SlideShare a Scribd company logo
1 of 27
Download to read offline
South end of The I-35W Bridge North end of The I-35W Bridge
The I-35W Bridge The 10th Avenue Bridge
Long Section
Cross Section
(Deck Slab)
Slab Concrete
(t=3,8cm)
REALIZATION
ORIGINAL DESIGN
Additional Layer
of Concrete
Additional LOAD to
the Steel Structure
Central Barrier
Outside Railings
ADDITIONAL
STATIC LOADS:
+ 512,56 kg ≈
+ 6,1 %
•
•
•
•
•
•
•
•
•
•
•
ADDITIONAL STATIC LOADS
(at Construction Process):
+ 262.176,40 kg = 262 tons
“Thin” 1,25 cm
Gusset Plates
•
•
•
Cracks
DESIGN 1ST REFUBRISHMENT
The bridge, officially designated
"Bridge 9340", was designed by
Sverdrup & Parcel to 1961 by
standard specifications of AASHTO
(American Association of State
Highway Officials).
• Rennovation &
Reparation of
Structure (1970)
• Start annual
Inspection (1971)
1961
APPROVAL of MDOT
and US DOT*
Two options of design:
• 4-Truss System
• 2-Truss System (cheaper)
MDOT Approved the cheapest
one, using steel of fy 186 MPa
1963
OPERATIONAL
Structure was completed and
open to traffic, during an era
of large-scale projects to
build the Twin Cities freeway
system.
1967
CONSTRUCTION
The construction contracts, worth
in total more than $5.2 million at
the time, were done by HurCon Inc.
and Industrial Construction
Company.
1964
1970-1971
*MDOT = Minessota Departement of Transportation
US DOT = United State Departement of Transportation
DEFECTS
Some of “Gusset’s Plates” have
been corroded
1993
2nd REFUBRISHMENT
1970-1971
• Central Barriers
• Outside Railings
DEFECTS
• Cracking was discovered on steel
structure’s plates
• Structure was drilled out &
reinforced
• Monthly Inspection (6 months)
Early
2000’s
3rd REFUBRISHMENT
• Final Rennovation
• Four (4) lanes of road were
closed due to rennovation
2007
COLLAPSE ACCIDENT
The Accident occurred when
stockage of construction material
(sands, aggregates, cements)
placed alongside with heavy
equipments, without concern
July
2007
*MDOT = Minessota Departement of Transportation
US DOT = United State Departement of Transportation
August 1st 2007, 18:05
The Bridge Collapsed
•
•
•
•
Containment & Control :
• Continuous Maintenance
• Careful Handling of Material
UNSTABLE STRUCTURE
regarding to cracks on
steel plates
Deviation
Cracks on Steel Structures
Initiating Cause
Overload stockage
of material
Steel Structure Collapse
Preventive Safeguards
Structure Re-design & Rework
Loss Event
Structural Defects
(Cracks, etc.)
Mitigative Safeguards
Alternating equipment & sequence of
structure reparation work
Impacts
Safe Reparation Construction
Safely Operating Bridge
•
•
•
•
Bridge
Collapsed
OR
Fractured
Connections
Fractured
Beam
Fractured
Column / Pier
OR
OR
Overloaded
Structure
Excessive
Equipment
Placement
Excessive
Material
Stockage
AND
Design
Error
Lack of
Mainten-
-ance
Construction
Method Error
Defects of
Structure
•
•
•
Defects of Steel
Structure
Construction
Method Error
Design Error
Potential
Causes
Potential
Outcomes
BEFORE AFTER
Hazard:
Normal Operating Structural-
Defected Bridge
Structural
Failure
Traffic Jam
Human
Casualties
Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx
Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx
Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx
Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx

More Related Content

Similar to Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge ReportYvonne Chin
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)AISC/NSBA
 
Introduction to Bridges.pdf
Introduction to Bridges.pdfIntroduction to Bridges.pdf
Introduction to Bridges.pdfkarthik sampath
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015John Newquist
 
highway engineering study materials.pptx
highway engineering study materials.pptxhighway engineering study materials.pptx
highway engineering study materials.pptxkiruba684732
 
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)dgonano
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Buildingppt_master
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel liningMahesh Raj Bhatt
 
IBC ROUTE 139 June 9, 2006
IBC ROUTE 139 June 9, 2006IBC ROUTE 139 June 9, 2006
IBC ROUTE 139 June 9, 2006Manuj Ray
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2dgonano
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...mecocca5
 
CROSTI_IABMAS-ITALY
CROSTI_IABMAS-ITALYCROSTI_IABMAS-ITALY
CROSTI_IABMAS-ITALYStroNGER2012
 
Unit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxUnit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxRESHMAFEGADE
 

Similar to Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx (20)

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge Report
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Tony
TonyTony
Tony
 
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)
Pre-Fabricated Steel Bridges for Accelerated Bridge Construction (ABC)
 
Introduction to Bridges.pdf
Introduction to Bridges.pdfIntroduction to Bridges.pdf
Introduction to Bridges.pdf
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015
 
highway engineering study materials.pptx
highway engineering study materials.pptxhighway engineering study materials.pptx
highway engineering study materials.pptx
 
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
IBC ROUTE 139 June 9, 2006
IBC ROUTE 139 June 9, 2006IBC ROUTE 139 June 9, 2006
IBC ROUTE 139 June 9, 2006
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
 
CROSTI_IABMAS-ITALY
CROSTI_IABMAS-ITALYCROSTI_IABMAS-ITALY
CROSTI_IABMAS-ITALY
 
Unit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxUnit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptx
 
Rcc
RccRcc
Rcc
 
Special structure
Special structureSpecial structure
Special structure
 

Recently uploaded

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 

Recently uploaded (20)

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 

Tb Naufal Dzaki_2306195871_The I 35W Bridge Collapse.pptx

  • 1.
  • 2.
  • 3.
  • 4. South end of The I-35W Bridge North end of The I-35W Bridge The I-35W Bridge The 10th Avenue Bridge
  • 5.
  • 7. Cross Section (Deck Slab) Slab Concrete (t=3,8cm)
  • 9.
  • 10. Additional Layer of Concrete Additional LOAD to the Steel Structure
  • 11. Central Barrier Outside Railings ADDITIONAL STATIC LOADS: + 512,56 kg ≈ + 6,1 % • • • • • • • • • • • ADDITIONAL STATIC LOADS (at Construction Process): + 262.176,40 kg = 262 tons
  • 12. “Thin” 1,25 cm Gusset Plates • • • Cracks
  • 13.
  • 14. DESIGN 1ST REFUBRISHMENT The bridge, officially designated "Bridge 9340", was designed by Sverdrup & Parcel to 1961 by standard specifications of AASHTO (American Association of State Highway Officials). • Rennovation & Reparation of Structure (1970) • Start annual Inspection (1971) 1961 APPROVAL of MDOT and US DOT* Two options of design: • 4-Truss System • 2-Truss System (cheaper) MDOT Approved the cheapest one, using steel of fy 186 MPa 1963 OPERATIONAL Structure was completed and open to traffic, during an era of large-scale projects to build the Twin Cities freeway system. 1967 CONSTRUCTION The construction contracts, worth in total more than $5.2 million at the time, were done by HurCon Inc. and Industrial Construction Company. 1964 1970-1971 *MDOT = Minessota Departement of Transportation US DOT = United State Departement of Transportation DEFECTS Some of “Gusset’s Plates” have been corroded 1993 2nd REFUBRISHMENT 1970-1971 • Central Barriers • Outside Railings
  • 15. DEFECTS • Cracking was discovered on steel structure’s plates • Structure was drilled out & reinforced • Monthly Inspection (6 months) Early 2000’s 3rd REFUBRISHMENT • Final Rennovation • Four (4) lanes of road were closed due to rennovation 2007 COLLAPSE ACCIDENT The Accident occurred when stockage of construction material (sands, aggregates, cements) placed alongside with heavy equipments, without concern July 2007 *MDOT = Minessota Departement of Transportation US DOT = United State Departement of Transportation August 1st 2007, 18:05 The Bridge Collapsed
  • 17. Containment & Control : • Continuous Maintenance • Careful Handling of Material UNSTABLE STRUCTURE regarding to cracks on steel plates Deviation Cracks on Steel Structures Initiating Cause Overload stockage of material Steel Structure Collapse Preventive Safeguards Structure Re-design & Rework Loss Event Structural Defects (Cracks, etc.) Mitigative Safeguards Alternating equipment & sequence of structure reparation work Impacts Safe Reparation Construction Safely Operating Bridge
  • 18.
  • 21.
  • 23. Defects of Steel Structure Construction Method Error Design Error Potential Causes Potential Outcomes BEFORE AFTER Hazard: Normal Operating Structural- Defected Bridge Structural Failure Traffic Jam Human Casualties