Unlock the full potential of Microsoft Project 2016 for efficient project planning with this in-depth presentation. Delve into the intricacies of this powerful software as seasoned project management expert, provides a step-by-step walkthrough of its features and functionalities. From creating project schedules and defining tasks to assigning resources and tracking progress, every aspect is meticulously covered. Whether you're a novice looking to grasp the basics or a seasoned professional seeking advanced techniques, this presentation caters to all skill levels. Gain valuable insights, tips, and best practices to streamline your project planning process and maximize productivity. Dive into the world of Microsoft Project 2016 now and take your project management skills to the next level!
Mastering Project Planning with Microsoft Project 2016.pptx
1. SOFTWARE TOOLS - I
UNDER GUIDANCE
PROF. XXXXXXX
PREPARED BY
NAEEM LASHKARWALA
XXXXXXXXXXX
ACADEMIC YEAR (2023-2025)
MASTER OF TECHNOLOGY (XXXXXXXXXXX)
MICROSOFT PROJECT
3. BRIEF DETAILS OF PRESENTATION
IN THIS PRESENTATION WE WILL COVER FOLLOWING TOPICS
I. INTRODUCTION TO THE SCREEN / USER
INTERFACE
II. INITIAL SETTINGS SHOULD BE DONE BEFORE
STARTING
III. DIFFERENT OPRATIONS IN PROJECT
IV. FINDING CRITICAL PATH
V. FORMATING OF BAR
VI. PROJECT SUMMARY TASK
VII. ALL ABOUT CALENDER IN MS PROJECT
VIII. ADDING NEW COLUMNS
IX. ADDING RESOURCES AND RESOURCE’S
SHEET
X. ASSIGNING OF RESOURCES
5. Task Mode Has
Two Types
1. Manually
2. auto
Task Name is The
Activity Name
Ex.., Excavation,
PCC,ETC..
Duration is
Duration or Taken
Time By Activity
or Task
Task Or Activity
Start Date
Task or Activity
Finish Date
Predecessors
Contains main 4
Constraints That
Can Decide That
Which Activities
Will Start
Together or
Parallel.
7. I. Open MS Project 2016.
II. Before Start Using it, You Need to Set Certain Things on it for that Go to the
file menu on the right hand side upper corner.
III. You Get to See The Last Tab of Options There. Click on it.
IV. A Dialogue box will Prompt Up as Shown in Image.
Go To File
Menu
Click on
‘Options’
Prompt
Dialogue Box
8.
9. GENERAL TAB
In General TAB You Need to Set the DATE & Time
Format From Any of The Options above but
Generally Use DD-MM-YY
10.
11. DISPLAY TAB
In Display Tab Set Currency and Calendar According
to Your Project and Country.
12.
13. SCHEDULE TAB
In Schedule TAB Set Your Work Timing and Change
Assignment Unit Percentage to Decimal and Change
Task Mode to Manually to Auto for Ease of Work.
14.
15. ADVANCED TAB
In Advanced TAB, There are Chances of make
mistakes in entries, to overcome that we can undo
them by CTRL+Z, But There an Option in this TAB by
which you can increase this Undo Level, By Default
it is 20. You Can Changed this Level According to
Your Work.
18. Task Mode Has
Two Types
1. Manually
2. auto
Task Name is The
Activity Name
Ex.., Excavation,
PCC,ETC..
Duration is
Duration or Taken
Time By Activity
or Task
Task Or Activity
Start Date
Task or Activity
Finish Date
Predecessors
Contains main 4
Constraints That
Can Decide That
Which Activities
Will Start
Together or
Parallel.
20. Find Critical Path
of Network By
Clicking on
Critical Path
Option
After Clicking
Critical Activity
Option You Can
See The Change
of Color of Chart
Blue to Red.
Task Bar
Format
Menu
Critical
Path
22. I. So You Can See That The Critical Path Has Been Highlighted by Red Bars.
II. Now If You Look at the Bars The Only Gives the Duration of Activity as Bar, No
Other Information Can be Obtained By Them.
III. To do we need to Format the Bars.
Format
Menu
Format Bar Style
23.
24. TEXT TAB
• Go to the Text TAB on the right side corner as
shown, you will have the things.
• You Need to change it. So in the Text TAB just
change & Write Followings.
1. Left-
’Start’
2. Right-
’Finish’
3. Top-
‘Name’
4. Bottom-
‘Duration’
28. Project Summary Task
• It is Used to Determine total Summary or total
duration of entire project.
• To do the same, select the whole project data
from last corner of Screen..
Format Menu
Upper Left
Corner
Chk. Mark to
Project Summary
Task Button
32. How to Create New Calendar
• First go to Project Menu and after go to Change
Working Time Then Create New Calendar.
• Default you get standard Calendar you can copy
standard calendar and after making copy of calendar.
Changes Make According to your Project and Time and
Days and Week-offs.
Project Menu
Change
Working Time
Create New
Calendar
33. Changed Calendar
Made By Project
Planner During
Project Planning
and Scheduling
Create New
Calendar By
Clicking Create
New Calendar.
34. Apply New Project Calendar
• It Won’t Work or Apply Your Calendar Until & Unless
you Changed it.
• To Do So..
Project Menu
Project
Information
Change
Calendar
35. Change New
Calendar made by
You According to
Your
Requirements.
After Changing
Calendar Press
OK.
36. Yearly Exception
• Let us take example of 15th August That Occurs as Holiday
in Calendar Every Year.
• So You don’t need to add exception every year manually.
• To do so 1st Create the Exception of Independence Day for
Current Year & Double Click on It.
Project Menu
Change
Working Time
Select The
Calendar
Exception
[Details]
38. Weekly Exception
• Let us Take any Company that has alternate Saturday or
Sunday holiday.
• To do So Create an Exception..
Project
Menu
Change
Working
Time
Select The
Calendar
Work Weeks
[Details]
40. Monthly Exception
• Let us Take any Company that has Saturday or Sunday
holiday.
• To do So Create an Exception..
Project
Menu
Change
Working
Time
Select The
Calendar
Exception
[Details]
43. New Columns (Responsibility)
• Let Us Take You want to Add Responsible Person For Any
Activity or Task You Have to Add New Column for it..
• To Do So
Add New Column
[Right Click]
Column Fields
Rename TEXT 1
[Responsibilities]
Custom
Attributes
Look Up Add Value
Add Description /
Name
47. Resource Sheet
• In Resource Sheet We Add All Resources Who’s Needed
During an Overall Project.
• To Do So
Task Menu
Gantt Bar
Chart
[Dropdown]
Resource
Sheet
51. Resource Assign
• Now We Assign The Resources According to Work Type
and Requirements.
• To Do So
Go To Gantt
Chart
Add
Resources
Column
Assign
Resources