2. A project manager is leading a process improvement project for a factory operation. Currently, the
project manager and the team are performing the Monitor and Control Project Work process.
Which of the following activities might be carried out during this process?
A. Comparing actual project performance against the project management plan
B. Implementing approved change requests to achieve the project's objectives
C. Analyzing change requests and either approving or rejecting them
D. Gaining formal acceptance of the deliverables by the customer or sponsor
HINT: The Monitor and Control Project Work process is the process of tracking, reviewing, and
reporting overall progress to meet the performance objectives defined in the project management
plan.
Question
3. The correct answer is A.
Monitor and Control Project Work is the process of tracking, reviewing, and reporting overall
progress to meet the performance objectives defined in the project management plan.
Of the available choices, only comparing actual project performance against the project
management plan is performed during the Monitor and Control Project Work process.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.