed and extended where a New Design consisted of removal of existing roof slab and part of walls – so that new reservoir could be built inside of the existing reservoir shell. Considering doubtful structural stability of vibrating roof slab, no-entry has been declared due to H&S reasons. Demolition of the reservoir’s roof slab exposed that roof slab thickness was 8-10cm with deteriorated & corroded reinforcement (only 1 layer), bars were not even lapped and those which were attempted to over-lap had no contact with each other. Only plain bars were used, no ribbed bars! During walls plaster removal - 5-6 layers of plaster were detected whose removal exposed that during original construction some 20yrs ago – no water stop was used between horizontal 1.0m high layers of concrete installed in walls, next wall-layer of concrete installed directly over the joint from previous layer without any water-stop used. Water has easily found its path throughthese cold-joints. By revised Design, reservoir has been demolished (roof slab & part of walls), its shell used as a "lost formwork" for construction of new reservoirs inside of existing reservoirs.