DATA AND REVIEW


            Essentials of Validation
            Project Management
            Part II
            William Garvey




                                                                 A
                                                                         ll pharmaceutical validation projects are labor and
                                                                         capital intensive, and each must be planned and man-
                                                                         aged carefully. Numerous tasks and activities must be
                                                                         identified early and then scheduled to support the
                                                                 project completion date. Stakeholders such as the Quality As-
                                                                 surance (QA) and Calibration–Metrology departments must
                                                                 be alerted to impending increased workloads under com-
                                                                 pressed time frames. Standard operating procedures (SOPs)
                                                                 and protocol formats must be developed, test equipment must
                                                                 be purchased or rented, and contractors must be evaluated
                                                                 and hired. Managers must decide whether the US Food and
                                                                 Drug Administration will participate in the design review
                                                                 process, and if so, what will be the agency’s exact involvement
                                                                 and participation. Considering the set of activities and pro-
                                                                 grams that require timely completion, pharmaceutical vali-
                                                                 dation projects must be carefully organized, managed, and
                                           PFIZER INC.




                                                                 monitored.
                                                                    Part I of this article covered the following four critical com-
                                                                 ponents common to all successful validation projects: design
In the second half of this two-part series, the                  review to ensure GMP compliance, project scope definition,
                                                                 project labor and cost estimating, and validation master plan
author suggests that to qualify and validate a
                                                                 development (1). Part II of this article introduces three ad-
pharmaceutical manufacturing facility, one must
                                                                 ditional programs, thereby providing validation project man-
coordinate protocol and SOP development,
                                                                 agers and participants the knowledge to plan and execute a
scheduling and implementation, turnover                          project properly, no matter how difficult or complex. This
package preparation, and the management and                      final article also examines activities that are initiated well after
resolution of deviations and discrepancies. In                   project inception and often continue to project completion
                                                                 and operations:
combination with the programs described in Part
                                                                 • protocol and SOP development, scheduling, and imple-
I, these activities will help deliver projects on
                                                                    mentation;
schedule, at estimated cost, and with quality
                                                                 • turnover package preparation;
assured.                                                         • deviation and discrepancy management.
                                                                    This article does not present a detailed discussion of
                                                                 system-specific validation technologies because preparation
            William Garvey is Validation Consultant at
                                                                 and field execution of protocols are usually highly customized
            Millipore Corporation (Billerica, MA).
                                                                 by system and are beyond the article’s scope. General guide-
            Phone: (781) 533-2407.
                                                                 lines that are useful for protocol development and execution
            Email: William_garvey@millipore.com
                                                                 are described, however.
            Submitted: Sept. 1, 2005. Accepted: Oct. 10, 2005.
                                                                    The concept of turnover packages (TOPs) as applied to

8
pharmaceutical projects also are discussed. TOPs for biophar-     mat has evolved in such a way that many once obscure fea-
maceutical projects were first described in the late 1980s and    tures are now standard from company to company and from
have evolved into systems used by many engineering firms          consultant to consultant. Although no regulatory expectations
and manufacturers. Finally, this article reviews the manage-      or requirements exist for protocol format, all protocols must
ment and resolution of protocol deviations. Deviations are        provide the documentation that proves the system or equip-
commonplace and tend to increase in frequency with increas-       ment was installed and operates according to design. Conse-
ing equipment complexity. These three programs, when com-         quently, the following guidelines and lessons learned are note-
bined with those described in the preceding article, can assist   worthy and should be considered during protocol
project managers to deliver a validated facility on time and at   development.
                                                                      Preparing protocol forms. By definition, validation is the es-
budget. Equally important, quality will be evident, the tran-
sition time to operation will be shortened, and regulatory ex-    tablishment of documented evidence that provides a high de-
pectations will be satisfied.                                     gree of assurance that a specific process will consistently pro-
                                                                  duce a product that meets its predetermined specifications
Protocol and SOP development,                                     and quality attributes (2). Emphasis has been added, because
scheduling, and implementation                                    nowhere in the regulations is it stated that the validation of
Protocols and SOPs are fundamental to all validation proj-        equipment and systems must be absolute. Absolute assurance
ects, and are required by all regulatory agencies for compli-     is impossible to attain and attempts to reach this level of con-
ant facilities. Protocol and SOP development usually makes        fidence come at high cost, both financial and labor related (3).
up 30–40% of all labor on a typical validation project, and       Applying this basic principle to protocol preparation, docu-
therefore, document quality and efficient preparation can-        ments should be prepared with the following considerations.
not be understated. In general, approved protocols and draft          For installation qualification (IQ), carefully manage the
SOPs must be delivered to coincide with certain milestones        breadth and depth of equipment and system inspection and
in the facility construction schedule, and therefore, careful     verification. For example, a typical piping and instrumenta-
planning and scheduling are essential.                            tion diagram (P&ID) for a sterilizer or water-for-injection
   One overriding principle that is central to all validation     (WFI) system literally contains hundreds of individual pieces
projects is that construction will not wait for protocol prepa-   of field-verifiable information. These pieces can range from
ration, review, and approval. The validation team must de-        the obvious (e.g., pump manufacturer and model number)
liver field-ready protocols that are suitable for implementa-     to less critical items (e.g., the size of electrical conduit) to the
tion when mechanical systems are installed and started. The       least important (e.g., type of covering on pipe insulation).
construction schedule must be interpreted and fully under-        Although confirming that the proper centrifugal pump is in-
stood. Late protocol delivery often means that verifications      stalled will ensure product quality, an exhaustive inspection
and inspections will become more complicated, or even             of pump subcomponents will not provide the same benefit.
missed entirely. System access is reduced or eliminated, and      It must be remembered that most pharmaceutical equipment
the personnel responsible for installation and start-up may       is supplied and installed by reputable vendors and contrac-
have left the site. Unfortunately, failure to deliver protocols   tors (4). Therefore, the opportunity to detect and correct er-
on time usually extends the validation schedule far beyond        rors occurs long before the item is shipped and installed. The
the established completion date, thus adding cost and creat-      tendency and temptation in validation is to over-specify and
ing conflicts for resources and personnel. Neither of these       over-inspect. This should be avoided because all inspections
outcomes are desirable, but they can be avoided with proper       must be meaningful and contribute to the high degree of as-
planning and management.                                          surance described previously.
   Very early in the project, protocol and SOP formats must           One way to manage IQ tests and verifications is through
be standardized and approved for use. In general, the SOP         the careful design of protocol forms and attachments. In the
format is usually well established at project inception; there-   early history of pharmaceutical validation, engineers and sci-
fore, companies rarely need to modify document templates          entists often inspected equipment and systems with design
for project purposes. Protocol format, however, is often a dif-   specifications in hand. Although this method always achieved
ferent matter. Historically, protocol content and arrangement     IQ objectives, validation personnel were frequently hindered
have varied widely within the industry, although some har-        by the large number of individual specifications contained
monization is now evident. Employing different contractors        in these design documents. Many specified features were not
on projects, each with different standard offerings, can lead     verifiable or were verifiable only with much difficulty and ex-
to format inconsistency. Many equipment vendors now sup-          pense (e.g., pump impeller material of construction).
ply very detailed protocols that differ considerably from those       To avoid this dilemma, protocols have evolved to contain
prepared in-house or by consultants. And within companies,        forms, similar to those in batch records, that force the compar-
preferences of individual departments and divisions often         ison between actual and design information. These forms sat-
cause protocol layout and content to deviate from the ac-         isfy regulatory requirements and provide a concise and organ-
cepted standard. Fortunately, however, industry protocol for-     ized document when implemented. In general, validation

                                                                                                                                    9
DATA AND REVIEW




Figure 1: Suggested form for installation qualification verification.   Figure 2: An example of an installation qualification verification form.
Companies should create a form for each major piece of equipment,       This form is for an air-handling unit chilled water supply and return.
instrument, or utility. In this example, the form applies to a large    Shading indicates that the specification is unavailable.
central station air-handling unit. Shading indicates that the
specification is unavailable.                                           be easily duplicated and customized for similar systems, and
                                                                        implementation is organized and expedited. Furthermore,
personnel should create a form (see Figures 1 and 2) for each           IQ acceptance criteria are easily stated and completely un-
major piece of equipment, instrument, or utility. Protocols for         ambiguous: Information contained in actual column corre-
complex systems (e.g., WFI) will contain dozens of forms.               sponds with information contained in specified column.
                                                                           Separating IQ, OQ, and PQ documents. Many companies com-
Major components requiring inspection can be identified on
drawings by the assignment of unique numbers (e.g., Trans-              bine IQ and operational qualification (OQ), or OQ and per-
mitter PIT-XXX, Fan EF-XXX, Pump P-XXX). Minor compo-                   formance qualification (PQ), into one document. Although
nents with an assigned tag number (e.g., hand valves, heating,          this approach is sometimes practical, it is not always advis-
ventilation, and air-conditioning volume dampers, drains) can           able for several reasons:
usually be omitted. Forms also may be correlated with critical          • It is far easier to manage document review and approval
components and subsystems identified in the system TOP.                     when each validation phase (i.e., IQ, OQ, and PQ) is de-
   The first column of each form (see Figures 1 and 2) lists at-            scribed in its own protocol. Combined protocols for com-
tributes that require inspection and verification. The next col-            plicated systems could be several hundred pages in length.
umn contains specifications and data. The third column,“Ac-             • IQ implementation can begin while the OQ is being reviewed
tual,” is used to record actual data. Contents of each cell in              and approved. Likewise, OQ can begin while the PQ proto-
columns 1 and 2 are determined by carefully reviewing design                col is under review. Remembering that construction will not
documents, specifications, and submittals. Again, the attrib-               wait for protocol review and approval, separating protocols
utes chosen for inspection are those that provide high assur-               will improve the likelihood that documents are available for
ance of delivery and installation according to design. If a spec-           implementation at critical construction milestones.
                                                                           Omitting QA approval of IQ. Validation is a systematic and mul-
ification is unavailable, the corresponding cell is shaded and
actual data are entered for record purposes during execution.           tidisciplinary undertaking comprising two predominating fields:
   By carefully designing forms in this manner, the breadth             engineering and science. Usually, IQ is the engineer’s responsi-
and depth of system inspection are controlled, protocols can            bility, and PQ is the scientist’s specialty. OQ serves as a transi-

10
DATA AND REVIEW
tion between IQ and PQ and often has both engineering and            with the facility construction schedule. This task is not easy.
scientific components. Because IQ is largely an engineering          Validation commonly deals with mechanically complete sys-
function, some companies omit the QA approval of IQ proto-           tems, while system construction proceeds in stages and by
cols entirely. Furthermore, acceptable OQ and PQ outcomes            building sections. Manufacturing facilities should be turned
will often reinforce that systems were installed as designed. The    over to the owner system by system, but this usually happens
regulatory risk associated with the exclusion of QA approval is      only on fast-track projects. The construction manager should
low and will often expedite IQ review and approval.                  be encouraged to turn over each system in the order needed
   Eliminating unnecessary or complicated tests. As described        by validation (e.g., supporting systems first, followed by
previously, all validation inspection and testing should be          process equipment). Rarely are individual systems and equip-
meaningful and demonstrate system or equipment compli-               ment installed in their entirety and started. Usually, a section
ance with an approved design. Labor- and resource-intensive          of a building is constructed, with each building trade being
inspections and tests that yield only a marginal increase in         scheduled to perform a specific job. For example, riggers will
quality assurance should be avoided. This can include tripli-        set a pump skid while pipefitters concurrently fabricate as-
cate testing of alarms and operational sequences when only           sociated piping. Then, this work is followed by electricians,
a single verification is sufficient. Other marginal tests include    who install conduit and pull conductors, followed by insula-
autoclave-jacket temperature uniformity (unless used for di-         tors and the instrumentation and calibration teams. The out-
agnostic purposes) and the operation of hot WFI systems at           come is that qualification, particularly IQ, is discontinuous
subprocess temperatures ( 70 C) for extended periods of              with many starts and stops. Although 60 hours may have been
time. In addition, do not risk damage to systems and equip-          allocated to implement a system’s IQ and OQ, the entire du-
ment to test an alarm. Running pumps dry to activate low-            ration could be weeks or months, depending on the construc-
pressure or low-flow alarms is not a good practice. Chang-           tion schedule (see Figure 3). It is the validation project man-
ing setpoints or equivalent methods can often simulate these         ager’s responsibility to carefully review the construction
conditions. Above all, avoid specifying inspections and tests        schedule to determine when systems will be mechanically
that are difficult to perform or implement, unless there is a        complete, started, and turned over to the owner. On the basis
regulatory requirement or other compelling, beneficial need.         of this review, a validation schedule can be prepared that may
   Preparing acceptance criteria. All acceptance criteria must       be synchronized with the construction schedule.
be based on system and equipment design, not arbitrarily as-            Foremost, validation deals with complete systems, not sec-
signed or determined. Designs are based on both quantita-            tions or portions, and the validation schedule must be
tive (numerical) and qualitative user requirements and in-           arranged as such. System completion dates must be projected
dustry standards. If a certain quality or output is expected         from the construction schedule and added to the validation
from an engineered system, the system is designed accord-            schedule. Project management software such as Microsoft
ingly. Common examples include:                                      Project (Microsoft Corporation, Redmond, WA) is commonly
• terminal high-efficiency particulate air (HEPA) filtration         used to develop and maintain this schedule, although other
    and high room air change rates, resulting in low airborne        software is available and equally useful. Dependencies be-
    particulate levels;                                              tween construction and validation must be created in the val-
• high recirculating velocity ( 5 ft/s) and temperature ( 80         idation schedule to allow for construction delays or improve-
     C), resulting in low bioburden in WFI systems;                  ments. When preparing a validation schedule from the
• full and segmented jackets on steam sterilizers to ensure          underlying construction schedule, the following points should
    and maintain chamber temperature uniformity.                     be considered:
   Acceptance criteria should be set equal to, and in some           • Target IQ approval and start of implementation to coin-
cases broader than, the underlying specification. It is a seri-         cide when system or equipment construction is approxi-
ous, but common, mistake to assign acceptance criteria to a             mately 25–50% complete. This timing will provide an ad-
system that exceeds the system’s capability or intent. Such an          equate opportunity to perform all required inspections
error will lead to test failures and excessive, wasteful testing.       while system access and construction personnel are still
Examples include particulate counting in compressed gas sys-            available. Consequently, the preparation of the IQ proto-
tems for which filters are nonexistent or particle-additive, and        col should begin 6–8 weeks before the target date to per-
using high population, high D-value bioindicators when low              mit comprehensive review and approval by all participants.
F0 sterilization cycles (liquids) are validated. When design spec-      Allow 5 days after system mechanical completion to com-
ifications may be unknown (e.g., for legacy systems), testing           plete the majority of IQ inspections.
for information and baseline development (for future valida-         • Schedule OQ approval and start of implementation to co-
tion needs) are the preferred acceptance criteria and avoid the         incide when systems or equipment are started for the first
problems and deviations described previously.                           time, often during precommissioning. Again, allow 6–8
   All successful validation projects are characterized by care-        weeks minimum for protocol review and approval to en-
ful planning and scheduling of project activities. Early on,            sure on-time availability. Except for minor, open items, IQ
validation deliverables must be identified and coordinated              should be nearly complete before OQ implementation is

                                                                                                                                 11
DATA AND REVIEW




Figure 3: A partial validation schedule integrated with a facility construction schedule.


   started. Historically, OQ protocols have always been the               price, it is unlikely that the construction team will delay fab-
   most difficult to prepare, so planning is imperative.                  rication, installation, or start-up because protocol develop-
• Schedule PQ approval and the start of implementation                    ment and approval are late. It is essential to deliver approved
   when commissioning is completed and the system is de-                  documents on time for implementation. Any delay results in
   livered and accepted. IQ and OQ should be substantially                opportunity lost, added expense, and a prolonged schedule.
   complete and any open items should not affect system per-                 Equally important is the development of forms for record-
   formance. These include common punchlist items such as                 ing data and information in IQ protocols. All protocols must
   valve tagging, labeling, insulation, and the completion of             be based on design information. Because specifications can
   as-built drawings. PQ for supporting systems such as WFI               be seemingly limitless for complex sanitary and process sys-
   and clean-steam systems should start as soon as possible be-           tems, the breadth and depth of inspection and testing must
   cause these systems provide inputs to critical process systems         be carefully managed. Acceptance criteria also must be based
   such as sterilizers and washers. Delays in supporting and an-          on design, not arbitrarily established when no specifications
   cillary systems will only delay the qualification and valida-          exist. Incorrect acceptance criteria often lead to test failures,
   tion of equipment these systems were designed to support.              unnecessary investigations, and needless expenditure of re-
• Concurrent with IQ protocol preparation, prepare corre-                 sources. Validation personnel should remember that valida-
   sponding system and equipment SOPs such as operation,                  tion provides a high degree of assurance—not absolute as-
   maintenance, and cleaning. SOPs should be available in                 surance—that a system was installed and operates according
   draft form at IQ start and verified and validated during               to design. Assurance approaching absolute comes at substan-
   OQ. Ideally, each SOP should be approved for use when                  tial cost, usually manifested by unnecessary, irrelevant test-
   PQ is completed to ensure that a fully compliant system is             ing, numerous deviations, and schedule delays.
   placed into routine service.
                                                                          Turnover package (TOP) preparation
   This section has addressed the preparation, scheduling, im-
plementation, and verification of protocols and SOPs. For an              TOPs for pharmaceutical and biopharmaceutical facilities is
average facility, it is common to have 30 or more qualified and           an optional, but important, program that was first described
validated systems, each with its own required documentation.              formally around 1987 (5), although the concept originated
Clearly, careful upfront planning is required to ensure that all          several years before then. In the late 1980s, the TOP program
validation activities are coordinated with the facility construc-         was instituted at several new facilities, mainly biopharma-
tion schedule. Because most construction projects are fixed               ceutical, by one large engineering firm specializing in biotech

12
DATA AND REVIEW
facility design, construction, and validation. Other compa-
nies quickly adopted the program. The objective then, as it
still remains today, is to shorten the duration required to com-
pletely validate a manufacturing facility. More specifically,
TOPs were designed to replace 90% of typical IQ inspec-
tions and verifications recorded in protocols, while still achiev-
ing the same degree of regulatory compliance. When a TOP
is properly planned and implemented, these objectives are
accomplished, with the added benefit of consolidated system
documentation available to the maintenance team at project
completion. In this respect, the TOP is the precursor for much
of the current industry effort to commission, rather than val-       Figure 4: Boundary between two validated systems: purified water
idate, pharmaceutical facilities today. Nonetheless, the TOP         system and fluidized-bed dryer make up air unit.
is still relevant, because it provides a definitive system base-
line for all validation activities, facility operations, and main-   piping, and so forth, included in one system but excluded
tenance requirements that follow.                                    from the other. The following suggestions may be useful when
    TOP planning and development should begin early in the           establishing system boundaries:
facility design process, preferably when P&IDs and airflow           • Identify logical groupings of equipment (usually clustered
diagrams (AFDs) are approved. The TOP is a prevalidation                on a single P&ID or AFD).
activity that continues until a system or piece of equipment         • Verify independent operation. One system operates inde-
is transferred to the owner. The construction manager must              pendently from an adjoining or supporting system (5).
be made aware of TOP requirements during the bidding                    It is the TOP coordinator’s responsibility, in consultation
process, not after, because the TOP may add to construction          with other project team members, to define system and equip-
cost and schedule. Before beginning a comprehensive and or-          ment boundaries. Once boundary drawings have been pre-
ganized TOP program, the following elements must be ad-              pared, copies are transmitted to the construction manager
dressed or compiled:                                                 for reference purposes and the validation team to support
• A TOP coordinator is needed. This person is often a de-            protocol preparation. The original highlighted drawing is in-
    greed engineer or equivalent.                                    serted into the corresponding TOP binder.
• System and equipment boundary drawings that demar-                    Concurrent with system boundary development, a list of
    cate system–system interactions must be prepared.                required forms, reports, certifications, drawings, and submit-
• TOP matrices that identify tests, inspections, and docu-           tals for TOP inclusion is prepared by the coordinator and for-
    mentation requirements for each validated system and             warded to responsible parties, including equipment vendors,
    piece of equipment must be prepared.                             Instrumentation–Calibration Departments, and the construc-
• Standardized, preapproved forms for documenting inspec-            tion manager and subcontractors. Project participants may
    tions and test results are required.                             be allowed to use their own standard documents (e.g., pres-
• All project stakeholders, particularly the construction man-       sure test forms, cleaning certifications, calibration data sheets),
    ager and subcontractors, must accept the program (5).            provided these forms supply the detail and authentications
    It is advisable that TOP implementation be integrated with       required by GMPs. All vendor and contractor standard forms
and managed as part of the validation program, if possible.          should be reviewed in advance, if possible. If these documents
There are several reasons for this. TOPs directly benefit the        are unacceptable, test forms that meet both project and GMP
validation team because each TOP contains system drawings,           requirements should be prepared and offered as replacements.
specifications, and manuals that are useful for protocol de-            After boundary drawings and the document list have been
velopment and execution. Furthermore, the TOP contributes            distributed, a matrix is prepared for each system or piece of
to overall facility GMP compliance. Most validation person-          equipment where TOP is required. A spreadsheet is commonly
nel have QA backgrounds, with the attendant attention to de-         used to organize the matrix. The left column of the spread-
tail and knowledge of GMP.                                           sheet is subdivided into the following areas and disciplines:
    A three-ring binder is allocated for each system or piece of     • general information (e.g., submittals, purchase orders, and
equipment scheduled for TOP development. Multiple binders               as-built drawings);
may be required for large or complex systems with many sub-          • equipment (e.g., pumps, motors, tanks, AHU, and fans);
systems and components. Then, system boundaries are es-              • piping;
tablished for each identified system (see Figure 4). Bound-          • electrical (e.g., motor control centers, transformers, and
aries are usually designated by highlighting system drawings            grounding);
(i.e., P&IDs and AFDs) to demarcate systems. Because utili-          • instrumentation (e.g., temperature, level, and pressure
ties interface with or support other process systems and equip-         transmitters);
ment, it is important to identify components, instruments,           • controls and programmable logic controllers (PLC) (e.g.,

                                                                                                                                    13
DATA AND REVIEW
                                                                                                          so that missing items and other
                                                                                                          important information can be
                                                                                                          determined and identified by
                                                                                                          simple review.
                                                                                                             After matrices have been pre-
                                                                                                          pared for all selected systems
                                                                                                          and equipment, each matrix
                                                                                                          must be approved by the con-
                                                                                                          struction manager, facility
                                                                                                          owner, TOP coordinator, and
                                                                                                          QA department. Approval
                                                                                                          demonstrates the importance
                                                                                                          of TOP as a partial replacement
                                                                                                          for IQ and helps reinforce the
                                                                                                          value of TOP for expediting
                                                                                                          project completion.
                                                                                                             Each matrix is placed into the
                                                                                                          corresponding system binder
                                                                                                          along with the boundary draw-
                                                                                                          ing. It is now the TOP coordi-
                                                                                                          nator’s responsibility to moni-
Figure 5: Typical turnover package (TOP) matrix (1 of 6 total pages).                                    tor construction progress and
                                                                                                         to collect and file the documents
   control valves, displays, PLC components, and input–out-             identified in each matrix. Some of these documents relate to
   put checkout);                                                       common inspections such as motor–pump alignment, pip-
• HVAC (e.g., air balance report and high-efficiency partic-            ing pressure testing, and air balancing. In many instances, the
   ulate air [HEPA] filter efficiency testing);                         TOP coordinator, along with the owner and a QA specialist,
• other (5).                                                            should witness field testing as performed. The product of this
   Each area and discipline is further subdivided by the docu-          testing (e.g., reports, certifications, and test forms) should be
ment type required to prove acceptable system installation and          reviewed, approved, and added to the TOP binder. It is im-
precommissioning. Using process piping as an example, doc-              portant to get construction manager agreement early that
uments to be assembled and filed with the TOP may include:              tests and verifications will be witnessed because this may cause
• material certification;                                               a momentary delay in the construction schedule while indi-
• piping pressure test;                                                 viduals are assembled to witness the test (5).
• line slope verification;                                                  In addition to test forms and certifications, equipment spec-
• cleaning verification.                                                ifications, manuals, factory reports, and so forth should be in-
Similar documents that provide proof of satisfactory instal-            cluded in each system TOP. Copies of red-lined drawings also
lation and operation also are identified for each of the disci-         should be added until redrawn as-built drawings become avail-
plines (e.g., general and equipment) described previously.              able. Because system TOPs may be consulted numerous times
   The matrix is completed by reviewing each boundary draw-             while construction is underway, control of incomplete binders
ing and then recording equipment numbers, instrument num-               is essential. Validation staff often refer to information (e.g.,
bers, or line numbers in the cells in the top row (one num-             manuals) in each TOP to prepare protocols and SOPs. Orig-
ber per cell) (see Figure 5). Only major, numbered items                inal documents and test reports must not be accidentally re-
should be recorded (e.g., pumps, tanks, control valves, fans,           moved and lost.
instruments, and filters). Hand-operated valves and other                   When all TOP matrix requirements have been satisfied for
minor components should be omitted. With the basic ma-                  a particular system or piece of equipment, the binders are au-
trix completed, the project team then must decide which doc-            dited for completeness. When properly planned and executed,
uments, certifications, and reports are required to substan-            the TOP binder is essentially complete when the system is
tiate satisfactory installation. Some document types will be            turned over to the owner for OQ and PQ. Individuals who ap-
required for some systems but not others. Ordinarily, cells in          proved the matrix initially approve the completed TOP. Once
the body of a matrix are crossed or shaded to indicate where            approved, it is common to prepare three copies of each binder—
a specific document is required. Later, as documents are re-            one for maintenance, one for operations, and a third for archive
ceived and added to the TOP, the corresponding cell can be              purposes. IQ completion then becomes an academic exercise
darkened or crossed again to indicate that the requirement              that is basically limited to certifying TOP approval and docu-
has been fulfilled. In this way, the matrix acts as a punchlist,        mentation of system SOPs. Finally, as systems undergo change

14
DATA AND REVIEW
                                                                                                                         Conclusion
control and are modified and altered, the corresponding TOP
is updated accordingly.                                                                                                  This article completes a two-part series about the essentials
                                                                                                                         of effective validation project management. Every project is
Deviation and discrepancy management                                                                                     unique in size and complexity, but common features are found
Deviations from protocol test methods and acceptance cri-                                                                in all projects. These include the requirement for design re-
teria are commonplace and inevitable when protocols are im-                                                              view to ensure compliance with good manufacturing prac-
plemented. As systems and equipment become more com-                                                                     tices, labor and cost estimating, and master plan develop-
plex, the number of deviations and discrepancies per system                                                              ment. Turnover packages in the style described in this article
tend to increase. In addition, deviations occur more frequently                                                          may be unfamiliar but should be considered for all projects,
as the breadth and depth of inspection and testing increases.                                                            regardless of size, duration, or urgency of completion. All
Generally, there are three sources of protocol deviations:                                                               projects use protocols to prove and document the “high de-
• Preliminary design specifications and drawings are used                                                                gree of assurance” required by regulatory authorities. Nonethe-
   for protocol preparation. Protocols are then not modified                                                             less, it is important that protocols be carefully designed to
   after designs have been finalized.                                                                                    manage the degree of inspection and testing, to avoid low
• The installed equipment, instrument, or utility does not                                                               value or needless verifications, and to arrive on time approved
   correspond to design drawings, specifications, and oper-                                                              and ready for implementation. Unfortunately, deviations are
   ational sequences.                                                                                                    often too familiar and probably unavoidable but can be less-
• Equipment and system installation and operation are cor-                                                               ened by design control, system commissioning, and careful
   rect, but a protocol error, usually design misinterpretation,                                                         document review.
   has occurred.                                                                                                            Successful validation project completion is never guaranteed.
   All deviations require careful management, evaluation, and                                                            All projects confront uncertainty, conflicts in schedule and lim-
scientific justification. If a system or piece of equipment ex-                                                          itation of resources. The concepts and details of validation are
hibits multiple deviations, one should question whether the                                                              sometimes misapplied and frequently misunderstood. Valida-
system is complete and suitable for validation. Within the                                                               tion is multidimensional. It requires special individuals who
past 15 years, protocols have begun to include pages for doc-                                                            are scientifically literate, mechanically oriented, and very prac-
umenting and explaining deviations as standard features. This                                                            tical. Validation is also very systematic. Failure of a precursor
has partly arisen because validation concepts today are much                                                             (e.g., installation qualification or operational qualification) often
better understood, particularly the relationship of design con-                                                          translates into suboptimal performance of the successor (e.g.,
formance to product quality and therapeutic response. One                                                                operational qualification and performance qualification).
fact is absolutely clear about system and equipment devia-                                                                  Considering that many validation projects are performed
tions: There should be no anticipated effect or alteration on                                                            once in a career or corporate life cycle, it is no surprise that
product quality beyond official or recognized standards (3).                                                             projects frequently extend beyond completion dates and bud-
   Deviations—be they protocol errors, test failures, or dis-                                                            geted costs. Properly planned and managed projects increase
crepancies from test methodology—must be fully described                                                                 the likelihood of success. Poor results usually are the outcome
on protocol deviation pages and in validation final reports. All                                                         of incomplete planning and inadequate execution. By follow-
remedial actions required to restore the equipment or system                                                             ing the guidelines and principles presented here, project goals
to an operational and compliant state should be fully explained.                                                         (e.g., completion on time, at budget, with quality) become
If properly implemented, commissioning will serve to reduce                                                              more attainable. Considering the cost to build new facilities
deviations to negligible levels. Only validation-ready systems                                                           and the added cost to validate them, well-managed valida-
will be available for inspection and testing. For multimillion-                                                          tion projects are self-compensating. Rework, operational in-
dollar projects with numerous systems and pieces of process                                                              efficiencies, and compliance concerns are reduced or elimi-
equipment, a centralized deviation management function may                                                               nated. Clearly, these benefits, both economic and regulatory,
be beneficial. Centralized management ensures that each de-                                                              should never be overlooked or minimized.
viation is processed uniformly and will remove the burden of
                                                                                                                         References
follow-up and closeout from the validation engineer and sci-
                                                                                                                           1. W. Garvey, “Essentials of Validation Project Management, Part I,”
entist. Furthermore, a central program is well suited for com-
                                                                                                                              Pharm. Technol. 29 (12), 68–76 (2005).
puterization, perhaps using any of the CAPA-style programs
                                                                                                                           2. US Food and Drug Administration,“Guideline on General Princi-
currently in use today.                                                                                                       ples of Process Validation,” (FDA, Rockville, MD, May 1987), p. 2.
   Beneficial, or “positive” deviations, also should be acknowl-                                                           3. W. Garvey,“Effective Validation Project Management,” oral presenta-
edged and explained. Positive deviations occur infrequently, and                                                              tion at Interphex Conference 2005, New York, NY, April 26–28 2005.
                                                                                                                           4. W. Garvey, “Integrated Validation Programs for Solid Dosage Fa-
are usually limited to improved materials of construction (e.g.,
                                                                                                                              cilities–Part 2,” Amer. Pharm. Rev. 2 (3), 17 (1999).
304L stainless steel specified, 316L delivered), expanded operat-
                                                                                                                           5. M. Chin, “TOP: A Rational Approach For Ensuring Proper Biophar-
ing ranges and additional, unspecified features. These deviations                                                             maceutical Plant Construction,” in Proceedings from PharmTech Con-
should at least be recognized as such, although there is rarely any                                                           ference ’87 (Aster Publishing Corporation, Eugene, OR, 1987). PT
need to perform an in-depth investigation or analysis.
                                                                                                                                                                                                                   RP0006EN00
        © Reprinted from PHARMACEUTICAL TECHNOLOGY, January 2006                                                                                                                Printed in U.S.A.
   Copyright Notice Copyright by Advanstar Communications Inc. Advanstar Communications Inc. retains all rights to this article. This article may only be viewed or printed (1) for personal use. User may not
    actively save any text or graphics/photos to local hard drives or duplicate this article in whole or in part, in any medium. Advanstar Communications Inc. home page is located at http://www.advanstar.com.

More Related Content

What's hot

Ppg Capabilities 2010
Ppg Capabilities 2010Ppg Capabilities 2010
Ppg Capabilities 2010JimShinkle
 
IT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGIT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGArul Nambi
 
Spc and msa brochure
Spc and msa brochureSpc and msa brochure
Spc and msa brochureLotterW
 
Ch2 pressman
Ch2   pressmanCh2   pressman
Ch2 pressmansuresh461
 
Bilbro james
Bilbro jamesBilbro james
Bilbro jamesNASAPMC
 
Configuration management-plan template
Configuration management-plan templateConfiguration management-plan template
Configuration management-plan templateVivek Srivastava
 
CMMI CONSULTING
CMMI CONSULTINGCMMI CONSULTING
CMMI CONSULTINGArul Nambi
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementNelson Piedra
 
Portfolio Management Processes Flow
Portfolio Management Processes FlowPortfolio Management Processes Flow
Portfolio Management Processes FlowRicardo Viana Vargas
 
St Final Hsiq Questcon Sales Presentation 092006
St Final Hsiq Questcon Sales Presentation 092006St Final Hsiq Questcon Sales Presentation 092006
St Final Hsiq Questcon Sales Presentation 092006anjuabel
 
Compare project management tool - FMS vs Redmine
Compare project management tool - FMS vs RedmineCompare project management tool - FMS vs Redmine
Compare project management tool - FMS vs Redminemekongsolution
 
E1013201
E1013201E1013201
E1013201nrb_6
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brianNASAPMC
 
Bli.it concepts-regarding-gamp-guide-en
Bli.it concepts-regarding-gamp-guide-enBli.it concepts-regarding-gamp-guide-en
Bli.it concepts-regarding-gamp-guide-enBLI.IT
 

What's hot (20)

Symons
SymonsSymons
Symons
 
Ppg Capabilities 2010
Ppg Capabilities 2010Ppg Capabilities 2010
Ppg Capabilities 2010
 
IT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGIT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTING
 
Spc and msa brochure
Spc and msa brochureSpc and msa brochure
Spc and msa brochure
 
Ch2 pressman
Ch2   pressmanCh2   pressman
Ch2 pressman
 
Bilbro james
Bilbro jamesBilbro james
Bilbro james
 
Saurabh_Mahajan_CV
Saurabh_Mahajan_CVSaurabh_Mahajan_CV
Saurabh_Mahajan_CV
 
Configuration management-plan template
Configuration management-plan templateConfiguration management-plan template
Configuration management-plan template
 
GPN Services
GPN ServicesGPN Services
GPN Services
 
CMMI CONSULTING
CMMI CONSULTINGCMMI CONSULTING
CMMI CONSULTING
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process Improvement
 
Ch27 (1)
Ch27 (1)Ch27 (1)
Ch27 (1)
 
Portfolio Management Processes Flow
Portfolio Management Processes FlowPortfolio Management Processes Flow
Portfolio Management Processes Flow
 
Project Assessment
Project AssessmentProject Assessment
Project Assessment
 
St Final Hsiq Questcon Sales Presentation 092006
St Final Hsiq Questcon Sales Presentation 092006St Final Hsiq Questcon Sales Presentation 092006
St Final Hsiq Questcon Sales Presentation 092006
 
Compare project management tool - FMS vs Redmine
Compare project management tool - FMS vs RedmineCompare project management tool - FMS vs Redmine
Compare project management tool - FMS vs Redmine
 
An industry perspective on qb d
An industry perspective on qb dAn industry perspective on qb d
An industry perspective on qb d
 
E1013201
E1013201E1013201
E1013201
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
 
Bli.it concepts-regarding-gamp-guide-en
Bli.it concepts-regarding-gamp-guide-enBli.it concepts-regarding-gamp-guide-en
Bli.it concepts-regarding-gamp-guide-en
 

Viewers also liked

social networking in education.
social networking in education.social networking in education.
social networking in education.guest416927
 
Hazley Biography
Hazley BiographyHazley Biography
Hazley Biographyahazley
 
Top 10 Things I Learned in Public Relations
Top 10 Things I Learned in Public RelationsTop 10 Things I Learned in Public Relations
Top 10 Things I Learned in Public Relationsbherrin3
 
The Near Future of CSS
The Near Future of CSSThe Near Future of CSS
The Near Future of CSSRachel Andrew
 
Classroom Management Tips for Kids and Adolescents
Classroom Management Tips for Kids and AdolescentsClassroom Management Tips for Kids and Adolescents
Classroom Management Tips for Kids and AdolescentsShelly Sanchez Terrell
 
Activism x Technology
Activism x TechnologyActivism x Technology
Activism x TechnologyWebVisions
 

Viewers also liked (6)

social networking in education.
social networking in education.social networking in education.
social networking in education.
 
Hazley Biography
Hazley BiographyHazley Biography
Hazley Biography
 
Top 10 Things I Learned in Public Relations
Top 10 Things I Learned in Public RelationsTop 10 Things I Learned in Public Relations
Top 10 Things I Learned in Public Relations
 
The Near Future of CSS
The Near Future of CSSThe Near Future of CSS
The Near Future of CSS
 
Classroom Management Tips for Kids and Adolescents
Classroom Management Tips for Kids and AdolescentsClassroom Management Tips for Kids and Adolescents
Classroom Management Tips for Kids and Adolescents
 
Activism x Technology
Activism x TechnologyActivism x Technology
Activism x Technology
 

Similar to Essentials of Validation Project Management - Part 2

Design Controls: Building Objective Evidence and Process Architecture to Mee...
Design Controls: Building Objective Evidence and Process Architecture  to Mee...Design Controls: Building Objective Evidence and Process Architecture  to Mee...
Design Controls: Building Objective Evidence and Process Architecture to Mee...April Bright
 
Master transfer.pdf
Master transfer.pdfMaster transfer.pdf
Master transfer.pdfApVirtuoso
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to considerOlivia Wilson
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsQUONTRASOLUTIONS
 
Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.Anthony Grenier
 
White Paper On Engineering Pmf
White Paper On Engineering PmfWhite Paper On Engineering Pmf
White Paper On Engineering Pmfguestb12736
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]Flu Plant
 
19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittalsatyaragha786
 
Module-4 PART-2&3.ppt
Module-4 PART-2&3.pptModule-4 PART-2&3.ppt
Module-4 PART-2&3.pptSharatNaik11
 
QAinDesignGuidance.pdf
QAinDesignGuidance.pdfQAinDesignGuidance.pdf
QAinDesignGuidance.pdfEnoOriarein
 
Project Initiation Document Linda Doll
Project Initiation Document Linda DollProject Initiation Document Linda Doll
Project Initiation Document Linda DollLinda Doll
 
Validation Master Plan Modern Pharmaceutics
Validation Master Plan Modern PharmaceuticsValidation Master Plan Modern Pharmaceutics
Validation Master Plan Modern PharmaceuticsMittalGandhi
 
Project management
Project managementProject management
Project managementNihal Ranjan
 
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩm
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩmPhụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩm
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩmCông ty Cổ phần Tư vấn Thiết kế GMP EU
 

Similar to Essentials of Validation Project Management - Part 2 (20)

Design Controls: Building Objective Evidence and Process Architecture to Mee...
Design Controls: Building Objective Evidence and Process Architecture  to Mee...Design Controls: Building Objective Evidence and Process Architecture  to Mee...
Design Controls: Building Objective Evidence and Process Architecture to Mee...
 
Master transfer.pdf
Master transfer.pdfMaster transfer.pdf
Master transfer.pdf
 
5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutions
 
Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.
 
White Paper On Engineering Pmf
White Paper On Engineering PmfWhite Paper On Engineering Pmf
White Paper On Engineering Pmf
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]
Transfer technologypharmaceuticalmanufacturingtrs961annex7[1]
 
19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal
 
ST&PFinalArticle
ST&PFinalArticleST&PFinalArticle
ST&PFinalArticle
 
Module-4 PART-2&3.ppt
Module-4 PART-2&3.pptModule-4 PART-2&3.ppt
Module-4 PART-2&3.ppt
 
QAinDesignGuidance.pdf
QAinDesignGuidance.pdfQAinDesignGuidance.pdf
QAinDesignGuidance.pdf
 
Project Initiation Document Linda Doll
Project Initiation Document Linda DollProject Initiation Document Linda Doll
Project Initiation Document Linda Doll
 
Validation Master Plan Modern Pharmaceutics
Validation Master Plan Modern PharmaceuticsValidation Master Plan Modern Pharmaceutics
Validation Master Plan Modern Pharmaceutics
 
ValidationMasterPlan
ValidationMasterPlanValidationMasterPlan
ValidationMasterPlan
 
Project management
Project managementProject management
Project management
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩm
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩmPhụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩm
Phụ lục 7. Hướng dẫn của WHO trong chuyển giao công nghệ sản xuất dược phẩm
 
Service Delivery & Support
Service Delivery & SupportService Delivery & Support
Service Delivery & Support
 
Qa & qc
Qa & qcQa & qc
Qa & qc
 

Recently uploaded

Pharmaceutical Marketting: Unit-5, Pricing
Pharmaceutical Marketting: Unit-5, PricingPharmaceutical Marketting: Unit-5, Pricing
Pharmaceutical Marketting: Unit-5, PricingArunagarwal328757
 
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
PULMONARY EDEMA AND  ITS  MANAGEMENT.pdfPULMONARY EDEMA AND  ITS  MANAGEMENT.pdf
PULMONARY EDEMA AND ITS MANAGEMENT.pdfDolisha Warbi
 
POST NATAL EXERCISES AND ITS IMPACT.pptx
POST NATAL EXERCISES AND ITS IMPACT.pptxPOST NATAL EXERCISES AND ITS IMPACT.pptx
POST NATAL EXERCISES AND ITS IMPACT.pptxvirengeeta
 
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranMusic Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranTara Rajendran
 
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...saminamagar
 
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
COVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptxCOVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptx
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptxBibekananda shah
 
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdf
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdfPULMONARY EMBOLISM AND ITS MANAGEMENTS.pdf
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdfDolisha Warbi
 
Measurement of Radiation and Dosimetric Procedure.pptx
Measurement of Radiation and Dosimetric Procedure.pptxMeasurement of Radiation and Dosimetric Procedure.pptx
Measurement of Radiation and Dosimetric Procedure.pptxDr. Dheeraj Kumar
 
See the 2,456 pharmacies on the National E-Pharmacy Platform
See the 2,456 pharmacies on the National E-Pharmacy PlatformSee the 2,456 pharmacies on the National E-Pharmacy Platform
See the 2,456 pharmacies on the National E-Pharmacy PlatformKweku Zurek
 
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfLippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfSreeja Cherukuru
 
Let's Talk About It: To Disclose or Not to Disclose?
Let's Talk About It: To Disclose or Not to Disclose?Let's Talk About It: To Disclose or Not to Disclose?
Let's Talk About It: To Disclose or Not to Disclose?bkling
 
Case Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxCase Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxNiranjan Chavan
 
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Report Back from SGO: What’s New in Uterine Cancer?.pptx
Report Back from SGO: What’s New in Uterine Cancer?.pptxReport Back from SGO: What’s New in Uterine Cancer?.pptx
Report Back from SGO: What’s New in Uterine Cancer?.pptxbkling
 
Biomechanics- Shoulder Joint!!!!!!!!!!!!
Biomechanics- Shoulder Joint!!!!!!!!!!!!Biomechanics- Shoulder Joint!!!!!!!!!!!!
Biomechanics- Shoulder Joint!!!!!!!!!!!!ibtesaam huma
 
The next social challenge to public health: the information environment.pptx
The next social challenge to public health:  the information environment.pptxThe next social challenge to public health:  the information environment.pptx
The next social challenge to public health: the information environment.pptxTina Purnat
 
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...Badalona Serveis Assistencials
 
Informed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxInformed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxSasikiranMarri
 
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...Wessex Health Partners
 

Recently uploaded (20)

Pharmaceutical Marketting: Unit-5, Pricing
Pharmaceutical Marketting: Unit-5, PricingPharmaceutical Marketting: Unit-5, Pricing
Pharmaceutical Marketting: Unit-5, Pricing
 
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
PULMONARY EDEMA AND  ITS  MANAGEMENT.pdfPULMONARY EDEMA AND  ITS  MANAGEMENT.pdf
PULMONARY EDEMA AND ITS MANAGEMENT.pdf
 
POST NATAL EXERCISES AND ITS IMPACT.pptx
POST NATAL EXERCISES AND ITS IMPACT.pptxPOST NATAL EXERCISES AND ITS IMPACT.pptx
POST NATAL EXERCISES AND ITS IMPACT.pptx
 
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara RajendranMusic Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
Music Therapy's Impact in Palliative Care| IAPCON2024| Dr. Tara Rajendran
 
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...
call girls in Dwarka Sector 21 Metro DELHI 🔝 >༒9540349809 🔝 genuine Escort Se...
 
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
COVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptxCOVID-19  (NOVEL CORONA  VIRUS DISEASE PANDEMIC ).pptx
COVID-19 (NOVEL CORONA VIRUS DISEASE PANDEMIC ).pptx
 
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdf
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdfPULMONARY EMBOLISM AND ITS MANAGEMENTS.pdf
PULMONARY EMBOLISM AND ITS MANAGEMENTS.pdf
 
Measurement of Radiation and Dosimetric Procedure.pptx
Measurement of Radiation and Dosimetric Procedure.pptxMeasurement of Radiation and Dosimetric Procedure.pptx
Measurement of Radiation and Dosimetric Procedure.pptx
 
See the 2,456 pharmacies on the National E-Pharmacy Platform
See the 2,456 pharmacies on the National E-Pharmacy PlatformSee the 2,456 pharmacies on the National E-Pharmacy Platform
See the 2,456 pharmacies on the National E-Pharmacy Platform
 
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdfLippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
Lippincott Microcards_ Microbiology Flash Cards-LWW (2015).pdf
 
Epilepsy
EpilepsyEpilepsy
Epilepsy
 
Let's Talk About It: To Disclose or Not to Disclose?
Let's Talk About It: To Disclose or Not to Disclose?Let's Talk About It: To Disclose or Not to Disclose?
Let's Talk About It: To Disclose or Not to Disclose?
 
Case Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptxCase Report Peripartum Cardiomyopathy.pptx
Case Report Peripartum Cardiomyopathy.pptx
 
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in paharganj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Report Back from SGO: What’s New in Uterine Cancer?.pptx
Report Back from SGO: What’s New in Uterine Cancer?.pptxReport Back from SGO: What’s New in Uterine Cancer?.pptx
Report Back from SGO: What’s New in Uterine Cancer?.pptx
 
Biomechanics- Shoulder Joint!!!!!!!!!!!!
Biomechanics- Shoulder Joint!!!!!!!!!!!!Biomechanics- Shoulder Joint!!!!!!!!!!!!
Biomechanics- Shoulder Joint!!!!!!!!!!!!
 
The next social challenge to public health: the information environment.pptx
The next social challenge to public health:  the information environment.pptxThe next social challenge to public health:  the information environment.pptx
The next social challenge to public health: the information environment.pptx
 
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...
Presentació "Real-Life VR Integration for Mild Cognitive Impairment Rehabilit...
 
Informed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptxInformed Consent Empowering Healthcare Decision-Making.pptx
Informed Consent Empowering Healthcare Decision-Making.pptx
 
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...
Wessex Health Partners Wessex Integrated Care, Population Health, Research & ...
 

Essentials of Validation Project Management - Part 2

  • 1. DATA AND REVIEW Essentials of Validation Project Management Part II William Garvey A ll pharmaceutical validation projects are labor and capital intensive, and each must be planned and man- aged carefully. Numerous tasks and activities must be identified early and then scheduled to support the project completion date. Stakeholders such as the Quality As- surance (QA) and Calibration–Metrology departments must be alerted to impending increased workloads under com- pressed time frames. Standard operating procedures (SOPs) and protocol formats must be developed, test equipment must be purchased or rented, and contractors must be evaluated and hired. Managers must decide whether the US Food and Drug Administration will participate in the design review process, and if so, what will be the agency’s exact involvement and participation. Considering the set of activities and pro- grams that require timely completion, pharmaceutical vali- dation projects must be carefully organized, managed, and PFIZER INC. monitored. Part I of this article covered the following four critical com- ponents common to all successful validation projects: design In the second half of this two-part series, the review to ensure GMP compliance, project scope definition, project labor and cost estimating, and validation master plan author suggests that to qualify and validate a development (1). Part II of this article introduces three ad- pharmaceutical manufacturing facility, one must ditional programs, thereby providing validation project man- coordinate protocol and SOP development, agers and participants the knowledge to plan and execute a scheduling and implementation, turnover project properly, no matter how difficult or complex. This package preparation, and the management and final article also examines activities that are initiated well after resolution of deviations and discrepancies. In project inception and often continue to project completion and operations: combination with the programs described in Part • protocol and SOP development, scheduling, and imple- I, these activities will help deliver projects on mentation; schedule, at estimated cost, and with quality • turnover package preparation; assured. • deviation and discrepancy management. This article does not present a detailed discussion of system-specific validation technologies because preparation William Garvey is Validation Consultant at and field execution of protocols are usually highly customized Millipore Corporation (Billerica, MA). by system and are beyond the article’s scope. General guide- Phone: (781) 533-2407. lines that are useful for protocol development and execution Email: William_garvey@millipore.com are described, however. Submitted: Sept. 1, 2005. Accepted: Oct. 10, 2005. The concept of turnover packages (TOPs) as applied to 8
  • 2. pharmaceutical projects also are discussed. TOPs for biophar- mat has evolved in such a way that many once obscure fea- maceutical projects were first described in the late 1980s and tures are now standard from company to company and from have evolved into systems used by many engineering firms consultant to consultant. Although no regulatory expectations and manufacturers. Finally, this article reviews the manage- or requirements exist for protocol format, all protocols must ment and resolution of protocol deviations. Deviations are provide the documentation that proves the system or equip- commonplace and tend to increase in frequency with increas- ment was installed and operates according to design. Conse- ing equipment complexity. These three programs, when com- quently, the following guidelines and lessons learned are note- bined with those described in the preceding article, can assist worthy and should be considered during protocol project managers to deliver a validated facility on time and at development. Preparing protocol forms. By definition, validation is the es- budget. Equally important, quality will be evident, the tran- sition time to operation will be shortened, and regulatory ex- tablishment of documented evidence that provides a high de- pectations will be satisfied. gree of assurance that a specific process will consistently pro- duce a product that meets its predetermined specifications Protocol and SOP development, and quality attributes (2). Emphasis has been added, because scheduling, and implementation nowhere in the regulations is it stated that the validation of Protocols and SOPs are fundamental to all validation proj- equipment and systems must be absolute. Absolute assurance ects, and are required by all regulatory agencies for compli- is impossible to attain and attempts to reach this level of con- ant facilities. Protocol and SOP development usually makes fidence come at high cost, both financial and labor related (3). up 30–40% of all labor on a typical validation project, and Applying this basic principle to protocol preparation, docu- therefore, document quality and efficient preparation can- ments should be prepared with the following considerations. not be understated. In general, approved protocols and draft For installation qualification (IQ), carefully manage the SOPs must be delivered to coincide with certain milestones breadth and depth of equipment and system inspection and in the facility construction schedule, and therefore, careful verification. For example, a typical piping and instrumenta- planning and scheduling are essential. tion diagram (P&ID) for a sterilizer or water-for-injection One overriding principle that is central to all validation (WFI) system literally contains hundreds of individual pieces projects is that construction will not wait for protocol prepa- of field-verifiable information. These pieces can range from ration, review, and approval. The validation team must de- the obvious (e.g., pump manufacturer and model number) liver field-ready protocols that are suitable for implementa- to less critical items (e.g., the size of electrical conduit) to the tion when mechanical systems are installed and started. The least important (e.g., type of covering on pipe insulation). construction schedule must be interpreted and fully under- Although confirming that the proper centrifugal pump is in- stood. Late protocol delivery often means that verifications stalled will ensure product quality, an exhaustive inspection and inspections will become more complicated, or even of pump subcomponents will not provide the same benefit. missed entirely. System access is reduced or eliminated, and It must be remembered that most pharmaceutical equipment the personnel responsible for installation and start-up may is supplied and installed by reputable vendors and contrac- have left the site. Unfortunately, failure to deliver protocols tors (4). Therefore, the opportunity to detect and correct er- on time usually extends the validation schedule far beyond rors occurs long before the item is shipped and installed. The the established completion date, thus adding cost and creat- tendency and temptation in validation is to over-specify and ing conflicts for resources and personnel. Neither of these over-inspect. This should be avoided because all inspections outcomes are desirable, but they can be avoided with proper must be meaningful and contribute to the high degree of as- planning and management. surance described previously. Very early in the project, protocol and SOP formats must One way to manage IQ tests and verifications is through be standardized and approved for use. In general, the SOP the careful design of protocol forms and attachments. In the format is usually well established at project inception; there- early history of pharmaceutical validation, engineers and sci- fore, companies rarely need to modify document templates entists often inspected equipment and systems with design for project purposes. Protocol format, however, is often a dif- specifications in hand. Although this method always achieved ferent matter. Historically, protocol content and arrangement IQ objectives, validation personnel were frequently hindered have varied widely within the industry, although some har- by the large number of individual specifications contained monization is now evident. Employing different contractors in these design documents. Many specified features were not on projects, each with different standard offerings, can lead verifiable or were verifiable only with much difficulty and ex- to format inconsistency. Many equipment vendors now sup- pense (e.g., pump impeller material of construction). ply very detailed protocols that differ considerably from those To avoid this dilemma, protocols have evolved to contain prepared in-house or by consultants. And within companies, forms, similar to those in batch records, that force the compar- preferences of individual departments and divisions often ison between actual and design information. These forms sat- cause protocol layout and content to deviate from the ac- isfy regulatory requirements and provide a concise and organ- cepted standard. Fortunately, however, industry protocol for- ized document when implemented. In general, validation 9
  • 3. DATA AND REVIEW Figure 1: Suggested form for installation qualification verification. Figure 2: An example of an installation qualification verification form. Companies should create a form for each major piece of equipment, This form is for an air-handling unit chilled water supply and return. instrument, or utility. In this example, the form applies to a large Shading indicates that the specification is unavailable. central station air-handling unit. Shading indicates that the specification is unavailable. be easily duplicated and customized for similar systems, and implementation is organized and expedited. Furthermore, personnel should create a form (see Figures 1 and 2) for each IQ acceptance criteria are easily stated and completely un- major piece of equipment, instrument, or utility. Protocols for ambiguous: Information contained in actual column corre- complex systems (e.g., WFI) will contain dozens of forms. sponds with information contained in specified column. Separating IQ, OQ, and PQ documents. Many companies com- Major components requiring inspection can be identified on drawings by the assignment of unique numbers (e.g., Trans- bine IQ and operational qualification (OQ), or OQ and per- mitter PIT-XXX, Fan EF-XXX, Pump P-XXX). Minor compo- formance qualification (PQ), into one document. Although nents with an assigned tag number (e.g., hand valves, heating, this approach is sometimes practical, it is not always advis- ventilation, and air-conditioning volume dampers, drains) can able for several reasons: usually be omitted. Forms also may be correlated with critical • It is far easier to manage document review and approval components and subsystems identified in the system TOP. when each validation phase (i.e., IQ, OQ, and PQ) is de- The first column of each form (see Figures 1 and 2) lists at- scribed in its own protocol. Combined protocols for com- tributes that require inspection and verification. The next col- plicated systems could be several hundred pages in length. umn contains specifications and data. The third column,“Ac- • IQ implementation can begin while the OQ is being reviewed tual,” is used to record actual data. Contents of each cell in and approved. Likewise, OQ can begin while the PQ proto- columns 1 and 2 are determined by carefully reviewing design col is under review. Remembering that construction will not documents, specifications, and submittals. Again, the attrib- wait for protocol review and approval, separating protocols utes chosen for inspection are those that provide high assur- will improve the likelihood that documents are available for ance of delivery and installation according to design. If a spec- implementation at critical construction milestones. Omitting QA approval of IQ. Validation is a systematic and mul- ification is unavailable, the corresponding cell is shaded and actual data are entered for record purposes during execution. tidisciplinary undertaking comprising two predominating fields: By carefully designing forms in this manner, the breadth engineering and science. Usually, IQ is the engineer’s responsi- and depth of system inspection are controlled, protocols can bility, and PQ is the scientist’s specialty. OQ serves as a transi- 10
  • 4. DATA AND REVIEW tion between IQ and PQ and often has both engineering and with the facility construction schedule. This task is not easy. scientific components. Because IQ is largely an engineering Validation commonly deals with mechanically complete sys- function, some companies omit the QA approval of IQ proto- tems, while system construction proceeds in stages and by cols entirely. Furthermore, acceptable OQ and PQ outcomes building sections. Manufacturing facilities should be turned will often reinforce that systems were installed as designed. The over to the owner system by system, but this usually happens regulatory risk associated with the exclusion of QA approval is only on fast-track projects. The construction manager should low and will often expedite IQ review and approval. be encouraged to turn over each system in the order needed Eliminating unnecessary or complicated tests. As described by validation (e.g., supporting systems first, followed by previously, all validation inspection and testing should be process equipment). Rarely are individual systems and equip- meaningful and demonstrate system or equipment compli- ment installed in their entirety and started. Usually, a section ance with an approved design. Labor- and resource-intensive of a building is constructed, with each building trade being inspections and tests that yield only a marginal increase in scheduled to perform a specific job. For example, riggers will quality assurance should be avoided. This can include tripli- set a pump skid while pipefitters concurrently fabricate as- cate testing of alarms and operational sequences when only sociated piping. Then, this work is followed by electricians, a single verification is sufficient. Other marginal tests include who install conduit and pull conductors, followed by insula- autoclave-jacket temperature uniformity (unless used for di- tors and the instrumentation and calibration teams. The out- agnostic purposes) and the operation of hot WFI systems at come is that qualification, particularly IQ, is discontinuous subprocess temperatures ( 70 C) for extended periods of with many starts and stops. Although 60 hours may have been time. In addition, do not risk damage to systems and equip- allocated to implement a system’s IQ and OQ, the entire du- ment to test an alarm. Running pumps dry to activate low- ration could be weeks or months, depending on the construc- pressure or low-flow alarms is not a good practice. Chang- tion schedule (see Figure 3). It is the validation project man- ing setpoints or equivalent methods can often simulate these ager’s responsibility to carefully review the construction conditions. Above all, avoid specifying inspections and tests schedule to determine when systems will be mechanically that are difficult to perform or implement, unless there is a complete, started, and turned over to the owner. On the basis regulatory requirement or other compelling, beneficial need. of this review, a validation schedule can be prepared that may Preparing acceptance criteria. All acceptance criteria must be synchronized with the construction schedule. be based on system and equipment design, not arbitrarily as- Foremost, validation deals with complete systems, not sec- signed or determined. Designs are based on both quantita- tions or portions, and the validation schedule must be tive (numerical) and qualitative user requirements and in- arranged as such. System completion dates must be projected dustry standards. If a certain quality or output is expected from the construction schedule and added to the validation from an engineered system, the system is designed accord- schedule. Project management software such as Microsoft ingly. Common examples include: Project (Microsoft Corporation, Redmond, WA) is commonly • terminal high-efficiency particulate air (HEPA) filtration used to develop and maintain this schedule, although other and high room air change rates, resulting in low airborne software is available and equally useful. Dependencies be- particulate levels; tween construction and validation must be created in the val- • high recirculating velocity ( 5 ft/s) and temperature ( 80 idation schedule to allow for construction delays or improve- C), resulting in low bioburden in WFI systems; ments. When preparing a validation schedule from the • full and segmented jackets on steam sterilizers to ensure underlying construction schedule, the following points should and maintain chamber temperature uniformity. be considered: Acceptance criteria should be set equal to, and in some • Target IQ approval and start of implementation to coin- cases broader than, the underlying specification. It is a seri- cide when system or equipment construction is approxi- ous, but common, mistake to assign acceptance criteria to a mately 25–50% complete. This timing will provide an ad- system that exceeds the system’s capability or intent. Such an equate opportunity to perform all required inspections error will lead to test failures and excessive, wasteful testing. while system access and construction personnel are still Examples include particulate counting in compressed gas sys- available. Consequently, the preparation of the IQ proto- tems for which filters are nonexistent or particle-additive, and col should begin 6–8 weeks before the target date to per- using high population, high D-value bioindicators when low mit comprehensive review and approval by all participants. F0 sterilization cycles (liquids) are validated. When design spec- Allow 5 days after system mechanical completion to com- ifications may be unknown (e.g., for legacy systems), testing plete the majority of IQ inspections. for information and baseline development (for future valida- • Schedule OQ approval and start of implementation to co- tion needs) are the preferred acceptance criteria and avoid the incide when systems or equipment are started for the first problems and deviations described previously. time, often during precommissioning. Again, allow 6–8 All successful validation projects are characterized by care- weeks minimum for protocol review and approval to en- ful planning and scheduling of project activities. Early on, sure on-time availability. Except for minor, open items, IQ validation deliverables must be identified and coordinated should be nearly complete before OQ implementation is 11
  • 5. DATA AND REVIEW Figure 3: A partial validation schedule integrated with a facility construction schedule. started. Historically, OQ protocols have always been the price, it is unlikely that the construction team will delay fab- most difficult to prepare, so planning is imperative. rication, installation, or start-up because protocol develop- • Schedule PQ approval and the start of implementation ment and approval are late. It is essential to deliver approved when commissioning is completed and the system is de- documents on time for implementation. Any delay results in livered and accepted. IQ and OQ should be substantially opportunity lost, added expense, and a prolonged schedule. complete and any open items should not affect system per- Equally important is the development of forms for record- formance. These include common punchlist items such as ing data and information in IQ protocols. All protocols must valve tagging, labeling, insulation, and the completion of be based on design information. Because specifications can as-built drawings. PQ for supporting systems such as WFI be seemingly limitless for complex sanitary and process sys- and clean-steam systems should start as soon as possible be- tems, the breadth and depth of inspection and testing must cause these systems provide inputs to critical process systems be carefully managed. Acceptance criteria also must be based such as sterilizers and washers. Delays in supporting and an- on design, not arbitrarily established when no specifications cillary systems will only delay the qualification and valida- exist. Incorrect acceptance criteria often lead to test failures, tion of equipment these systems were designed to support. unnecessary investigations, and needless expenditure of re- • Concurrent with IQ protocol preparation, prepare corre- sources. Validation personnel should remember that valida- sponding system and equipment SOPs such as operation, tion provides a high degree of assurance—not absolute as- maintenance, and cleaning. SOPs should be available in surance—that a system was installed and operates according draft form at IQ start and verified and validated during to design. Assurance approaching absolute comes at substan- OQ. Ideally, each SOP should be approved for use when tial cost, usually manifested by unnecessary, irrelevant test- PQ is completed to ensure that a fully compliant system is ing, numerous deviations, and schedule delays. placed into routine service. Turnover package (TOP) preparation This section has addressed the preparation, scheduling, im- plementation, and verification of protocols and SOPs. For an TOPs for pharmaceutical and biopharmaceutical facilities is average facility, it is common to have 30 or more qualified and an optional, but important, program that was first described validated systems, each with its own required documentation. formally around 1987 (5), although the concept originated Clearly, careful upfront planning is required to ensure that all several years before then. In the late 1980s, the TOP program validation activities are coordinated with the facility construc- was instituted at several new facilities, mainly biopharma- tion schedule. Because most construction projects are fixed ceutical, by one large engineering firm specializing in biotech 12
  • 6. DATA AND REVIEW facility design, construction, and validation. Other compa- nies quickly adopted the program. The objective then, as it still remains today, is to shorten the duration required to com- pletely validate a manufacturing facility. More specifically, TOPs were designed to replace 90% of typical IQ inspec- tions and verifications recorded in protocols, while still achiev- ing the same degree of regulatory compliance. When a TOP is properly planned and implemented, these objectives are accomplished, with the added benefit of consolidated system documentation available to the maintenance team at project completion. In this respect, the TOP is the precursor for much of the current industry effort to commission, rather than val- Figure 4: Boundary between two validated systems: purified water idate, pharmaceutical facilities today. Nonetheless, the TOP system and fluidized-bed dryer make up air unit. is still relevant, because it provides a definitive system base- line for all validation activities, facility operations, and main- piping, and so forth, included in one system but excluded tenance requirements that follow. from the other. The following suggestions may be useful when TOP planning and development should begin early in the establishing system boundaries: facility design process, preferably when P&IDs and airflow • Identify logical groupings of equipment (usually clustered diagrams (AFDs) are approved. The TOP is a prevalidation on a single P&ID or AFD). activity that continues until a system or piece of equipment • Verify independent operation. One system operates inde- is transferred to the owner. The construction manager must pendently from an adjoining or supporting system (5). be made aware of TOP requirements during the bidding It is the TOP coordinator’s responsibility, in consultation process, not after, because the TOP may add to construction with other project team members, to define system and equip- cost and schedule. Before beginning a comprehensive and or- ment boundaries. Once boundary drawings have been pre- ganized TOP program, the following elements must be ad- pared, copies are transmitted to the construction manager dressed or compiled: for reference purposes and the validation team to support • A TOP coordinator is needed. This person is often a de- protocol preparation. The original highlighted drawing is in- greed engineer or equivalent. serted into the corresponding TOP binder. • System and equipment boundary drawings that demar- Concurrent with system boundary development, a list of cate system–system interactions must be prepared. required forms, reports, certifications, drawings, and submit- • TOP matrices that identify tests, inspections, and docu- tals for TOP inclusion is prepared by the coordinator and for- mentation requirements for each validated system and warded to responsible parties, including equipment vendors, piece of equipment must be prepared. Instrumentation–Calibration Departments, and the construc- • Standardized, preapproved forms for documenting inspec- tion manager and subcontractors. Project participants may tions and test results are required. be allowed to use their own standard documents (e.g., pres- • All project stakeholders, particularly the construction man- sure test forms, cleaning certifications, calibration data sheets), ager and subcontractors, must accept the program (5). provided these forms supply the detail and authentications It is advisable that TOP implementation be integrated with required by GMPs. All vendor and contractor standard forms and managed as part of the validation program, if possible. should be reviewed in advance, if possible. If these documents There are several reasons for this. TOPs directly benefit the are unacceptable, test forms that meet both project and GMP validation team because each TOP contains system drawings, requirements should be prepared and offered as replacements. specifications, and manuals that are useful for protocol de- After boundary drawings and the document list have been velopment and execution. Furthermore, the TOP contributes distributed, a matrix is prepared for each system or piece of to overall facility GMP compliance. Most validation person- equipment where TOP is required. A spreadsheet is commonly nel have QA backgrounds, with the attendant attention to de- used to organize the matrix. The left column of the spread- tail and knowledge of GMP. sheet is subdivided into the following areas and disciplines: A three-ring binder is allocated for each system or piece of • general information (e.g., submittals, purchase orders, and equipment scheduled for TOP development. Multiple binders as-built drawings); may be required for large or complex systems with many sub- • equipment (e.g., pumps, motors, tanks, AHU, and fans); systems and components. Then, system boundaries are es- • piping; tablished for each identified system (see Figure 4). Bound- • electrical (e.g., motor control centers, transformers, and aries are usually designated by highlighting system drawings grounding); (i.e., P&IDs and AFDs) to demarcate systems. Because utili- • instrumentation (e.g., temperature, level, and pressure ties interface with or support other process systems and equip- transmitters); ment, it is important to identify components, instruments, • controls and programmable logic controllers (PLC) (e.g., 13
  • 7. DATA AND REVIEW so that missing items and other important information can be determined and identified by simple review. After matrices have been pre- pared for all selected systems and equipment, each matrix must be approved by the con- struction manager, facility owner, TOP coordinator, and QA department. Approval demonstrates the importance of TOP as a partial replacement for IQ and helps reinforce the value of TOP for expediting project completion. Each matrix is placed into the corresponding system binder along with the boundary draw- ing. It is now the TOP coordi- nator’s responsibility to moni- Figure 5: Typical turnover package (TOP) matrix (1 of 6 total pages). tor construction progress and to collect and file the documents control valves, displays, PLC components, and input–out- identified in each matrix. Some of these documents relate to put checkout); common inspections such as motor–pump alignment, pip- • HVAC (e.g., air balance report and high-efficiency partic- ing pressure testing, and air balancing. In many instances, the ulate air [HEPA] filter efficiency testing); TOP coordinator, along with the owner and a QA specialist, • other (5). should witness field testing as performed. The product of this Each area and discipline is further subdivided by the docu- testing (e.g., reports, certifications, and test forms) should be ment type required to prove acceptable system installation and reviewed, approved, and added to the TOP binder. It is im- precommissioning. Using process piping as an example, doc- portant to get construction manager agreement early that uments to be assembled and filed with the TOP may include: tests and verifications will be witnessed because this may cause • material certification; a momentary delay in the construction schedule while indi- • piping pressure test; viduals are assembled to witness the test (5). • line slope verification; In addition to test forms and certifications, equipment spec- • cleaning verification. ifications, manuals, factory reports, and so forth should be in- Similar documents that provide proof of satisfactory instal- cluded in each system TOP. Copies of red-lined drawings also lation and operation also are identified for each of the disci- should be added until redrawn as-built drawings become avail- plines (e.g., general and equipment) described previously. able. Because system TOPs may be consulted numerous times The matrix is completed by reviewing each boundary draw- while construction is underway, control of incomplete binders ing and then recording equipment numbers, instrument num- is essential. Validation staff often refer to information (e.g., bers, or line numbers in the cells in the top row (one num- manuals) in each TOP to prepare protocols and SOPs. Orig- ber per cell) (see Figure 5). Only major, numbered items inal documents and test reports must not be accidentally re- should be recorded (e.g., pumps, tanks, control valves, fans, moved and lost. instruments, and filters). Hand-operated valves and other When all TOP matrix requirements have been satisfied for minor components should be omitted. With the basic ma- a particular system or piece of equipment, the binders are au- trix completed, the project team then must decide which doc- dited for completeness. When properly planned and executed, uments, certifications, and reports are required to substan- the TOP binder is essentially complete when the system is tiate satisfactory installation. Some document types will be turned over to the owner for OQ and PQ. Individuals who ap- required for some systems but not others. Ordinarily, cells in proved the matrix initially approve the completed TOP. Once the body of a matrix are crossed or shaded to indicate where approved, it is common to prepare three copies of each binder— a specific document is required. Later, as documents are re- one for maintenance, one for operations, and a third for archive ceived and added to the TOP, the corresponding cell can be purposes. IQ completion then becomes an academic exercise darkened or crossed again to indicate that the requirement that is basically limited to certifying TOP approval and docu- has been fulfilled. In this way, the matrix acts as a punchlist, mentation of system SOPs. Finally, as systems undergo change 14
  • 8. DATA AND REVIEW Conclusion control and are modified and altered, the corresponding TOP is updated accordingly. This article completes a two-part series about the essentials of effective validation project management. Every project is Deviation and discrepancy management unique in size and complexity, but common features are found Deviations from protocol test methods and acceptance cri- in all projects. These include the requirement for design re- teria are commonplace and inevitable when protocols are im- view to ensure compliance with good manufacturing prac- plemented. As systems and equipment become more com- tices, labor and cost estimating, and master plan develop- plex, the number of deviations and discrepancies per system ment. Turnover packages in the style described in this article tend to increase. In addition, deviations occur more frequently may be unfamiliar but should be considered for all projects, as the breadth and depth of inspection and testing increases. regardless of size, duration, or urgency of completion. All Generally, there are three sources of protocol deviations: projects use protocols to prove and document the “high de- • Preliminary design specifications and drawings are used gree of assurance” required by regulatory authorities. Nonethe- for protocol preparation. Protocols are then not modified less, it is important that protocols be carefully designed to after designs have been finalized. manage the degree of inspection and testing, to avoid low • The installed equipment, instrument, or utility does not value or needless verifications, and to arrive on time approved correspond to design drawings, specifications, and oper- and ready for implementation. Unfortunately, deviations are ational sequences. often too familiar and probably unavoidable but can be less- • Equipment and system installation and operation are cor- ened by design control, system commissioning, and careful rect, but a protocol error, usually design misinterpretation, document review. has occurred. Successful validation project completion is never guaranteed. All deviations require careful management, evaluation, and All projects confront uncertainty, conflicts in schedule and lim- scientific justification. If a system or piece of equipment ex- itation of resources. The concepts and details of validation are hibits multiple deviations, one should question whether the sometimes misapplied and frequently misunderstood. Valida- system is complete and suitable for validation. Within the tion is multidimensional. It requires special individuals who past 15 years, protocols have begun to include pages for doc- are scientifically literate, mechanically oriented, and very prac- umenting and explaining deviations as standard features. This tical. Validation is also very systematic. Failure of a precursor has partly arisen because validation concepts today are much (e.g., installation qualification or operational qualification) often better understood, particularly the relationship of design con- translates into suboptimal performance of the successor (e.g., formance to product quality and therapeutic response. One operational qualification and performance qualification). fact is absolutely clear about system and equipment devia- Considering that many validation projects are performed tions: There should be no anticipated effect or alteration on once in a career or corporate life cycle, it is no surprise that product quality beyond official or recognized standards (3). projects frequently extend beyond completion dates and bud- Deviations—be they protocol errors, test failures, or dis- geted costs. Properly planned and managed projects increase crepancies from test methodology—must be fully described the likelihood of success. Poor results usually are the outcome on protocol deviation pages and in validation final reports. All of incomplete planning and inadequate execution. By follow- remedial actions required to restore the equipment or system ing the guidelines and principles presented here, project goals to an operational and compliant state should be fully explained. (e.g., completion on time, at budget, with quality) become If properly implemented, commissioning will serve to reduce more attainable. Considering the cost to build new facilities deviations to negligible levels. Only validation-ready systems and the added cost to validate them, well-managed valida- will be available for inspection and testing. For multimillion- tion projects are self-compensating. Rework, operational in- dollar projects with numerous systems and pieces of process efficiencies, and compliance concerns are reduced or elimi- equipment, a centralized deviation management function may nated. Clearly, these benefits, both economic and regulatory, be beneficial. Centralized management ensures that each de- should never be overlooked or minimized. viation is processed uniformly and will remove the burden of References follow-up and closeout from the validation engineer and sci- 1. W. Garvey, “Essentials of Validation Project Management, Part I,” entist. Furthermore, a central program is well suited for com- Pharm. Technol. 29 (12), 68–76 (2005). puterization, perhaps using any of the CAPA-style programs 2. US Food and Drug Administration,“Guideline on General Princi- currently in use today. ples of Process Validation,” (FDA, Rockville, MD, May 1987), p. 2. Beneficial, or “positive” deviations, also should be acknowl- 3. W. Garvey,“Effective Validation Project Management,” oral presenta- edged and explained. Positive deviations occur infrequently, and tion at Interphex Conference 2005, New York, NY, April 26–28 2005. 4. W. Garvey, “Integrated Validation Programs for Solid Dosage Fa- are usually limited to improved materials of construction (e.g., cilities–Part 2,” Amer. Pharm. Rev. 2 (3), 17 (1999). 304L stainless steel specified, 316L delivered), expanded operat- 5. M. Chin, “TOP: A Rational Approach For Ensuring Proper Biophar- ing ranges and additional, unspecified features. These deviations maceutical Plant Construction,” in Proceedings from PharmTech Con- should at least be recognized as such, although there is rarely any ference ’87 (Aster Publishing Corporation, Eugene, OR, 1987). PT need to perform an in-depth investigation or analysis. RP0006EN00 © Reprinted from PHARMACEUTICAL TECHNOLOGY, January 2006 Printed in U.S.A. Copyright Notice Copyright by Advanstar Communications Inc. Advanstar Communications Inc. retains all rights to this article. This article may only be viewed or printed (1) for personal use. User may not actively save any text or graphics/photos to local hard drives or duplicate this article in whole or in part, in any medium. Advanstar Communications Inc. home page is located at http://www.advanstar.com.