SlideShare a Scribd company logo
1 of 28
BUDDH INTERNATIONAL CIRCUIT
PRESENTED BY: CHANDRADARSHAN JAIN
M.PHARM + MBA (P’CEUTICS)
P007
About Project
India’s Racing Arena
Jaypee International Circuit
Location : Greater Noida ,UP, India
Capacity : 1,20,000
Owner : Jaypee Group
Operator : Jaypee Sports International
Limited
Start : 2007
Opened : Oct. 2011
Construction cost : INR 20 billion
Architect : Hermann Tike
Project Manager : Sameer Gaur
Area : 2,500 acres
Circuit : Fact Sheet
• Length: 5.14km
• Turns: 16
• Highest point of elevation: 14m
• Width of the track: Between 18m – 20m
•
• Top speeds on the circuit: About
• 320km/h, for an F1 car
• Total seating capacity: About 120,000
• Distance from New Delhi: 40km approx.
• Surface : Asphalt concrete with Graywacke
Facts about Construction
In constructing Circuit
4 million cubic ton of Earth
were removed
325000 tons of asphalt were
used
130000 metric cube of
concrete were used
450 km of fiber optic cables
were used
Project Objectives
 Bring the F1 closerto the fans and the indian masses
 Make india a multi-sport country
 Boost to the hotel and tourism industry
 Lift to the country profile
 Potential to generate huge revenues and employment opportunities
Stake
holder
• IOA ( Indian Olympic Association )
• FIA (Federation Internationale de l’Automobile )
• FOA (Formula One Administration )
• JPSK Sports Pvt Ltd
• Participating Teams
• Fans
Tilke GmbH of Aachen, Germany (Design partner)
L & T (General contractor)
Kimley-Horn & Associates (Transportation and urban planning )
Walter P Moore & Associates (Traffic planning and transportation engineering)
Terracon Consultants (Geotechnical engineering & material quality)
Carlson Brigance & Doering inc. (Surveying & infrastructure expertise)
Miro Rivera Architects (Specific designs for structures & facilities)
Siemens (Race control management system)
Teracom + BSNL (Modems)
Airtel (Communication)
BHEL (Power)
BEL (Surveillance equipment)
ESPN-STAR (Telecasting)
Request for proposalRequest for proposal Site Plan
Project Planning
• A main Grand Stand
• 10 Temporary stands to seat more 100000 people
• 3 story cantilever building with 41 garages
• A race control room
• A state art of media center to cater more than 600 media person
• 18 fully furnished team buildings
• Pit zones
• A medical building
• A challenging Circuit
Site Specification
Project Execution
Plan
1. Acquisition of land
2. Construction of roads
3. Construction of first layer of circuit
4. Construction of stadium
5. Construction of pit zones
6. Construction of second layer of circuit
7. Construction of medical building
8. Construction of final layer of circuit
Construction Project - WBS
Work process
In October 2009 Earthwork was started
to build the track
Earth to a layer of 25 cm were compacted to a degree of
97% to make an embankment which will not sink
In July 2010 Project came to Halt Due to
Nature’s Furry
In Oct 2010 Project Geared Up
• Asphalt Specialist Dr Rainer Hart joined the project to construct
the race track
• A high polishing aggregate was required for preventing tire
damage on high speed
• The aggregate was exported from nearly 300 km far from
constructing site
Construction of Race track
The race track was built in five layers :
1st
layer : 25 cm granular sub base
2nd
layer : 20 cm wet macadam
3rd
layer : 9 cm asphalt base coarse ( to withstand ith heavy forces)
4th
layer : 5 cm binder coarse ( to endure the shearing forces from fast running cars)
5th
layer : 4 cm wear in coarse ( asphalt paved over a bind coarse to complete the track)
Construction of main grand stand
Foundation of main grand stand was completely water logged. So the first task in constructing it was to
pump that water.
After pumping water the structure of main grand stand was build from concrete and steel
The main grand stand has :
 A height of 30 m
 Length of 138 m
 56 trusses weighing 40 metric ton each
 40 m cantilever roof with 50000 square meters of
insulated aluminium sheeting
Aluminium sheets were chosen for roofing the main
grand stand due to its durability flexibility and
light weight.
50000 square meter aluminium sheets of 0.9 cm
thickness and 55 m length were used for roofing
the main grand stand.
150 km of fiber optical cables and 450 km of data and electric cables were spread beneath
the track connecting various hi-tech equipment to control room.
This includes :
 Real time video surveillance of race track
 Digital signalling system
 Electronic time keeping system
 50 race track cameras
 33 marshal post
 32 digiflags
Crash barriers of latest technology are employed in circuit to
ensure safety of the each car drivers as well as other people
present in the circuit.
Tec-Pro barriers replacing the tire barriers are employed in
the circuit
Nearly 2000 barriers along with 10 km guard rail 15 km FIA
fencing and 16 km U-drain has been provided in the track
PIT LANE & PIT
GARAGES
Get ready for virtual tour !!!
BUDDH INTERNATIONAL CIRCUIT: INDIA'S PREMIER RACING VENUE

More Related Content

What's hot

Industrial Training report on International convention center , Patna
 Industrial Training report on International convention center , Patna  Industrial Training report on International convention center , Patna
Industrial Training report on International convention center , Patna Aditya Divyadarshi
 
1. Case study report GIFT CITY Assignment 01.pdf
1. Case study report GIFT CITY Assignment 01.pdf1. Case study report GIFT CITY Assignment 01.pdf
1. Case study report GIFT CITY Assignment 01.pdfAnahatVikram3
 
Mlr convention centre, bangloor.
Mlr convention centre, bangloor.Mlr convention centre, bangloor.
Mlr convention centre, bangloor.self employer
 
Orion mall - Bangalore
Orion mall - BangaloreOrion mall - Bangalore
Orion mall - BangaloreMario Clement
 
Hyderabad international convention centre
Hyderabad international convention centreHyderabad international convention centre
Hyderabad international convention centrericha bihari
 
Hyderabad convention centre
Hyderabad convention centreHyderabad convention centre
Hyderabad convention centreappysuppy
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin towerSomya Gupta
 
Hyderabad International Convention Centre (HICC) Complete Plans
Hyderabad International Convention Centre (HICC) Complete PlansHyderabad International Convention Centre (HICC) Complete Plans
Hyderabad International Convention Centre (HICC) Complete PlansKARTIK KANKAR
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013engineeringwatch
 
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.simrandeo3
 
Shyam Thesis Report
Shyam Thesis ReportShyam Thesis Report
Shyam Thesis ReportShyam Singh
 
DLF Cyber city (integrated business district)
DLF Cyber city (integrated business district)  DLF Cyber city (integrated business district)
DLF Cyber city (integrated business district) Kapil Kaushik
 
Indian habitat centre (6)
Indian habitat centre (6)Indian habitat centre (6)
Indian habitat centre (6)tivar rose
 

What's hot (20)

Industrial Training report on International convention center , Patna
 Industrial Training report on International convention center , Patna  Industrial Training report on International convention center , Patna
Industrial Training report on International convention center , Patna
 
Yas Viceroy Hotel
Yas Viceroy HotelYas Viceroy Hotel
Yas Viceroy Hotel
 
1. Case study report GIFT CITY Assignment 01.pdf
1. Case study report GIFT CITY Assignment 01.pdf1. Case study report GIFT CITY Assignment 01.pdf
1. Case study report GIFT CITY Assignment 01.pdf
 
Ferrari world, abu dhabi
Ferrari world, abu dhabiFerrari world, abu dhabi
Ferrari world, abu dhabi
 
Mlr convention centre, bangloor.
Mlr convention centre, bangloor.Mlr convention centre, bangloor.
Mlr convention centre, bangloor.
 
Orion mall - Bangalore
Orion mall - BangaloreOrion mall - Bangalore
Orion mall - Bangalore
 
CASE STUDY F/o FINE ARTS JAMIA DELHI
CASE STUDY F/o FINE ARTS JAMIA DELHICASE STUDY F/o FINE ARTS JAMIA DELHI
CASE STUDY F/o FINE ARTS JAMIA DELHI
 
Hyderabad international convention centre
Hyderabad international convention centreHyderabad international convention centre
Hyderabad international convention centre
 
SPORTS COMPLEX,JAMIA MILLIA ISLAMAI, NEW DELHI
SPORTS COMPLEX,JAMIA MILLIA ISLAMAI, NEW DELHISPORTS COMPLEX,JAMIA MILLIA ISLAMAI, NEW DELHI
SPORTS COMPLEX,JAMIA MILLIA ISLAMAI, NEW DELHI
 
Indian Habitat Centre
Indian Habitat CentreIndian Habitat Centre
Indian Habitat Centre
 
Kohinoor square
Kohinoor squareKohinoor square
Kohinoor square
 
Hyderabad convention centre
Hyderabad convention centreHyderabad convention centre
Hyderabad convention centre
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
 
Yas Hotel, Abu Dhabi
Yas Hotel, Abu DhabiYas Hotel, Abu Dhabi
Yas Hotel, Abu Dhabi
 
Hyderabad International Convention Centre (HICC) Complete Plans
Hyderabad International Convention Centre (HICC) Complete PlansHyderabad International Convention Centre (HICC) Complete Plans
Hyderabad International Convention Centre (HICC) Complete Plans
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.
case study of World Trade Park, jaipur, rajasthan & Logix City Centre Noida.
 
Shyam Thesis Report
Shyam Thesis ReportShyam Thesis Report
Shyam Thesis Report
 
DLF Cyber city (integrated business district)
DLF Cyber city (integrated business district)  DLF Cyber city (integrated business district)
DLF Cyber city (integrated business district)
 
Indian habitat centre (6)
Indian habitat centre (6)Indian habitat centre (6)
Indian habitat centre (6)
 

Similar to BUDDH INTERNATIONAL CIRCUIT: INDIA'S PREMIER RACING VENUE

Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaductJayanta Sen
 
Presentation made during Key Note Addess
Presentation made during Key Note AddessPresentation made during Key Note Addess
Presentation made during Key Note AddessIEI GSC
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfKARTHIKGOUD64
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listColin Cai
 
Presentation : Future of Civil Engineering
Presentation : Future of Civil EngineeringPresentation : Future of Civil Engineering
Presentation : Future of Civil EngineeringIEI GSC
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationPierre HUBERT
 
Brief introduction of Beijing Yueji
Brief introduction of Beijing YuejiBrief introduction of Beijing Yueji
Brief introduction of Beijing YuejiSales Manager Paul
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Mohammed wahab
 

Similar to BUDDH INTERNATIONAL CIRCUIT: INDIA'S PREMIER RACING VENUE (20)

Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Presentation made during Key Note Addess
Presentation made during Key Note AddessPresentation made during Key Note Addess
Presentation made during Key Note Addess
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
Metro Work
Metro WorkMetro Work
Metro Work
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects list
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
Presentation : Future of Civil Engineering
Presentation : Future of Civil EngineeringPresentation : Future of Civil Engineering
Presentation : Future of Civil Engineering
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
 
Brief introduction of Beijing Yueji
Brief introduction of Beijing YuejiBrief introduction of Beijing Yueji
Brief introduction of Beijing Yueji
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 

BUDDH INTERNATIONAL CIRCUIT: INDIA'S PREMIER RACING VENUE

  • 1. BUDDH INTERNATIONAL CIRCUIT PRESENTED BY: CHANDRADARSHAN JAIN M.PHARM + MBA (P’CEUTICS) P007
  • 2. About Project India’s Racing Arena Jaypee International Circuit Location : Greater Noida ,UP, India Capacity : 1,20,000 Owner : Jaypee Group Operator : Jaypee Sports International Limited Start : 2007 Opened : Oct. 2011 Construction cost : INR 20 billion Architect : Hermann Tike Project Manager : Sameer Gaur Area : 2,500 acres
  • 3. Circuit : Fact Sheet • Length: 5.14km • Turns: 16 • Highest point of elevation: 14m • Width of the track: Between 18m – 20m • • Top speeds on the circuit: About • 320km/h, for an F1 car • Total seating capacity: About 120,000 • Distance from New Delhi: 40km approx. • Surface : Asphalt concrete with Graywacke
  • 4. Facts about Construction In constructing Circuit 4 million cubic ton of Earth were removed 325000 tons of asphalt were used 130000 metric cube of concrete were used 450 km of fiber optic cables were used
  • 5. Project Objectives  Bring the F1 closerto the fans and the indian masses  Make india a multi-sport country  Boost to the hotel and tourism industry  Lift to the country profile  Potential to generate huge revenues and employment opportunities
  • 6. Stake holder • IOA ( Indian Olympic Association ) • FIA (Federation Internationale de l’Automobile ) • FOA (Formula One Administration ) • JPSK Sports Pvt Ltd • Participating Teams • Fans
  • 7. Tilke GmbH of Aachen, Germany (Design partner) L & T (General contractor) Kimley-Horn & Associates (Transportation and urban planning ) Walter P Moore & Associates (Traffic planning and transportation engineering) Terracon Consultants (Geotechnical engineering & material quality) Carlson Brigance & Doering inc. (Surveying & infrastructure expertise) Miro Rivera Architects (Specific designs for structures & facilities) Siemens (Race control management system) Teracom + BSNL (Modems) Airtel (Communication) BHEL (Power) BEL (Surveillance equipment) ESPN-STAR (Telecasting)
  • 8. Request for proposalRequest for proposal Site Plan Project Planning
  • 9. • A main Grand Stand • 10 Temporary stands to seat more 100000 people • 3 story cantilever building with 41 garages • A race control room • A state art of media center to cater more than 600 media person • 18 fully furnished team buildings • Pit zones • A medical building • A challenging Circuit Site Specification
  • 10. Project Execution Plan 1. Acquisition of land 2. Construction of roads 3. Construction of first layer of circuit 4. Construction of stadium 5. Construction of pit zones 6. Construction of second layer of circuit 7. Construction of medical building 8. Construction of final layer of circuit
  • 12. Work process In October 2009 Earthwork was started to build the track Earth to a layer of 25 cm were compacted to a degree of 97% to make an embankment which will not sink
  • 13. In July 2010 Project came to Halt Due to Nature’s Furry
  • 14. In Oct 2010 Project Geared Up • Asphalt Specialist Dr Rainer Hart joined the project to construct the race track • A high polishing aggregate was required for preventing tire damage on high speed • The aggregate was exported from nearly 300 km far from constructing site
  • 15. Construction of Race track The race track was built in five layers : 1st layer : 25 cm granular sub base 2nd layer : 20 cm wet macadam 3rd layer : 9 cm asphalt base coarse ( to withstand ith heavy forces) 4th layer : 5 cm binder coarse ( to endure the shearing forces from fast running cars) 5th layer : 4 cm wear in coarse ( asphalt paved over a bind coarse to complete the track)
  • 16. Construction of main grand stand Foundation of main grand stand was completely water logged. So the first task in constructing it was to pump that water. After pumping water the structure of main grand stand was build from concrete and steel The main grand stand has :  A height of 30 m  Length of 138 m  56 trusses weighing 40 metric ton each  40 m cantilever roof with 50000 square meters of insulated aluminium sheeting
  • 17. Aluminium sheets were chosen for roofing the main grand stand due to its durability flexibility and light weight. 50000 square meter aluminium sheets of 0.9 cm thickness and 55 m length were used for roofing the main grand stand.
  • 18. 150 km of fiber optical cables and 450 km of data and electric cables were spread beneath the track connecting various hi-tech equipment to control room. This includes :  Real time video surveillance of race track  Digital signalling system  Electronic time keeping system  50 race track cameras  33 marshal post  32 digiflags
  • 19. Crash barriers of latest technology are employed in circuit to ensure safety of the each car drivers as well as other people present in the circuit. Tec-Pro barriers replacing the tire barriers are employed in the circuit Nearly 2000 barriers along with 10 km guard rail 15 km FIA fencing and 16 km U-drain has been provided in the track
  • 20.
  • 21. PIT LANE & PIT GARAGES
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. Get ready for virtual tour !!!