SlideShare a Scribd company logo
1 of 11
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
December 10, 2020
Project Overview
Braddock District
Lake Accotink Dredging
DPWES Stormwater Planning Division
Agenda and Presenters
2
Lake Accotink Dredging
 Introductory Comments
 Supervisor Walkinshaw
 Background (Dredging History and Park Master Planning)
 Charles Smith (DPWES)
 Overview
 Team
 Schedule
 Other Work Going On in the Area
 Arcadis Presentation of Field Work Plan for
Winter 2020-2021
 Mike Wooden (Arcadis)
 Frank Graziano (WSSI)
 Wes Thomas (Arcadis)
 Akshay Kumar (Arcadis)
 Amanda Kohler (Arcadis)
 Questions and Answers
 Adam Wynn (Park Authority)
 Susan Larcher (Arcadis)
Photo by Thomas Kinder July 2019 – with permission of Save Lake Accotink
Photo from
Friends of
Lake
Accotink
Park
LAKE ACCOTINK CHANGES OVER TIME
Concrete Dam Constructed
Initial Lake Volume: 811 ac-ft
* 1960s Dredge
(Volume Uncertain)
*1985 Dredge
Dredge volume:
211,000 cy
*
?*
 Lake Accotink has been dredged three times
over the past 40 years.
 Previous dredging was completed in May
2008 ($10 Mil.) and removed 193,000 CY of
Sediment.
 An average of 20,000 CY of sediment is
deposited in the lake per year.
 The estimated average depth of the lake is 4
feet and will continue to decrease over time
without intervention.
2008 Dredge
Dredge volume:
193,000 cy
3(Presented at the BOS Budget Committee Presentation September 17, 2019)
LAKE ACCOTINK MASTER PLAN PUBLIC ENGAGEMENT PROCESS
• Master Plan began Spring 2016
• 5 Public Meetings/Workshops held with Community
• Facilities, programming & Usage
• Natural and Cultural Resources
• Trails
• Lake Management
• Natural resource studies were conducted to inventory critical plant
and wildlife species
• Lake Options shared with the public
• Community Online Questionnaire for Lake Options was circulated
• Comments received though website, email, and by phone
4(Presented at the BOS Budget Committee Presentation September 17, 2019)
LAKE ACCOTINK PUBLIC ENGAGEMENT PROCESS
Outcomes
• Results of public input
• 90% favored having a lake
• 65% in favor of retaining the existing footprint
• Save Lake Accotink, a non-profit organization, submitted a
petition in favor of dredging the lake and constructing a forebay.
• HOAs adjoining Lake Accotink support retaining the lake.
5(Presented at the BOS Budget Committee Presentation September 17, 2019)
DPWES Stormwater Planning Division
Project Overview
6
Lake Accotink Dredging
Dredging Order of Magnitude Cost Estimate
Initial Dredging Contingency Total
$24.5M $6.0M $30.5M
Annual Costs
Maintenance
Dredging
Dam
Maintenance
Total
$2.0M $0.013M $2.013M
30 Year Lifecycle Dam Repair & Upgrades
$4.7M in Year 30
Dredging Cost: $ 30,500,000
Annual Maintenance Cost: $2,013,000
30 Year Lifecycle Dam Repair: $4,700,000
Description
• Dredge estimated 350,000 cubic yards of sediment
to restore lake to average 8 ft depth.
• Pump sediment to Wakefield Park for dewatering
and disposal.
• Establish maintenance dredging program to
sustain the lake.
• Retain aesthetic and recreation value of the lake.
DPWES Stormwater Planning Division
Project Team
7
Lake Accotink Dredging
Department of Public
Works & Environmental
Services
Charles Smith
Project Manager – Stormwater
Justin Pistore
Project Manager - Stormwater
Aaron George
Lake Management – Stormwater
Jay Horstman
Construction Management –
Capital Facilities
Tom Richardson
Sanitary Sewer Coordination –
Wastewater
Fairfax County Park
Authority
Valerie Maislin
Project Manager – Planning and
Development
Adam Wynn
Lake Accotink Park Master Plan
Project Manager – Planning and
Development
Dan Grulke
Lake Accotink Manager – Park
Services
Chris Goldbecker
Lake Front Park Manager – Park
Services
Amber Stramel
Area 2 Manager – Park Operations
Braddock District
Supervisor
Marcia Pape
Supervisor’s Aide
Arcadis
Team
Mike Wooden
Project Manager
Fernando Pasquel
Project Director
Doug Sawyers
Account Manager
Akshay Kumar
Assistant Project Manager
Wesley Thomas
Dredging & Materials Management
Amanda Kohler
Conveyance & Dewatering System
Shannon Dunn
Sediment Characterization & Water Quality
Susan Larcher
Public Outreach
Frank Graziano (WSSI)
Survey & Permitting
ECS
Geotechnical Analysis
Key Stakeholder
Groups
Friends of Lake Accotink Park
Friends of Accotink Creek
Save Lake Accotink
Homeowner & Civic
Associations
Lake Accotink Dredging
Critical Players
DPWES Stormwater Planning Division
What To Expect
8
Lake Accotink Dredging
 Data collection and survey to design
dredge and determine where dredge
operations could be done
 Site preparation in Lake Accotink &
Wakefield Parks
 Dredging, pipeline and spoils processing
operations
 Daily commercial truck traffic north of
Braddock Road to remove sediment
 Light vehicle traffic daily in Lake Accotink
Park to support dredging and pipeline
operations
 Restoration and monitoring
DPWES Stormwater Planning Division
Project Schedule
9
Lake Accotink Dredging
 Data collection and survey – April 2021
 Alternatives Analysis – July 2021
 Concept Design and Value Engineering
Study – April 2022
 Final Design and Permitting – March
2023
 Begin Dredging – March 2023
 Complete Dredging – November 2025
 Post Construction Monitoring – October
2028
Lake Accotink dredging operations June 21,
2006 – Photo by Fairfax County DPWES
DPWES Stormwater Planning Division
Things Going On Around Lake Accotink & Wakefield Park
10
Lake Accotink Dredging
Arcadis field work for Lake
Accotink Dredging Project
Accotink Creek at
Wakefield Park stream
restoration
VDOT survey work for Braddock
Road Corridor Project
Park Authority trail work near
Danbury Forest
Washington Gas utility
work near Rolling Road
Audrey Moore RecCenter
renovation
DPWES Stormwater Planning Division
Discussion
Discussion & Questions
11
Native mussels below Lake Accotink dam –
Photo by Friends of Accotink Creek
For Additional Information, to Comment or Sign up for Email
Updates, Please Visit the Project Web Page:
https://www.fairfaxcounty.gov/publicworks/lake-accotink-
dredging
Lake Accotink Dredging
Community stewardship – Photo by Friends
of Lake Accotink Park
Cardboard boat regatta – Photo
by Friends of Lake Accotink Park
Mallard ducks – Photo by Fairfax
County Park Authority

More Related Content

What's hot

Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationFairfax County
 
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...San Diego County Water Authority
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Recycling and Resource Management Division
 
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02FridaKa
 
Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Bob MacMillan
 
C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_finalpublicinvolvement
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewSteve Williams
 
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...Recycling and Resource Management Division
 
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...Deltares
 
Building a Sustainable Infrastructure at NASA
Building a Sustainable Infrastructure at NASABuilding a Sustainable Infrastructure at NASA
Building a Sustainable Infrastructure at NASAJenna Riemenschneider
 
Karen Edelvang-list of projects
Karen Edelvang-list of projectsKaren Edelvang-list of projects
Karen Edelvang-list of projectsKaren Edelvang
 
Fall 2015--DEC Upated on Spring Creek Restoration Project
Fall 2015--DEC Upated on Spring Creek Restoration ProjectFall 2015--DEC Upated on Spring Creek Restoration Project
Fall 2015--DEC Upated on Spring Creek Restoration Projectecowatchers
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedJose Calderon Garcia
 
GIS for Infrastructure Management
GIS for Infrastructure ManagementGIS for Infrastructure Management
GIS for Infrastructure ManagementDavid Puckett
 

What's hot (20)

2016 resume
2016 resume2016 resume
2016 resume
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Gude landfill remediation 161019
Gude landfill remediation 161019Gude landfill remediation 161019
Gude landfill remediation 161019
 
Gude Landfill Remediation update
Gude Landfill Remediation updateGude Landfill Remediation update
Gude Landfill Remediation update
 
RAB NASA Update
RAB NASA UpdateRAB NASA Update
RAB NASA Update
 
Storm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master PlansStorm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master Plans
 
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
Part 2: Bay-Delta Conservation Plan Implementation Process and Portfolio Alte...
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
 
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02
Afsismidtermreviewconsortiumpresentationv2 110203031825-phpapp02
 
Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3
 
C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_final
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year Review
 
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
 
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
DSD-SEA 2018 Software Application in Integrated Water Resources Management in...
 
Building a Sustainable Infrastructure at NASA
Building a Sustainable Infrastructure at NASABuilding a Sustainable Infrastructure at NASA
Building a Sustainable Infrastructure at NASA
 
Bear River Development Project
Bear River Development ProjectBear River Development Project
Bear River Development Project
 
Karen Edelvang-list of projects
Karen Edelvang-list of projectsKaren Edelvang-list of projects
Karen Edelvang-list of projects
 
Fall 2015--DEC Upated on Spring Creek Restoration Project
Fall 2015--DEC Upated on Spring Creek Restoration ProjectFall 2015--DEC Upated on Spring Creek Restoration Project
Fall 2015--DEC Upated on Spring Creek Restoration Project
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimized
 
GIS for Infrastructure Management
GIS for Infrastructure ManagementGIS for Infrastructure Management
GIS for Infrastructure Management
 

Similar to Lake Accotink Dredging Public Meeting Presentation December 2020

Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationFairfax County
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfecowatchers
 
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectAccotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Fairfax County
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
 
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...Graeme Donaldson
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitFairfax County
 
Rabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectRabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectFairfax County
 
Rocky Run Tributary at Dulles Access Road Stream Restoration Project
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectRocky Run Tributary at Dulles Access Road Stream Restoration Project
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectFairfax County
 
Stormwater Presentation to Friends of Lake Accotink Park 12-2019
Stormwater Presentation to Friends of Lake Accotink Park 12-2019Stormwater Presentation to Friends of Lake Accotink Park 12-2019
Stormwater Presentation to Friends of Lake Accotink Park 12-2019Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
 
Pohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream RestorationPohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfecowatchers
 
CLP RFQ Draft ESE 401 Draft
CLP RFQ Draft ESE 401 DraftCLP RFQ Draft ESE 401 Draft
CLP RFQ Draft ESE 401 DraftJustin Vitkus
 
Wakefield Park South Stream Restoration
Wakefield Park South Stream RestorationWakefield Park South Stream Restoration
Wakefield Park South Stream RestorationFairfax County
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond ImprovementFairfax County
 
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Fairfax County
 

Similar to Lake Accotink Dredging Public Meeting Presentation December 2020 (20)

Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream Restoration
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
 
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectAccotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration Project
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021Snakeden Branch at Lake Audubon January 2021
Snakeden Branch at Lake Audubon January 2021
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality Retrofit
 
Rabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration ProjectRabbit Branch Tributary Restoration Project
Rabbit Branch Tributary Restoration Project
 
Rocky Run Tributary at Dulles Access Road Stream Restoration Project
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectRocky Run Tributary at Dulles Access Road Stream Restoration Project
Rocky Run Tributary at Dulles Access Road Stream Restoration Project
 
Stormwater Presentation to Friends of Lake Accotink Park 12-2019
Stormwater Presentation to Friends of Lake Accotink Park 12-2019Stormwater Presentation to Friends of Lake Accotink Park 12-2019
Stormwater Presentation to Friends of Lake Accotink Park 12-2019
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration Project
 
Pohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream RestorationPohick Creek Tributary at Greentree Village Park Stream Restoration
Pohick Creek Tributary at Greentree Village Park Stream Restoration
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdf
 
CLP RFQ Draft ESE 401 Draft
CLP RFQ Draft ESE 401 DraftCLP RFQ Draft ESE 401 Draft
CLP RFQ Draft ESE 401 Draft
 
Wakefield Park South Stream Restoration
Wakefield Park South Stream RestorationWakefield Park South Stream Restoration
Wakefield Park South Stream Restoration
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Lake Accotink Dredging Public Meeting Presentation December 2020

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! December 10, 2020 Project Overview Braddock District Lake Accotink Dredging
  • 2. DPWES Stormwater Planning Division Agenda and Presenters 2 Lake Accotink Dredging  Introductory Comments  Supervisor Walkinshaw  Background (Dredging History and Park Master Planning)  Charles Smith (DPWES)  Overview  Team  Schedule  Other Work Going On in the Area  Arcadis Presentation of Field Work Plan for Winter 2020-2021  Mike Wooden (Arcadis)  Frank Graziano (WSSI)  Wes Thomas (Arcadis)  Akshay Kumar (Arcadis)  Amanda Kohler (Arcadis)  Questions and Answers  Adam Wynn (Park Authority)  Susan Larcher (Arcadis) Photo by Thomas Kinder July 2019 – with permission of Save Lake Accotink Photo from Friends of Lake Accotink Park
  • 3. LAKE ACCOTINK CHANGES OVER TIME Concrete Dam Constructed Initial Lake Volume: 811 ac-ft * 1960s Dredge (Volume Uncertain) *1985 Dredge Dredge volume: 211,000 cy * ?*  Lake Accotink has been dredged three times over the past 40 years.  Previous dredging was completed in May 2008 ($10 Mil.) and removed 193,000 CY of Sediment.  An average of 20,000 CY of sediment is deposited in the lake per year.  The estimated average depth of the lake is 4 feet and will continue to decrease over time without intervention. 2008 Dredge Dredge volume: 193,000 cy 3(Presented at the BOS Budget Committee Presentation September 17, 2019)
  • 4. LAKE ACCOTINK MASTER PLAN PUBLIC ENGAGEMENT PROCESS • Master Plan began Spring 2016 • 5 Public Meetings/Workshops held with Community • Facilities, programming & Usage • Natural and Cultural Resources • Trails • Lake Management • Natural resource studies were conducted to inventory critical plant and wildlife species • Lake Options shared with the public • Community Online Questionnaire for Lake Options was circulated • Comments received though website, email, and by phone 4(Presented at the BOS Budget Committee Presentation September 17, 2019)
  • 5. LAKE ACCOTINK PUBLIC ENGAGEMENT PROCESS Outcomes • Results of public input • 90% favored having a lake • 65% in favor of retaining the existing footprint • Save Lake Accotink, a non-profit organization, submitted a petition in favor of dredging the lake and constructing a forebay. • HOAs adjoining Lake Accotink support retaining the lake. 5(Presented at the BOS Budget Committee Presentation September 17, 2019)
  • 6. DPWES Stormwater Planning Division Project Overview 6 Lake Accotink Dredging Dredging Order of Magnitude Cost Estimate Initial Dredging Contingency Total $24.5M $6.0M $30.5M Annual Costs Maintenance Dredging Dam Maintenance Total $2.0M $0.013M $2.013M 30 Year Lifecycle Dam Repair & Upgrades $4.7M in Year 30 Dredging Cost: $ 30,500,000 Annual Maintenance Cost: $2,013,000 30 Year Lifecycle Dam Repair: $4,700,000 Description • Dredge estimated 350,000 cubic yards of sediment to restore lake to average 8 ft depth. • Pump sediment to Wakefield Park for dewatering and disposal. • Establish maintenance dredging program to sustain the lake. • Retain aesthetic and recreation value of the lake.
  • 7. DPWES Stormwater Planning Division Project Team 7 Lake Accotink Dredging Department of Public Works & Environmental Services Charles Smith Project Manager – Stormwater Justin Pistore Project Manager - Stormwater Aaron George Lake Management – Stormwater Jay Horstman Construction Management – Capital Facilities Tom Richardson Sanitary Sewer Coordination – Wastewater Fairfax County Park Authority Valerie Maislin Project Manager – Planning and Development Adam Wynn Lake Accotink Park Master Plan Project Manager – Planning and Development Dan Grulke Lake Accotink Manager – Park Services Chris Goldbecker Lake Front Park Manager – Park Services Amber Stramel Area 2 Manager – Park Operations Braddock District Supervisor Marcia Pape Supervisor’s Aide Arcadis Team Mike Wooden Project Manager Fernando Pasquel Project Director Doug Sawyers Account Manager Akshay Kumar Assistant Project Manager Wesley Thomas Dredging & Materials Management Amanda Kohler Conveyance & Dewatering System Shannon Dunn Sediment Characterization & Water Quality Susan Larcher Public Outreach Frank Graziano (WSSI) Survey & Permitting ECS Geotechnical Analysis Key Stakeholder Groups Friends of Lake Accotink Park Friends of Accotink Creek Save Lake Accotink Homeowner & Civic Associations Lake Accotink Dredging Critical Players
  • 8. DPWES Stormwater Planning Division What To Expect 8 Lake Accotink Dredging  Data collection and survey to design dredge and determine where dredge operations could be done  Site preparation in Lake Accotink & Wakefield Parks  Dredging, pipeline and spoils processing operations  Daily commercial truck traffic north of Braddock Road to remove sediment  Light vehicle traffic daily in Lake Accotink Park to support dredging and pipeline operations  Restoration and monitoring
  • 9. DPWES Stormwater Planning Division Project Schedule 9 Lake Accotink Dredging  Data collection and survey – April 2021  Alternatives Analysis – July 2021  Concept Design and Value Engineering Study – April 2022  Final Design and Permitting – March 2023  Begin Dredging – March 2023  Complete Dredging – November 2025  Post Construction Monitoring – October 2028 Lake Accotink dredging operations June 21, 2006 – Photo by Fairfax County DPWES
  • 10. DPWES Stormwater Planning Division Things Going On Around Lake Accotink & Wakefield Park 10 Lake Accotink Dredging Arcadis field work for Lake Accotink Dredging Project Accotink Creek at Wakefield Park stream restoration VDOT survey work for Braddock Road Corridor Project Park Authority trail work near Danbury Forest Washington Gas utility work near Rolling Road Audrey Moore RecCenter renovation
  • 11. DPWES Stormwater Planning Division Discussion Discussion & Questions 11 Native mussels below Lake Accotink dam – Photo by Friends of Accotink Creek For Additional Information, to Comment or Sign up for Email Updates, Please Visit the Project Web Page: https://www.fairfaxcounty.gov/publicworks/lake-accotink- dredging Lake Accotink Dredging Community stewardship – Photo by Friends of Lake Accotink Park Cardboard boat regatta – Photo by Friends of Lake Accotink Park Mallard ducks – Photo by Fairfax County Park Authority

Editor's Notes

  1. Construction: FY2018 = July 2018
  2. And a third common question has been about the potential location of the sediment forebay considered with Option C. The Lake Sustainability Study mentions two locations (basically within the footprint of the lake primarily to minimize impacts to wetlands and forested areas) but does not specifically define a location . . . It is more about the concept. Several have questioned the possibility of locating the forebay closer to Braddock Road to enhance access to a major road to minimize potential trucking impacts. The same subject had been discussed by the project team. Location closer to Braddock Road would enhance access, however, we need to evaluate potential impacts to the Virginia Power easement. Ideally, we would want to locate the forebay below the point where Long Branch joins Accotink Creek, which leaves us a very narrow area to work within. This area is also heavily forested with wetlands so there are environmental impacts to consider. We’re also considering options to pump the sediment north of Braddock Road to Wakefield Park or Howery Field Park. Ultimately, location of the forebay and sediment removal will require much greater engineering analysis.
  3. Construction: FY2018 = July 2018
  4. Construction: FY2018 = July 2018
  5. Construction: FY2018 = July 2018
  6. Construction: FY2018 = July 2018
  7. Construction: FY2018 = July 2018
  8. Construction: FY2018 = July 2018