Integrated Project Delivery (IPD)
and Building Information Modeling (BIM)
ASIAN INSTITUTE OF TECHNOLOGY
PRESENTED BY Pisut Aunwong st119842
PRESENTED TO
1
1
Introduction
 Background
 Problem statement
 Objective
 Scope of Study
ASIAN INSTITUTE OF TECHNOLOGY
Presentation outline
2
Literature Review
 Project Definition
 What is Project
Delivery System?
 Building Information
Technology
 Integrated Project
Delivery and Building
Information
Modeling
3
Data Preparation
 The Studies
Framework
 Integrated Project
Delivery Procedure
 Building Information
Modeling Tool
 Building Information
Modeling in
Different working
Environment
 Framework
4
Summary
 The Building
Information
Modeling (IPD) using
in each stage of
Integrated Project
Delivery (IPD)
 The Integrated
Project Delivery
(IPD) Using Building
Information
Modeling (BIM)
Framework
5
Conclusion and
Recommendation
 Conclusion
 Recommendation
2
1
Introduction
 Background
 Problem statement
 Objective
 Scope of Study
ASIAN INSTITUTE OF TECHNOLOGY
3
ASIAN INSTITUTE OF TECHNOLOGY Background
Burj Khalifa in Dubai
Unique Design
Complex Design
Difficult for
construction
There are one complexity which is
mutual interdependencies between
different stakeholders.
For instant, engineers, architects,
contractors, lawyers, authorities,
financing bodies, suppliers and
trades
4
ASIAN INSTITUTE OF TECHNOLOGY Background
The advantages of applied BIM in
construction industry which is related with
 cost reduction
 significant time saving
 control through the project life cycle
Building Information Modeling Unique Design
Complex
Design
Difficult for
construction
5
ASIAN INSTITUTE OF TECHNOLOGY Background
Figure 1.1 Automated Clash Detections in One Island East
Project in Hong Kong (Azhar, 2008)
Building Information Modeling
6
ASIAN INSTITUTE OF TECHNOLOGY Background
Building Information Modeling
Figure 1.2 comprise of the architectural, structural and MEP
systems were created by building information model (Azhar, 2008)
7
ASIAN INSTITUTE OF TECHNOLOGY Background
Building Information Modeling Tools
Integrated Project Delivery
Project Delivery System
8
ASIAN INSTITUTE OF TECHNOLOGY Background
Building Information Modeling
Tools
Integrated Project Delivery
Project Delivery System
Obtain The Highest Benefits of
BIM and IPD
9
ASIAN INSTITUTE OF TECHNOLOGY
HOW?
Problem Statement
Building Information Modeling Integrated Project Delivery
10
ASIAN INSTITUTE OF TECHNOLOGY Objective
 To study the Integrated project delivery (IPD) approach particularly using
Building Information Modeling (BIM)
 To study the application of Building Information Modeling (BIM) to support
Integrated project delivery (IPD)
 To develop a framework of Integrated project delivery (IPD) using Building
Information Modeling (BIM)
11
2
Literature Review
 Project Definition
 What is Project Delivery System?
 Building Information Technology
 Integrated Project Delivery and Building
Information Modeling
ASIAN INSTITUTE OF TECHNOLOGY
12
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Definition
TEMPORARY UNIQUE
The Project Management Institute definition of Project, which is “a temporary endeavor undertaken to
generate a unique product, service, or result. The project’s temporary nature was specified that a project has
definite beginning point and the end point. To define the end of project, objectives of the project must have
been achieved or when the project is terminated because its objective will not or cannot be met, or when
the need for the project no longer exists.
13
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Delivery System
Design Bid Build (DBB)
Design Build (DB)
Construct Management at Risk
Integrated Project Delivery
14
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Delivery System Design Bid Build (DBB)
Extensive Contractor Input
Minimal Contractor Input
Concept
Planning
Preliminary
Design
Final Design Bid
If over
budget,
redesign
and rebid
Permits Select Contractor Construction
Cost
Established
Select
Architect
Final Cost
Determined
15
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Delivery System Design Build (DB)
Minimal Contractor Input Extensive Contractor Input
Concept Planning Preliminary Design
Select
Design
Builder
Final Design and Project Clearances
Construction
Cost
Established
Select
Architect
16
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Delivery System Integrated Project Delivery
Integrated Project Delivery (IPD) is a new approach to organize
project team. IPD is integrating all team members which
included owner, architect, construction manager, engineers, and
subcontractors. As a result, the project benefits are achieved.
According to Integrated Project Delivery: A guide, Integrated
Project Delivery (IPD) has been defined as a project delivery
system which integrates people, systems, business’s
organization and practices into a process. The process is
collaboratively harnesses talents and insights of all participants
to optimize project results, increase value to the owner, reduce
waste, and maximize efficiency through all phases of design,
fabrication, and construction (American Institute of Architects
California Council, 2007). Moreover, Integrated Project
Delivery is suited with collaborative variety of contractual
arrangements and IPD set may include the project’s participants
which is better than the basic triad of owner, architect, and
contractor.
Architect
Owner
Construction
manager
Engineers
Subcontractors
17
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Project Delivery System Integrated Project Delivery
Figure 2.3 Integrated Project Delivery Core Group
18
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Building Information Modeling
Figure 2.4 Building Information Modeling Lifecycle
19
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Building Information Modeling
Figure 2.5 nDimension in Building Information Modeling 20
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Building Information Modeling The benefits of Building Information Modeling
No Potential benefit for PMs Reason?
1 Organize the project schedule and budget
An integrated 5D BIM model immediately updates both the schedule and
budget when any design change occurs
2 Work well with the design team
By using the integrated 5D BIM model to visualize and explore the impact
of changes, s/he can keep project scope in check and become a
trustworthy liaison between the designers and Owner Hiring.
3 Hiring and controlling the Subcontractors
Having a handle on clash detection and coordination plays a key role in
keeping Sub-contractors’ work predictable
4
Requests for information (RFIs) and change
order
Utilizing Coordination Resolution in preconstruction, these numbers can be
brought to near zero.
21
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Building Information Modeling The benefits of Building Information Modeling
No Potential benefit for PMs Reason?
5
Optimize the owner’s experience and
satisfaction
Owner received a big injection of confidence in the GC when the PM
showed him/her how design decisions impacted cost and schedule.
6 Project closeout
PM to present a 6D BIM – a facilities resource with information on
warranties, specifications, maintenance schedules, and other valuable
information.
7 Profit margin
By thoroughly understanding the project in 5D, the PM has more tools at
his disposal to keep tight reins, and more reports to monitor progress.
8
Progressive owners are mandating BIM on
their projects
Becoming the BIM expert, in both preconstruction and out in the field,
makes the PM invaluable and a key player.
9 PM Firm growth
Project's success with 5D BIM means the opportunity to grow the firm's
reputation and helps the corporate team win new business. 22
ASIAN INSTITUTE OF TECHNOLOGY `
Literature Review
Building Information Modeling The benefits of Building Information Modeling
No Potential benefit for PMs Reason?
5
Optimize the owner’s experience and
satisfaction
Owner received a big injection of confidence in the GC when the PM
showed him/her how design decisions impacted cost and schedule.
6 Project closeout
PM to present a 6D BIM – a facilities resource with information on
warranties, specifications, maintenance schedules, and other valuable
information.
7 Profit margin
By thoroughly understanding the project in 5D, the PM has more tools at
his disposal to keep tight reins, and more reports to monitor progress.
8
Progressive owners are mandating BIM on
their projects
Becoming the BIM expert, in both preconstruction and out in the field,
makes the PM invaluable and a key player.
9 PM Firm growth
Project's success with 5D BIM means the opportunity to grow the firm's
reputation and helps the corporate team win new business. 23
3
Data Preparation
 The Studies Framework
 Integrated Project Delivery Procedure
 Building Information Modeling Tool
 Building Information Modeling in Different working
Environment
 Framework
ASIAN INSTITUTE OF TECHNOLOGY
24
The Studies Framework
ASIAN INSTITUTE OF TECHNOLOGY
The study framework
Literature Review
Project Delivery
System
BIM Conceptual
IPD Approach BIM Tools
IPD Framework BIM Application
Working
Environmental
Framework of IPD using BIM
Integrated project delivery (IPD)
approach particularly using Building
Information Modeling (BIM)
(Objective 1)
Application of Building
Information Modeling
(Objective 2)
Framework of Integrated project
delivery (IPD) using Building
Information Modeling (BIM)
(Objective 3)
OBJECTIVE ACHIEVED
Objective
Identification
Data
preparation
Framework
25
ASIAN INSTITUTE OF TECHNOLOGY
Integrated Project Delivery Procedure
The approach of Integrated Project Delivery has been provided
as following each stage below
(1)Conceptualization
(2)Design
a. Criteria design
b. Detail design
(3)Implementation procurement
(4)Construction
(5)And closeout (own and operate)
26
The Studies Framework
ASIAN INSTITUTE OF TECHNOLOGY
Integrated Project Delivery Procedure
Conceptualization Implementation
Criteria design Detail design
Design
27
The Studies Framework
ASIAN INSTITUTE OF TECHNOLOGY
Integrated Project Delivery Procedure
Implementation document Construction
Close out (Own/Operate)
28
The Studies Framework
ASIAN INSTITUTE OF TECHNOLOGY
Integrated Project Delivery Procedure
Conceptualization Implementation document Construction
Close out
(Own/Operate)
Criteria design Detail design
Design
Figure 3.2 Integrated Project Delivery Approach
29
The Studies Framework
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool
Building Information Modeling equipment
Building Information Modeling application
30
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling equipment
Microsoft Hololens
31
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling equipment
Figure 3.3 Trimble Connect for HoloLens utilizes mixed-reality
technology to take 3D content off the screen and into the real-
world
32
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling equipment
Figure 3.4 Trimble Connect for HoloLens utilizes mixed-reality
technology on construction filed
33
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling equipment
Figure 3.5 Trimble Connect for HoloLens utilizes mixed-reality
technology to team collaboration
34
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling application
Figure 3.6 BIM application in different working environmental
35
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling application
No Name Company
1 Revit Architecture Autodesk Inc.
2 Revit Structure Autodesk Inc.
3 Revit MEP Autodesk Inc.
4 Autodesk Civil 3D Autodesk Inc.
5 Autodesk 3ds Max Design Autodesk Inc.
6 Autodesk Maya Autodesk Inc.
7 Autodesk Inventor Autodesk Inc.
8 Autodesk Impression Autodesk Inc.
9 Autodesk Collaborative Autodesk Inc.
10 Autodesk Design Review Autodesk Inc.
11 Autodesk Navisworks Autodesk Inc.
12 Autodesk Quantity Take off Autodesk Inc.
13 Autodesk FMDesktop Autodesk Inc.
14 Construction Management Software Autodesk Inc.
Table 3.1 BIM Application list (example application)
36
4
Summary
 The Building Information Modeling (IPD) using in each
stage of Integrated Project Delivery (IPD)
 The Integrated Project Delivery (IPD) Using Building
Information Modeling (BIM) Framework
ASIAN INSTITUTE OF TECHNOLOGY
37
ASIAN INSTITUTE OF TECHNOLOGY
Building Information Modeling Tool Building Information Modeling application
Table 4.1 BIM Application is using in each stage of IPD
No Name CONC DES IMD CONS OPT
1 Revit Architecture • • • •
2 Revit Structure • • • •
3 Revit MEP • • • •
4 Autodesk Civil 3D • •
5 Autodesk 3ds Max Design •
6 Autodesk Maya •
7 Autodesk Inventor • • •
8 Autodesk Impression •
9 Autodesk Collaborative • • • • •
10 Autodesk Design Review • • • •
11 Autodesk Navisworks • • •
12 Autodesk Quantity Take off • •
13 AutoCAD •
14 Autodesk FMDesktop •
38
ASIAN INSTITUTE OF TECHNOLOGY
The Integrated Project Delivery (IPD) Using Building Information Modeling (BIM) Framework
39
5
Conclusion and Recommendation
 Conclusion
 Recommendation
ASIAN INSTITUTE OF TECHNOLOGY
40
ASIAN INSTITUTE OF TECHNOLOGY
Conclusion
To achieve the highest benefit of Integrated Project Delivery (IPD), Integrated Project
Delivery (IPD) have to applied Building Information Modeling (BIM) due to BIM is tools
to use in IPD.
However, the tools of Building Information Modeling have divided into two types, which
are
(1) software/application
(2) BIM equipment.
Thus, the application are causing many benefits for Owner, Architect and Contractor to
reducing project duration, effectively management, reducing clash in project, providing
pre-construction, forecasting project environmental and different situation.
41
ASIAN INSTITUTE OF TECHNOLOGY
Conclusion
The study has been focused in Building Information Modeling Application.
There are many BIM application in market on these day. However, the
study has divided the application which is suitable in different phase in
Integrated Project Delivery Approach
Revit Structure Revit MEP
Autodesk
Navisworks
Construction
Management
Software
42
ASIAN INSTITUTE OF TECHNOLOGY
Conclusion
The framework of Integrated Project Delivery (IPD) using Building Information Modeling
(BIM) has been developed by apply Autodesk application to show how does Building
Information Modeling (BIM) is uses by Integrated Project Delivery Approach. The
framework is shown at figure 4.1 Integrated Project Delivery using Building Information
Modeling. The reason of using Autodesk’s application to do the explanation is the format
file which generated by Autodesk’s Application may use with other application under
Autodesk developer. Thus, the exchange file between different application may not cause
any conflict.
How Relationship
43
ASIAN INSTITUTE OF TECHNOLOGY
Recommendation
The framework has explained only
Autodesk’s application. There are many
BIM application which can do exchange file
to different application from other
developer.
Moreover, there are some application can
export the files in different types. The
reason is some type of work, such as steel
work is better to develop in other program
which is better than Autodesk software.
Show only
Autodesk
Application
Some
application is
better than
Autodesk
developer
44
THANK YOU
ASIAN INSTITUTE OF TECHNOLOGY
45

More Related Content

What's hot

Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentationryanabarton
 
Building Information Modelling Presentation
Building Information Modelling PresentationBuilding Information Modelling Presentation
Building Information Modelling PresentationMotasem Albanna
 
An Introduction to BIM.ppsx
An Introduction to BIM.ppsxAn Introduction to BIM.ppsx
An Introduction to BIM.ppsxMujahid Kadri
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation Omar Selim
 
Building information modeling & value to the AEC industry Part 2
Building information modeling &  value to the AEC industry   Part 2Building information modeling &  value to the AEC industry   Part 2
Building information modeling & value to the AEC industry Part 2Stephen Au
 
What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?Chun Keung Ng
 
Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectMANNU KUMAR
 
BIM project execution
BIM project executionBIM project execution
BIM project executionStephen Au
 

What's hot (20)

bim+ Presentation BIM Manager
bim+ Presentation BIM Managerbim+ Presentation BIM Manager
bim+ Presentation BIM Manager
 
BIM
BIMBIM
BIM
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
Building Information Modelling Presentation
Building Information Modelling PresentationBuilding Information Modelling Presentation
Building Information Modelling Presentation
 
An Introduction to BIM.ppsx
An Introduction to BIM.ppsxAn Introduction to BIM.ppsx
An Introduction to BIM.ppsx
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation
 
Building information modeling & value to the AEC industry Part 2
Building information modeling &  value to the AEC industry   Part 2Building information modeling &  value to the AEC industry   Part 2
Building information modeling & value to the AEC industry Part 2
 
Introduction to Building Information Modeling
Introduction to Building Information Modeling Introduction to Building Information Modeling
Introduction to Building Information Modeling
 
The Bim Process Explained
The Bim Process ExplainedThe Bim Process Explained
The Bim Process Explained
 
What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?
 
What is BIM?
What is BIM?What is BIM?
What is BIM?
 
BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
 
Bim and building life cycle
Bim and building life cycleBim and building life cycle
Bim and building life cycle
 
Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real project
 
BIM project execution
BIM project executionBIM project execution
BIM project execution
 
what is BIM
what is BIMwhat is BIM
what is BIM
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
BIM awareness
BIM awarenessBIM awareness
BIM awareness
 
BIM - Operational readiness
BIM - Operational readinessBIM - Operational readiness
BIM - Operational readiness
 
A gentle introduction to BIM
A gentle introduction to BIMA gentle introduction to BIM
A gentle introduction to BIM
 

Similar to IPD using BIM BY Pisut Aunwong

IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...IRJET Journal
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road ConstructionHeidi Owens
 
Digital construction for integrated project delivery
Digital construction for integrated project deliveryDigital construction for integrated project delivery
Digital construction for integrated project deliveryStephen Au
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling reportKiran Birdi
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...IRJET Journal
 
Application of BIM and Construction Process Simulation using 5D BIM for Resid...
Application of BIM and Construction Process Simulation using 5D BIM for Resid...Application of BIM and Construction Process Simulation using 5D BIM for Resid...
Application of BIM and Construction Process Simulation using 5D BIM for Resid...IRJET Journal
 
BIM and Construction Management Proven Tools, Methods, and Workflows
BIM and Construction Management Proven Tools, Methods, and WorkflowsBIM and Construction Management Proven Tools, Methods, and Workflows
BIM and Construction Management Proven Tools, Methods, and Workflowspinoy cadplus
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdfWaliEdwardian1
 
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIMIRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIMIRJET Journal
 
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET -  	  Digital Engineering & Project Management for AEC Industry using BIMIRJET -  	  Digital Engineering & Project Management for AEC Industry using BIM
IRJET - Digital Engineering & Project Management for AEC Industry using BIMIRJET Journal
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed
 
Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...Ionel GRECESCU
 
Application of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction ProjectApplication of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction ProjectIRJET Journal
 
IRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building ProjectIRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building ProjectIRJET Journal
 
15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaperTodd Sullivan
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...IRJET Journal
 
Hire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaHire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaAEO Design Consultants
 

Similar to IPD using BIM BY Pisut Aunwong (20)

IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
 
Ricci Piper
Ricci PiperRicci Piper
Ricci Piper
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road Construction
 
Digital construction for integrated project delivery
Digital construction for integrated project deliveryDigital construction for integrated project delivery
Digital construction for integrated project delivery
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling report
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...
 
Application of BIM and Construction Process Simulation using 5D BIM for Resid...
Application of BIM and Construction Process Simulation using 5D BIM for Resid...Application of BIM and Construction Process Simulation using 5D BIM for Resid...
Application of BIM and Construction Process Simulation using 5D BIM for Resid...
 
BIM and Construction Management Proven Tools, Methods, and Workflows
BIM and Construction Management Proven Tools, Methods, and WorkflowsBIM and Construction Management Proven Tools, Methods, and Workflows
BIM and Construction Management Proven Tools, Methods, and Workflows
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
 
Opening Keynote Speech (By Video) Ms. Ada Fung, JP Chairperson, The Construct...
Opening Keynote Speech (By Video) Ms. Ada Fung, JP Chairperson, The Construct...Opening Keynote Speech (By Video) Ms. Ada Fung, JP Chairperson, The Construct...
Opening Keynote Speech (By Video) Ms. Ada Fung, JP Chairperson, The Construct...
 
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIMIRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
 
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET -  	  Digital Engineering & Project Management for AEC Industry using BIMIRJET -  	  Digital Engineering & Project Management for AEC Industry using BIM
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
 
Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...
 
Application of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction ProjectApplication of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction Project
 
IRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building ProjectIRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building Project
 
15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
Hire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaHire best BIM Service Providers in Florida
Hire best BIM Service Providers in Florida
 

More from Roman Shrestha

RM Roman man shrestha.pptx
RM Roman man shrestha.pptxRM Roman man shrestha.pptx
RM Roman man shrestha.pptxRoman Shrestha
 
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management College
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management CollegeStrategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management College
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management CollegeRoman Shrestha
 
Brand Positioning of Nepali Carpet.pptx
Brand Positioning of Nepali Carpet.pptxBrand Positioning of Nepali Carpet.pptx
Brand Positioning of Nepali Carpet.pptxRoman Shrestha
 
Informatics college week 2.pptx
Informatics college week 2.pptxInformatics college week 2.pptx
Informatics college week 2.pptxRoman Shrestha
 
Boo hoo – learning from the largest European.pptx
Boo hoo – learning from the largest European.pptxBoo hoo – learning from the largest European.pptx
Boo hoo – learning from the largest European.pptxRoman Shrestha
 
Safety-Ass-4group-5.pptx
Safety-Ass-4group-5.pptxSafety-Ass-4group-5.pptx
Safety-Ass-4group-5.pptxRoman Shrestha
 
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...Roman Shrestha
 
FRC final presentation
FRC final presentationFRC final presentation
FRC final presentationRoman Shrestha
 
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptx
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptxBUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptx
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptxRoman Shrestha
 
BANCHAK COMPETITION WASTE FOR THE BEST.pptx
BANCHAK COMPETITION WASTE FOR THE BEST.pptxBANCHAK COMPETITION WASTE FOR THE BEST.pptx
BANCHAK COMPETITION WASTE FOR THE BEST.pptxRoman Shrestha
 
AIT Indoor Gaming Center.
AIT Indoor Gaming Center.AIT Indoor Gaming Center.
AIT Indoor Gaming Center.Roman Shrestha
 
INTEGRATED PROJECT PLANNING AND CONTROL
INTEGRATED PROJECT PLANNING AND CONTROLINTEGRATED PROJECT PLANNING AND CONTROL
INTEGRATED PROJECT PLANNING AND CONTROLRoman Shrestha
 
Modified nepali chulo
Modified nepali chulo Modified nepali chulo
Modified nepali chulo Roman Shrestha
 
Writing research paper
Writing research paperWriting research paper
Writing research paperRoman Shrestha
 
Project selection and report writing
Project selection and report writingProject selection and report writing
Project selection and report writingRoman Shrestha
 
Water movement in kathmandu
Water movement in kathmanduWater movement in kathmandu
Water movement in kathmanduRoman Shrestha
 
Risk assesment of 4 storey building
Risk assesment of 4 storey buildingRisk assesment of 4 storey building
Risk assesment of 4 storey buildingRoman Shrestha
 
Safety Procedures while working in height
Safety Procedures while working in heightSafety Procedures while working in height
Safety Procedures while working in heightRoman Shrestha
 

More from Roman Shrestha (20)

RM Roman man shrestha.pptx
RM Roman man shrestha.pptxRM Roman man shrestha.pptx
RM Roman man shrestha.pptx
 
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management College
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management CollegeStrategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management College
Strategic Marketing Plan for Sitaljyoti Academy: A +2 Hotel Management College
 
Eco homes in Nepal
Eco homes in NepalEco homes in Nepal
Eco homes in Nepal
 
Brand Positioning of Nepali Carpet.pptx
Brand Positioning of Nepali Carpet.pptxBrand Positioning of Nepali Carpet.pptx
Brand Positioning of Nepali Carpet.pptx
 
Informatics college week 2.pptx
Informatics college week 2.pptxInformatics college week 2.pptx
Informatics college week 2.pptx
 
Boo hoo – learning from the largest European.pptx
Boo hoo – learning from the largest European.pptxBoo hoo – learning from the largest European.pptx
Boo hoo – learning from the largest European.pptx
 
Safety-Ass-4group-5.pptx
Safety-Ass-4group-5.pptxSafety-Ass-4group-5.pptx
Safety-Ass-4group-5.pptx
 
Research-Cycle-Group
Research-Cycle-GroupResearch-Cycle-Group
Research-Cycle-Group
 
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...
Analysis-of-Accommodation-Facility-Service-Quality-Aspects-and-Students-Satis...
 
FRC final presentation
FRC final presentationFRC final presentation
FRC final presentation
 
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptx
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptxBUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptx
BUSINESS PERFORMANCE OF SMALL SIZE ENTERPRISES IN NEPAL.pptx
 
BANCHAK COMPETITION WASTE FOR THE BEST.pptx
BANCHAK COMPETITION WASTE FOR THE BEST.pptxBANCHAK COMPETITION WASTE FOR THE BEST.pptx
BANCHAK COMPETITION WASTE FOR THE BEST.pptx
 
AIT Indoor Gaming Center.
AIT Indoor Gaming Center.AIT Indoor Gaming Center.
AIT Indoor Gaming Center.
 
INTEGRATED PROJECT PLANNING AND CONTROL
INTEGRATED PROJECT PLANNING AND CONTROLINTEGRATED PROJECT PLANNING AND CONTROL
INTEGRATED PROJECT PLANNING AND CONTROL
 
Modified nepali chulo
Modified nepali chulo Modified nepali chulo
Modified nepali chulo
 
Writing research paper
Writing research paperWriting research paper
Writing research paper
 
Project selection and report writing
Project selection and report writingProject selection and report writing
Project selection and report writing
 
Water movement in kathmandu
Water movement in kathmanduWater movement in kathmandu
Water movement in kathmandu
 
Risk assesment of 4 storey building
Risk assesment of 4 storey buildingRisk assesment of 4 storey building
Risk assesment of 4 storey building
 
Safety Procedures while working in height
Safety Procedures while working in heightSafety Procedures while working in height
Safety Procedures while working in height
 

Recently uploaded

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 

IPD using BIM BY Pisut Aunwong

  • 1. Dr. Bonaventura H.W. Hadikusumo (Chairperson) Dr. Chotchai Charoenngam Dr. Huynh Trung Luong Integrated Project Delivery (IPD) and Building Information Modeling (BIM) ASIAN INSTITUTE OF TECHNOLOGY PRESENTED BY Pisut Aunwong st119842 PRESENTED TO 1
  • 2. 1 Introduction  Background  Problem statement  Objective  Scope of Study ASIAN INSTITUTE OF TECHNOLOGY Presentation outline 2 Literature Review  Project Definition  What is Project Delivery System?  Building Information Technology  Integrated Project Delivery and Building Information Modeling 3 Data Preparation  The Studies Framework  Integrated Project Delivery Procedure  Building Information Modeling Tool  Building Information Modeling in Different working Environment  Framework 4 Summary  The Building Information Modeling (IPD) using in each stage of Integrated Project Delivery (IPD)  The Integrated Project Delivery (IPD) Using Building Information Modeling (BIM) Framework 5 Conclusion and Recommendation  Conclusion  Recommendation 2
  • 3. 1 Introduction  Background  Problem statement  Objective  Scope of Study ASIAN INSTITUTE OF TECHNOLOGY 3
  • 4. ASIAN INSTITUTE OF TECHNOLOGY Background Burj Khalifa in Dubai Unique Design Complex Design Difficult for construction There are one complexity which is mutual interdependencies between different stakeholders. For instant, engineers, architects, contractors, lawyers, authorities, financing bodies, suppliers and trades 4
  • 5. ASIAN INSTITUTE OF TECHNOLOGY Background The advantages of applied BIM in construction industry which is related with  cost reduction  significant time saving  control through the project life cycle Building Information Modeling Unique Design Complex Design Difficult for construction 5
  • 6. ASIAN INSTITUTE OF TECHNOLOGY Background Figure 1.1 Automated Clash Detections in One Island East Project in Hong Kong (Azhar, 2008) Building Information Modeling 6
  • 7. ASIAN INSTITUTE OF TECHNOLOGY Background Building Information Modeling Figure 1.2 comprise of the architectural, structural and MEP systems were created by building information model (Azhar, 2008) 7
  • 8. ASIAN INSTITUTE OF TECHNOLOGY Background Building Information Modeling Tools Integrated Project Delivery Project Delivery System 8
  • 9. ASIAN INSTITUTE OF TECHNOLOGY Background Building Information Modeling Tools Integrated Project Delivery Project Delivery System Obtain The Highest Benefits of BIM and IPD 9
  • 10. ASIAN INSTITUTE OF TECHNOLOGY HOW? Problem Statement Building Information Modeling Integrated Project Delivery 10
  • 11. ASIAN INSTITUTE OF TECHNOLOGY Objective  To study the Integrated project delivery (IPD) approach particularly using Building Information Modeling (BIM)  To study the application of Building Information Modeling (BIM) to support Integrated project delivery (IPD)  To develop a framework of Integrated project delivery (IPD) using Building Information Modeling (BIM) 11
  • 12. 2 Literature Review  Project Definition  What is Project Delivery System?  Building Information Technology  Integrated Project Delivery and Building Information Modeling ASIAN INSTITUTE OF TECHNOLOGY 12
  • 13. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Definition TEMPORARY UNIQUE The Project Management Institute definition of Project, which is “a temporary endeavor undertaken to generate a unique product, service, or result. The project’s temporary nature was specified that a project has definite beginning point and the end point. To define the end of project, objectives of the project must have been achieved or when the project is terminated because its objective will not or cannot be met, or when the need for the project no longer exists. 13
  • 14. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Delivery System Design Bid Build (DBB) Design Build (DB) Construct Management at Risk Integrated Project Delivery 14
  • 15. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Delivery System Design Bid Build (DBB) Extensive Contractor Input Minimal Contractor Input Concept Planning Preliminary Design Final Design Bid If over budget, redesign and rebid Permits Select Contractor Construction Cost Established Select Architect Final Cost Determined 15
  • 16. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Delivery System Design Build (DB) Minimal Contractor Input Extensive Contractor Input Concept Planning Preliminary Design Select Design Builder Final Design and Project Clearances Construction Cost Established Select Architect 16
  • 17. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Delivery System Integrated Project Delivery Integrated Project Delivery (IPD) is a new approach to organize project team. IPD is integrating all team members which included owner, architect, construction manager, engineers, and subcontractors. As a result, the project benefits are achieved. According to Integrated Project Delivery: A guide, Integrated Project Delivery (IPD) has been defined as a project delivery system which integrates people, systems, business’s organization and practices into a process. The process is collaboratively harnesses talents and insights of all participants to optimize project results, increase value to the owner, reduce waste, and maximize efficiency through all phases of design, fabrication, and construction (American Institute of Architects California Council, 2007). Moreover, Integrated Project Delivery is suited with collaborative variety of contractual arrangements and IPD set may include the project’s participants which is better than the basic triad of owner, architect, and contractor. Architect Owner Construction manager Engineers Subcontractors 17
  • 18. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Project Delivery System Integrated Project Delivery Figure 2.3 Integrated Project Delivery Core Group 18
  • 19. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Building Information Modeling Figure 2.4 Building Information Modeling Lifecycle 19
  • 20. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Building Information Modeling Figure 2.5 nDimension in Building Information Modeling 20
  • 21. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Building Information Modeling The benefits of Building Information Modeling No Potential benefit for PMs Reason? 1 Organize the project schedule and budget An integrated 5D BIM model immediately updates both the schedule and budget when any design change occurs 2 Work well with the design team By using the integrated 5D BIM model to visualize and explore the impact of changes, s/he can keep project scope in check and become a trustworthy liaison between the designers and Owner Hiring. 3 Hiring and controlling the Subcontractors Having a handle on clash detection and coordination plays a key role in keeping Sub-contractors’ work predictable 4 Requests for information (RFIs) and change order Utilizing Coordination Resolution in preconstruction, these numbers can be brought to near zero. 21
  • 22. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Building Information Modeling The benefits of Building Information Modeling No Potential benefit for PMs Reason? 5 Optimize the owner’s experience and satisfaction Owner received a big injection of confidence in the GC when the PM showed him/her how design decisions impacted cost and schedule. 6 Project closeout PM to present a 6D BIM – a facilities resource with information on warranties, specifications, maintenance schedules, and other valuable information. 7 Profit margin By thoroughly understanding the project in 5D, the PM has more tools at his disposal to keep tight reins, and more reports to monitor progress. 8 Progressive owners are mandating BIM on their projects Becoming the BIM expert, in both preconstruction and out in the field, makes the PM invaluable and a key player. 9 PM Firm growth Project's success with 5D BIM means the opportunity to grow the firm's reputation and helps the corporate team win new business. 22
  • 23. ASIAN INSTITUTE OF TECHNOLOGY ` Literature Review Building Information Modeling The benefits of Building Information Modeling No Potential benefit for PMs Reason? 5 Optimize the owner’s experience and satisfaction Owner received a big injection of confidence in the GC when the PM showed him/her how design decisions impacted cost and schedule. 6 Project closeout PM to present a 6D BIM – a facilities resource with information on warranties, specifications, maintenance schedules, and other valuable information. 7 Profit margin By thoroughly understanding the project in 5D, the PM has more tools at his disposal to keep tight reins, and more reports to monitor progress. 8 Progressive owners are mandating BIM on their projects Becoming the BIM expert, in both preconstruction and out in the field, makes the PM invaluable and a key player. 9 PM Firm growth Project's success with 5D BIM means the opportunity to grow the firm's reputation and helps the corporate team win new business. 23
  • 24. 3 Data Preparation  The Studies Framework  Integrated Project Delivery Procedure  Building Information Modeling Tool  Building Information Modeling in Different working Environment  Framework ASIAN INSTITUTE OF TECHNOLOGY 24
  • 25. The Studies Framework ASIAN INSTITUTE OF TECHNOLOGY The study framework Literature Review Project Delivery System BIM Conceptual IPD Approach BIM Tools IPD Framework BIM Application Working Environmental Framework of IPD using BIM Integrated project delivery (IPD) approach particularly using Building Information Modeling (BIM) (Objective 1) Application of Building Information Modeling (Objective 2) Framework of Integrated project delivery (IPD) using Building Information Modeling (BIM) (Objective 3) OBJECTIVE ACHIEVED Objective Identification Data preparation Framework 25
  • 26. ASIAN INSTITUTE OF TECHNOLOGY Integrated Project Delivery Procedure The approach of Integrated Project Delivery has been provided as following each stage below (1)Conceptualization (2)Design a. Criteria design b. Detail design (3)Implementation procurement (4)Construction (5)And closeout (own and operate) 26
  • 27. The Studies Framework ASIAN INSTITUTE OF TECHNOLOGY Integrated Project Delivery Procedure Conceptualization Implementation Criteria design Detail design Design 27
  • 28. The Studies Framework ASIAN INSTITUTE OF TECHNOLOGY Integrated Project Delivery Procedure Implementation document Construction Close out (Own/Operate) 28
  • 29. The Studies Framework ASIAN INSTITUTE OF TECHNOLOGY Integrated Project Delivery Procedure Conceptualization Implementation document Construction Close out (Own/Operate) Criteria design Detail design Design Figure 3.2 Integrated Project Delivery Approach 29
  • 30. The Studies Framework ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling equipment Building Information Modeling application 30
  • 31. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling equipment Microsoft Hololens 31
  • 32. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling equipment Figure 3.3 Trimble Connect for HoloLens utilizes mixed-reality technology to take 3D content off the screen and into the real- world 32
  • 33. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling equipment Figure 3.4 Trimble Connect for HoloLens utilizes mixed-reality technology on construction filed 33
  • 34. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling equipment Figure 3.5 Trimble Connect for HoloLens utilizes mixed-reality technology to team collaboration 34
  • 35. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling application Figure 3.6 BIM application in different working environmental 35
  • 36. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling application No Name Company 1 Revit Architecture Autodesk Inc. 2 Revit Structure Autodesk Inc. 3 Revit MEP Autodesk Inc. 4 Autodesk Civil 3D Autodesk Inc. 5 Autodesk 3ds Max Design Autodesk Inc. 6 Autodesk Maya Autodesk Inc. 7 Autodesk Inventor Autodesk Inc. 8 Autodesk Impression Autodesk Inc. 9 Autodesk Collaborative Autodesk Inc. 10 Autodesk Design Review Autodesk Inc. 11 Autodesk Navisworks Autodesk Inc. 12 Autodesk Quantity Take off Autodesk Inc. 13 Autodesk FMDesktop Autodesk Inc. 14 Construction Management Software Autodesk Inc. Table 3.1 BIM Application list (example application) 36
  • 37. 4 Summary  The Building Information Modeling (IPD) using in each stage of Integrated Project Delivery (IPD)  The Integrated Project Delivery (IPD) Using Building Information Modeling (BIM) Framework ASIAN INSTITUTE OF TECHNOLOGY 37
  • 38. ASIAN INSTITUTE OF TECHNOLOGY Building Information Modeling Tool Building Information Modeling application Table 4.1 BIM Application is using in each stage of IPD No Name CONC DES IMD CONS OPT 1 Revit Architecture • • • • 2 Revit Structure • • • • 3 Revit MEP • • • • 4 Autodesk Civil 3D • • 5 Autodesk 3ds Max Design • 6 Autodesk Maya • 7 Autodesk Inventor • • • 8 Autodesk Impression • 9 Autodesk Collaborative • • • • • 10 Autodesk Design Review • • • • 11 Autodesk Navisworks • • • 12 Autodesk Quantity Take off • • 13 AutoCAD • 14 Autodesk FMDesktop • 38
  • 39. ASIAN INSTITUTE OF TECHNOLOGY The Integrated Project Delivery (IPD) Using Building Information Modeling (BIM) Framework 39
  • 40. 5 Conclusion and Recommendation  Conclusion  Recommendation ASIAN INSTITUTE OF TECHNOLOGY 40
  • 41. ASIAN INSTITUTE OF TECHNOLOGY Conclusion To achieve the highest benefit of Integrated Project Delivery (IPD), Integrated Project Delivery (IPD) have to applied Building Information Modeling (BIM) due to BIM is tools to use in IPD. However, the tools of Building Information Modeling have divided into two types, which are (1) software/application (2) BIM equipment. Thus, the application are causing many benefits for Owner, Architect and Contractor to reducing project duration, effectively management, reducing clash in project, providing pre-construction, forecasting project environmental and different situation. 41
  • 42. ASIAN INSTITUTE OF TECHNOLOGY Conclusion The study has been focused in Building Information Modeling Application. There are many BIM application in market on these day. However, the study has divided the application which is suitable in different phase in Integrated Project Delivery Approach Revit Structure Revit MEP Autodesk Navisworks Construction Management Software 42
  • 43. ASIAN INSTITUTE OF TECHNOLOGY Conclusion The framework of Integrated Project Delivery (IPD) using Building Information Modeling (BIM) has been developed by apply Autodesk application to show how does Building Information Modeling (BIM) is uses by Integrated Project Delivery Approach. The framework is shown at figure 4.1 Integrated Project Delivery using Building Information Modeling. The reason of using Autodesk’s application to do the explanation is the format file which generated by Autodesk’s Application may use with other application under Autodesk developer. Thus, the exchange file between different application may not cause any conflict. How Relationship 43
  • 44. ASIAN INSTITUTE OF TECHNOLOGY Recommendation The framework has explained only Autodesk’s application. There are many BIM application which can do exchange file to different application from other developer. Moreover, there are some application can export the files in different types. The reason is some type of work, such as steel work is better to develop in other program which is better than Autodesk software. Show only Autodesk Application Some application is better than Autodesk developer 44
  • 45. THANK YOU ASIAN INSTITUTE OF TECHNOLOGY 45