2. โข Introduction
โข Fusiliers Way Strategic Opportunity - WDC
โข Masterplan and progress to date - WDC
โข Community Stadium โ underlying principles
โข Community Stadium โ design and use
โข Programme / Timetable
โข Questions & Answers session
Agenda
3. www.warwickdc.gov.uk | 26/01/2018
Aims
The strategic aims of the projects are:
1. To place shape to create a new Community Stadium at the
community heart for a new sustainable community
2. To deliver on a proposal for a Community Stadium in the Local
Plan
3. To provide the final major schemes of the Leisure Development
Programme
4. To help achieve other Council objectives, including:
a. Exemplar Net Zero development
b. Delivery of a Gypsy and Traveller site
c. Improve Bio-Diversity
d. Enhance ability to travel on foot/cycle
e. Improve traffic management of area
f. Affordable housing
g. Support local economy
www.warwickdc.gov.uk | 26/01/2018
8. www.warwickdc.gov.uk | 26/01/2018
2. โPlot 9โ
Opus has the agreement to
purchase this site.
www.warwickdc.gov.uk | 26/01/2018
Proposal is a business centre with remote
offices and meeting rooms to rent and โself-
storageโ to rear
9. www.warwickdc.gov.uk | 26/01/2018
3. Utilities installation
Aptus are due to install a gas governor and an
electrical sub-station for the site
www.warwickdc.gov.uk | 26/01/2018
10. www.warwickdc.gov.uk | 26/01/2018
WCC are bringing a proposal forward
that needs some of WDCโs land and
buildings.
www.warwickdc.gov.uk | 26/01/2018
4. Neighbourhood Centre
and Farmhouse
11. www.warwickdc.gov.uk | 26/01/2018
Warwick District Council owns the Grade
Two-listed farmhouse, outbuildings and
orchard. Options are being considered.
www.warwickdc.gov.uk | 26/01/2018
4. Farmhouse and Orchard
12. www.warwickdc.gov.uk | 26/01/2018
The Myton Path will be an important
link in the Districtโs sustainable travel
network.
www.warwickdc.gov.uk | 26/01/2018
6. The Myton Path
13. www.warwickdc.gov.uk | 26/01/2018
Existing track at Edmondscote needs
significant outlay soon to continue.
This location is better for access, parking
and use by schools/community groups.
Moving from Edmondscote allows that
site to become Queen Elizabeth II Park
and to open up riverside walks.
www.warwickdc.gov.uk | 26/01/2018
7. Athletics Facility
14. www.warwickdc.gov.uk | 26/01/2018
The existing athletics facility and
adjoining land will be turned into
Queen Elizabeth II Park โ an informal
and sustainable public open space
with riverside walks and ponds.
www.warwickdc.gov.uk | 26/01/2018
Queen Elizabeth II Park
15. www.warwickdc.gov.uk | 26/01/2018
Warwickshire County Council are planning a new
primary school for the Myton Gardens area.
Planning permission has been sought.
www.warwickdc.gov.uk | 26/01/2018
8. Myton Gardens Primary School
16. www.warwickdc.gov.uk | 26/01/2018
The Department for Education is planning
to construct a new Alternative Provision
School for the County on the site.
www.warwickdc.gov.uk | 26/01/2018
9. Talenton Academy, Warwick
(Alternative Provision Free School)
17. www.warwickdc.gov.uk | 26/01/2018
Evergreen School intend to provide a 6th
Form Centre (at A) to provide all ages of
education to pupils with special
educational needs. They will also install a
new entrance way to the site from
Fusiliers Way.
www.warwickdc.gov.uk | 26/01/2018
10. Evergreen School 6th Form and
New Entrance
26. www.warwickdc.gov.uk | 26/01/2018
Use 1 โ match day
Use 2 โ community use
Use 3 โ office use
Use 4 โ commercial hirings
www.warwickdc.gov.uk | 26/01/2018
Community Stadium โ different uses
1
3 4
2
30. Underlying principles
โข Leasehold of 150 years
โข Peppercorn rent
โข 4,000 capacity stadium
โข Sole ownership
โข All revenue to LFC
โข Managed by LFC
โข User agreements
โข Revenue stream
31. www.warwickdc.gov.uk | 26/01/2018
Community & Economic Impact
Deliver new community facilities โ schools, nursery, shops, sports/leisure facilities, community
centre
Enhancement to existing facilities โ secondary school inc 6th form, sports/leisure facility
LFC will be able to run more teams and increase participation for children; wider community
sports activities; increased health promotion related activities
Athletics clubs will also be able to do more especially schoolsโ participation
Significant volunteer input = significant social value
Development will increase opportunities for business growth and job creation
Another underlying principle is community and economic impact
32. www.warwickdc.gov.uk | 26/01/2018
The Community Stadium has been a strategic priority for the Council for a number of years.
โข The Stadium will anchor a new quarter based on education, sport and leisure
โข Housing and commercial enabling development
โข It will provide a new home for Leamington Football Club, and it will enable the Council to
build a Gypsy and Traveller site on the Clubโs existing ground
โข Pitch to be all weather to allow for community use
โข Other facilities to be accessible to the community
www.warwickdc.gov.uk | 26/01/2018
5. Community Stadium & Enabling Development
33. www.warwickdc.gov.uk | 26/01/2018
www.warwickdc.gov.uk | 26/01/2018
5. Community Stadium
โข LFC โ lost ground in late 1980s to development
โข LFC โ started again on Harbury Lane in 2000 from bottom of Football League
pyramid which has served them well but now it is problematic
โข Site is too distant for frequent community use which limits ability to generate
income from non match sources and in turn reduces ability of LFC to reinvest
โข LFC approached WDC to find another site
โข Have looked at all WDC holdings - nothing suitable
โข Identified Europa Way area
โข Identified site in Local Plan
โข Negotiated land purchase from WCC
โข Able to sell some land to pay for it
โข Bought Farmhouse
โข Have land to sell to enable the Stadium
โข Undertook procurement exercise to
gain private sector investment
34. www.warwickdc.gov.uk | 26/01/2018
Enabling Development proposing retail/commercial and residential development
(80 homes) around the stadium.
www.warwickdc.gov.uk | 26/01/2018
5. Enabling Development
โข 2 blocks of homes to the north of the
Stadium
โข 2 blocks at either end of the Stadium
with
โข Retail/commercial on ground floor
โข Residential on three floors above
โข 40% affordable housing
โข Minimises on site car parking overall
โข Car parking for stadium via Technology
Park; Myton Fields; Park and Ride
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Council purchased land as enabling development for Stadium.
Bought all land for ยฃ3.2m
Sold freehold to Opus for this site for ยฃ4m plus
Opus lease to Rybrook
Rybrook moved from Europa Way
Current access via Fusiliers Way which will open onto Gallows Hill in 2024
Opened in 2021
Heads of terms to be finalised
Most valuable/prominent site in the area
Double frontage
Needs a gateway building design and Net Zero DPD wise
Vistry are obliged to provide electricity and gas to the site as part of their occupation of land in the area
Aptus are acting as their agents
To be placed in the corner of โPlot 9โ
Will require Council to grant freehold for the land and service access
Final legal matters being reviewed
Installation to begin soon
The two Councils are discussing the deal to be struck on the transfer of land between the parties and other matters such as access and provision of car parking to deliver this scheme.
Building currently vacant
Other elements of the โdealโ may be more complex
Listing means structure and character (and orchard) must remain
Orchard to become Public Open Space
Offices are private space
A public space use such as public house/restaurant/craft shops might be preferred
Nursery may be built in grounds (not the orchard)
Will connect area to national cycleway network, St Nicholas Park, Warwick Town Centre, Rail Stations in Warwick and Leamington
Connects to Fusiliers Way and Myton Road cycleways
Project Managers appointed
Redesign underway
Provides rear entrance for Myton and Warwick Schools
This will reduce traffic on Myton Road
Access to athletics facility
Access to Technology Park
Matchday access to stadium from Technology Park car parks
The athletics clubs have been assured the new design will be โno detrimentโ from the current facility.
Specialist accredited project managers to be procured. Local standard facility
England Athletics advising on design
Negotiations with WCC underway
Field events important to clubs
Access from Fusiliers Way
Parking to be provided
Extended Pavilion for community use
Costs and design work needed
New athletics facility to open before current one closes
Connection to Riverside House project as bridge will allow cycling and footpath along river connecting Warwick, Leamington and countryside
ยฃ750k Contribution from Homes England
Opportunity to enhance Biodiversity
The project has missed the deadline for provision in time for September 2024
Now scheduled for at least September 2025
A temporary solution will need to be found
Regular liaison between Leisure Development Programme and County project team
Co-operation on ecology, transport surveys etc.
Access to playing fields to be provided for major athletics events (for teams to gather and so on)
School for pupils who are not engaging in main-stream schooling
Design has just been completed but is currently confidential
Planning application expected soon
Preferred contractor identified
Design issue with space for The Myton Path
DfE Project Manager joins liaison meetings with WCC and Leisure Development Programme
Also aiming for September 2025 opening
Security and privacy will be important features
Evergreen School is currently accessed through Brittain Lane - a residential area off Myton Road
New access will provide much better connectivity and reduce traffic on Myton Road
Evergreen School wish to provide education right through to eighteen years old with a 6th Form
Planning issue with playing fields (at C) yet to be resolved
Current status of project unknown โ it is believed to be behind the other two educational projects
Sixth Form Centre built
Propose a Retirement Village on Myton Rd
Modular Village to deal with RAAC issues
Relocate sports fields to rear of site after RAAC solved
Consolidates its sports/leisure activities adjacent to WDC athletics track and stadium
Achieve rear access off Fusiliers Way for pedestrians, cyclists and some vehicular traffic
Pitches to be reorientated
New pavilion planned
Achieve rear access off Fusiliers Way for pedestrians and cyclists
Council has failed to deliver a site in 50 years of existence
Council has examined over 40 sites without success
Previous call for sites has not led to sites being identified
LFC site best opportunity to deliver transit and/or permanent site
Could serve South Warwick area or even whole of County
Feasibility study to be undertaken
Site management is key to successful operation
LFC agree to offer site to WDC
Option to remove covenant in place
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC
Describe location of new units
Circa 50 k of Grant funding from FF
ยฃ30k funding from WDC