SlideShare a Scribd company logo
1 of 44
Distance Protection
Schemes
Channel Independent
Schemes
Z3
Z3
Z1
Z1
Z2
Z2
Z3
Z2
Z1 1
.
T2
T3
Trip
T2
Z3
Z2
Z1
1
.
T2
T3
Trip
T2
Basic Distance Scheme
 Zone 1 set to 80% leaves 2 end zones
 Faults in end zone results in instantaneous
tripping at one end and time delayed at the
other
 Time delay may lead to system stability
problems
 Sequential clearance leaves no dead time for
high speed A/R cycle (transient fault becomes
permanent)
 Longer clearance times - More damage
Basic Distance Scheme -
Disadvantages
Z3
Z3
Z1X
Z1X
Z2
Z2
Z3
Z2
Z1 1
.
T2
T3
Trip
&
1
Z1X
A/R
Z3
Z2
Z1
1
.
T2
T3
Trip
&
1
Z1X
A/R
Z1
Z1
Zone 1 Extension Scheme
 No signalling channel required (may be used
as temporary replacement for carrier aided
scheme when comms. channel out of service)
 Provides fast fault clearance at both ends for a
transient fault anywhere along the line length
 Allows the use of high speed A/R cycle
Zone 1 Extension - Advantages
 Tripping can occur for external faults (but will be
followed by an autoreclose)
 Basic distance scheme logic applies following
reclose (i.e. potential for time delayed clearance
for permanent faults)
 Only suitable to systems where autoreclose is
used (for example can not be used on cable
circuits)
Zone 1 Extension Scheme -
Disadvantages
Loss of Load Accelerated Trip
Z3
Z3
Z1
Z1
Z2
Z2
Z2
..
&
..
.
Trip
&
&
.
1
.
LDA
LDB
LDC
0
T2
T1
0
T1 = 40ms (allows for slowest pickup of Zone 2)
T2 = 18ms (prevents LOL trip for external fault with
CB pole scatter)
 Fast fault clearance without the need for a
signalling channel
 Only applicable where 3 phase tripping is used
 Only operates for unbalanced faults
 Load current (above the current detector
settings) must exist prior to the fault to ‘arm’ the
scheme
 Can be used as back up to signal aided scheme
Loss of Load Scheme
Channel Dependent
Schemes
 Provide high speed clearance for all faults on line
(for example current differential)
 Do not provide inherent back-up protection
SOLUTION IS TO PROVIDE DISTANCE PROTECTION FOR BACK-
UP PROTECTION OF ADJACENT LINES WITH AN AIDED
TRIPPING SCHEME FOR HIGH SPEED PROTECTION OF WHOLE
LINE
 Requires the use of an ON/OFF signalling
channel between line ends (i.e. HF/VF/Fibre
Optic/Radio)
Unit Protection Schemes
 Acceleration
 Transfer tripping
– Direct
– Permissive Underreach
– Permissive Overreach
 Blocking
Types of Aided Tripping
Schemes
Z3
Z3
Z1
Z1
Z2
Z2
Z3
Z2
Z1 1
.
T2
T3
Trip
Z3
Z2
Z1
1
.
T2
T3
Trip
Tx
Rx
Tx
Rx
Send Logic : Z1
Trip Logic : Rx
Direct Transfer Trip
 All faults anywhere along the protected line can
be cleared instantaneously at both line ends
 Scheme can be advantageous for protecting 3
terminal lines due to ease of application
Direct Transfer Trip -
Advantages
 A very secure signalling channel is required :-
incorrect operation leads to false tripping
 Circuit breakers at both line ends must be closed
and contribute fault current to obtain high speed
fault clearance
 If the channel fails only the Basic scheme logic
will be provided
Direct Transfer Trip -
Disadvantages
Z3
Z3
Z1
Z1
Z2
Z2
Change
Z1
reach
Z3
Z1/Z2 1
.
T2
Trip
T3 Z3
Z1/Z2
1
.
T3
T2
Trip
Tx
Rx
Tx
Rx
1
.
1
.
Send Logic : Z1
Trip Logic : Rx + Z2
Acceleration Scheme (for
Reach Stepped Relay)
Permissive Schemes
Z3
Z3
Z1
Z1
Z2
Z2
Tx
Rx
Tx
Rx
Send Logic : Z1
Trip Logic : Rx + Z2
Z3
Z2
Z1 1
.
T2
T3
Trip
T2
&
Z3
Z2
Z1
1
.
T2
T3
Trip
T2
&
100
0
100
0
Permissive Underreach
Scheme
A
21
C
B
D
A
C
B
D
Send
Fault
Fault
 Race between relay at D
picking up and signal
send from relay at C
resetting, following
opening of breaker at C
 If signal send from C
resets before relay D
operates then aided
tripping will not occur
 To prevent this a 100ms
delay on drop off of the
signal send is used in
the scheme logic
21
21 21
Permissive Underreach
Scheme
Rx + Z2
Rx + Z2
 Only a simplex signalling channel required
 Scheme is very secure as signalling channel
only keyed for internal fault (Zone 1 initiation)
Permissive Underreach
Transfer Trip - Advantages
 If one terminal of the line is open then only
Basic scheme logic will apply
 If there is a weak infeed at one terminal then
only Basic scheme logic will apply
 If signalling channel fails then only Basic
scheme logic will apply
 Resistive coverage is governed by Zone 1
setting (may be limited on short lines)
Permissive Underreach
Transfer Trip - Disadvantages
Z3
Z2
Z1 1
.
T2
T3
Trip
&
T2
Z3
Z2
Z1
1
.
T2
T3
Trip
&
T2
Rx
Tx
Rx
Tx
Z3
Z3
Z1
Z1
Z2
Z2
Send Logic : Z2
Trip Logic : Rx + Z2
Permissive Overreach Scheme
Internal Fault
Z3
Z2
Z1 1
.
T2
T3
Trip
&
T2
Z3
Z2
Z1
1
.
T2
T3
Trip
&
T2
Rx
Tx
Rx
Tx
Z3
Z3
Z1
Z1
Z2
Z2
Send Logic : Z2
Trip Logic : Rx + Z2
Permissive Overreach Scheme
External Fault
Z3
Z2
Z1
T2
T3
Trip
&
T2
Z3
Z2
Z1
T2
T3
Trip
&
T2
&
1
Rx
Tx
CB open &
1
Rx
Tx
CB open
Z3
Z3
Z1
Z1
Z2
Z2
1
.
1
.
Send Logic : Z2
Trip Logic : Rx + Z2
Open terminal echo : CB Open + Rx
Permissive Overreach Scheme
(CB Echo Logic)
Z4
Z4
Z1
Z1
Z2
Z2
Z3
Z2
Z1
T2
T3
Trip
T2
Z3
Z2
Z1
T2
T3
Trip
T2
&
Z4
CB open &
Z4
CB open
Send Logic : Z2
Trip Logic : Rx + Z2
Open terminal echo : CB Open + Rx
Weak Infeed echo : Z4 + Rx
Permissive Overreach Scheme
(WI Echo Logic)
1
& &
&
Rx
Tx &
Rx
Tx
1
.
1
.
1
Z4
Z4
Z1
Z1
Z2
Z2
Z3
Z2
Z1
T3
Trip
&
T2
&
LDOV
Z3
Z2
Z1
T3
Trip
&
T2
& LDOV
&
Rx
Tx
Z4
CB open &
Rx
Tx Z4
CB open
& &
1
.
1
.
1 1
Send Logic : Z2
Trip Logic : Rx + Z2
Open terminal echo : CB Open + Rx
Weak Infeed echo : Z4 + Rx
Weak Infeed trip : Z4 + LDOV reset + Rx
Permissive Overreach Weak
Infeed Trip Scheme
 Provides better resistive coverage, especially
on short lines, where MHO measuring
elements are used
 For cases where one line terminal is open,
open breaker echo logic can be used
 For cases of weak or zero infeed at one line
terminal weak infeed logic can be used
(reverse looking zone required)
Permissive Overreach Transfer
Trip - Advantages
 Duplex signalling channel required
 Scheme is theoretically less secure then PUR
as signalling channel is keyed for external
faults
 If signalling channel fails then only Basic
scheme logic will apply
Permissive Overreach Transfer
Trip - Disadvantages
Blocking Schemes
Z3
Z2
Z1
T3
Trip
&
T2
&
Rx
Tx
1
.
Z3
Z3
Z1
Z1
Z2
Z2
Z3
Z2
Z1
T2
T3
Trip
&
T2
&
Rx
Tx
1
.
Blocking Scheme - Internal
Fault
Send Logic : Z3 + Z2
Trip Logic : Rx + Z2
Z3
Z2
Z1
T3
Trip
&
T2
&
Rx
Tx
1
.
Z3
Z3
Z1
Z1
Z2
Z2
Z3
Z2
Z1
T2
T3
Trip
&
T2
&
Rx
Tx
1
.
Blocking Scheme - External
Fault
Send Logic : Z3 + Z2
Trip Logic : Rx + Z2
Blocking Scheme - Advantages
 Only simplex signalling channel required
 Provides better resistive coverage than PUR on
short lines where MHO elements are used
 Fast tripping will still be possible at closed end of
line for all fault positions with remote breaker
open
 Fast tripping will still be possible at strong infeed
terminal for all fault positions where remote
terminal has no or weak infeed
 Only 2 forward zones of protection available
(unless relay has >3 Zones)
 If signalling channel fails then only Basic scheme
logic will apply
 Current sensitivity is lower as tripping elements
(Z2) are controlled by high set current level
detectors (to ensure blocking elements (Z3/Z4)
are more sensitive than tripping elements)
Blocking Scheme -
Disadvantages
 Permissive less reliable - require a signal from
remote relay plus local operation to trip
 Blocking less secure - require a signal from
remote relay to prevent a trip
 Permissive schemes are marginally faster and
more sensitive (timer plus high set current
elements on Blocking scheme)
Permissive Schemes vs
Blocking Schemes
Teed Feeders
B
A
C'
A'
B'
B'
A'
C
A-A’ - Zone 1 reach of relay at A
B-B’ - Zone 1 reach of relay at B
C-C’ - Zone 1 reach of relay at C
A’B’C’ Zone not covered by Zone 1 from any terminal.
Hence schemes reliant on Zone 1 operation would not
work (Z1 ext, PUR)
Teed Feeders - No
Zone 1 Coverage
B
A C
Zc
Zb
Za
Ia Ic
 Actual impedance to fault from terminal A = Za + Zb
 Measured voltage at terminal A V = Ia.Za + (Ia + Ic).Zb
 Measured current at terminal A I = Ia
 Impedance measured by relay A V/I = Za + Zb + (Ic/Ia).Zb
 Relay therefore measures a greater impedance than the actual impedance
and underreaches. Must allow for this underreach when setting Zone 2
elements to ensure correct scheme operation
Teed Feeders -
Underreaching
No infeed from terminal B.
Fault therefore not covered by Zone 1 from any
terminal. Hence schemes reliant on Zone 1
operation would not work (Z1 ext, PUR)
B
A C
Teed Feeders - No/Weak Infeed
at One Terminal
Relay at terminal B sees a reverse fault. No
scheme will operate at this terminal. Fault
clearance will be sequential following opening of
breaker A from relay A Zone 1 element.
B
A C
Teed Feeders - Problems (1)
Directional Earth Fault
(DEF)
 DEF schemes are identical to Distance
schemes
 DEF Forward replaces Zone 2, DEF Reverse
replaces Zone 3/4 Reverse
 No equivalent to Zone 1 as the DEF elements
can not have a defined reach, hence no
schemes using Zone 1 can be replicated (Z1
ext, PUR)
Directional Earth Fault
Schemes
21
Ea E
b
67N
21
RF
Independent
signalling
channel
Independent signalling channels allows the use of
different schemes for the distance and DEF
elements, for example PUR distance with POR DEF
Directional Earth Fault
Schemes
67N
Shared signalling channels limits the use of
schemes for the distance and DEF elements.
Both use the same scheme logic.
Directional Earth Fault
Schemes
21
Ea Eb
67N
21
RF
Shared Channel
67N
Distance Protection Various Reach Schemes.ppt

More Related Content

Similar to Distance Protection Various Reach Schemes.ppt

Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Rohini Haridas
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars PremanandDesai
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. katoAgrey Kato
 
Generator Transformer Protections.
Generator Transformer  Protections.Generator Transformer  Protections.
Generator Transformer Protections.Nischal Popat
 
transmission-line-protection.ppt
transmission-line-protection.ppttransmission-line-protection.ppt
transmission-line-protection.pptssuser0132001
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2Rahaf Waheep
 
DOCUMENT FOR SOTF PROTECTION FINAL
DOCUMENT FOR SOTF PROTECTION FINALDOCUMENT FOR SOTF PROTECTION FINAL
DOCUMENT FOR SOTF PROTECTION FINALEKANANDHAN G
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current ProtectionSARAVANAN A
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)Rohini Haridas
 
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedin
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedinBeginner guide on deployment of earth loopimpedance ss638 submission - linkedin
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedinRay Khan
 
High Performance Printed Circuit Boards - Lecture #3
High Performance Printed Circuit Boards - Lecture #3High Performance Printed Circuit Boards - Lecture #3
High Performance Printed Circuit Boards - Lecture #3Samsung Electro-Mechanics
 
Busbar protection LEC 1
Busbar protection  LEC 1Busbar protection  LEC 1
Busbar protection LEC 1Rahaf Waheep
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear johny renoald
 
Introduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsIntroduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsMd. Rashedul Islam
 

Similar to Distance Protection Various Reach Schemes.ppt (20)

Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
Basic protection and relaying
Basic protection and relayingBasic protection and relaying
Basic protection and relaying
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. kato
 
Generator Transformer Protections.
Generator Transformer  Protections.Generator Transformer  Protections.
Generator Transformer Protections.
 
Pilot protection
Pilot protectionPilot protection
Pilot protection
 
transmission-line-protection.ppt
transmission-line-protection.ppttransmission-line-protection.ppt
transmission-line-protection.ppt
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2
 
DOCUMENT FOR SOTF PROTECTION FINAL
DOCUMENT FOR SOTF PROTECTION FINALDOCUMENT FOR SOTF PROTECTION FINAL
DOCUMENT FOR SOTF PROTECTION FINAL
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
 
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedin
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedinBeginner guide on deployment of earth loopimpedance ss638 submission - linkedin
Beginner guide on deployment of earth loopimpedance ss638 submission - linkedin
 
High Performance Printed Circuit Boards - Lecture #3
High Performance Printed Circuit Boards - Lecture #3High Performance Printed Circuit Boards - Lecture #3
High Performance Printed Circuit Boards - Lecture #3
 
Busbar protection LEC 1
Busbar protection  LEC 1Busbar protection  LEC 1
Busbar protection LEC 1
 
PSPS Notes.pdf
PSPS Notes.pdfPSPS Notes.pdf
PSPS Notes.pdf
 
Carrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdfCarrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdf
 
Carrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdfCarrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdf
 
Terminaters
TerminatersTerminaters
Terminaters
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Introduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsIntroduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basics
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Distance Protection Various Reach Schemes.ppt

  • 4.  Zone 1 set to 80% leaves 2 end zones  Faults in end zone results in instantaneous tripping at one end and time delayed at the other  Time delay may lead to system stability problems  Sequential clearance leaves no dead time for high speed A/R cycle (transient fault becomes permanent)  Longer clearance times - More damage Basic Distance Scheme - Disadvantages
  • 6.  No signalling channel required (may be used as temporary replacement for carrier aided scheme when comms. channel out of service)  Provides fast fault clearance at both ends for a transient fault anywhere along the line length  Allows the use of high speed A/R cycle Zone 1 Extension - Advantages
  • 7.  Tripping can occur for external faults (but will be followed by an autoreclose)  Basic distance scheme logic applies following reclose (i.e. potential for time delayed clearance for permanent faults)  Only suitable to systems where autoreclose is used (for example can not be used on cable circuits) Zone 1 Extension Scheme - Disadvantages
  • 8. Loss of Load Accelerated Trip Z3 Z3 Z1 Z1 Z2 Z2 Z2 .. & .. . Trip & & . 1 . LDA LDB LDC 0 T2 T1 0 T1 = 40ms (allows for slowest pickup of Zone 2) T2 = 18ms (prevents LOL trip for external fault with CB pole scatter)
  • 9.  Fast fault clearance without the need for a signalling channel  Only applicable where 3 phase tripping is used  Only operates for unbalanced faults  Load current (above the current detector settings) must exist prior to the fault to ‘arm’ the scheme  Can be used as back up to signal aided scheme Loss of Load Scheme
  • 11.  Provide high speed clearance for all faults on line (for example current differential)  Do not provide inherent back-up protection SOLUTION IS TO PROVIDE DISTANCE PROTECTION FOR BACK- UP PROTECTION OF ADJACENT LINES WITH AN AIDED TRIPPING SCHEME FOR HIGH SPEED PROTECTION OF WHOLE LINE  Requires the use of an ON/OFF signalling channel between line ends (i.e. HF/VF/Fibre Optic/Radio) Unit Protection Schemes
  • 12.  Acceleration  Transfer tripping – Direct – Permissive Underreach – Permissive Overreach  Blocking Types of Aided Tripping Schemes
  • 14.  All faults anywhere along the protected line can be cleared instantaneously at both line ends  Scheme can be advantageous for protecting 3 terminal lines due to ease of application Direct Transfer Trip - Advantages
  • 15.  A very secure signalling channel is required :- incorrect operation leads to false tripping  Circuit breakers at both line ends must be closed and contribute fault current to obtain high speed fault clearance  If the channel fails only the Basic scheme logic will be provided Direct Transfer Trip - Disadvantages
  • 16. Z3 Z3 Z1 Z1 Z2 Z2 Change Z1 reach Z3 Z1/Z2 1 . T2 Trip T3 Z3 Z1/Z2 1 . T3 T2 Trip Tx Rx Tx Rx 1 . 1 . Send Logic : Z1 Trip Logic : Rx + Z2 Acceleration Scheme (for Reach Stepped Relay)
  • 18. Z3 Z3 Z1 Z1 Z2 Z2 Tx Rx Tx Rx Send Logic : Z1 Trip Logic : Rx + Z2 Z3 Z2 Z1 1 . T2 T3 Trip T2 & Z3 Z2 Z1 1 . T2 T3 Trip T2 & 100 0 100 0 Permissive Underreach Scheme
  • 19. A 21 C B D A C B D Send Fault Fault  Race between relay at D picking up and signal send from relay at C resetting, following opening of breaker at C  If signal send from C resets before relay D operates then aided tripping will not occur  To prevent this a 100ms delay on drop off of the signal send is used in the scheme logic 21 21 21 Permissive Underreach Scheme Rx + Z2 Rx + Z2
  • 20.  Only a simplex signalling channel required  Scheme is very secure as signalling channel only keyed for internal fault (Zone 1 initiation) Permissive Underreach Transfer Trip - Advantages
  • 21.  If one terminal of the line is open then only Basic scheme logic will apply  If there is a weak infeed at one terminal then only Basic scheme logic will apply  If signalling channel fails then only Basic scheme logic will apply  Resistive coverage is governed by Zone 1 setting (may be limited on short lines) Permissive Underreach Transfer Trip - Disadvantages
  • 22. Z3 Z2 Z1 1 . T2 T3 Trip & T2 Z3 Z2 Z1 1 . T2 T3 Trip & T2 Rx Tx Rx Tx Z3 Z3 Z1 Z1 Z2 Z2 Send Logic : Z2 Trip Logic : Rx + Z2 Permissive Overreach Scheme Internal Fault
  • 23. Z3 Z2 Z1 1 . T2 T3 Trip & T2 Z3 Z2 Z1 1 . T2 T3 Trip & T2 Rx Tx Rx Tx Z3 Z3 Z1 Z1 Z2 Z2 Send Logic : Z2 Trip Logic : Rx + Z2 Permissive Overreach Scheme External Fault
  • 24. Z3 Z2 Z1 T2 T3 Trip & T2 Z3 Z2 Z1 T2 T3 Trip & T2 & 1 Rx Tx CB open & 1 Rx Tx CB open Z3 Z3 Z1 Z1 Z2 Z2 1 . 1 . Send Logic : Z2 Trip Logic : Rx + Z2 Open terminal echo : CB Open + Rx Permissive Overreach Scheme (CB Echo Logic)
  • 25. Z4 Z4 Z1 Z1 Z2 Z2 Z3 Z2 Z1 T2 T3 Trip T2 Z3 Z2 Z1 T2 T3 Trip T2 & Z4 CB open & Z4 CB open Send Logic : Z2 Trip Logic : Rx + Z2 Open terminal echo : CB Open + Rx Weak Infeed echo : Z4 + Rx Permissive Overreach Scheme (WI Echo Logic) 1 & & & Rx Tx & Rx Tx 1 . 1 . 1
  • 26. Z4 Z4 Z1 Z1 Z2 Z2 Z3 Z2 Z1 T3 Trip & T2 & LDOV Z3 Z2 Z1 T3 Trip & T2 & LDOV & Rx Tx Z4 CB open & Rx Tx Z4 CB open & & 1 . 1 . 1 1 Send Logic : Z2 Trip Logic : Rx + Z2 Open terminal echo : CB Open + Rx Weak Infeed echo : Z4 + Rx Weak Infeed trip : Z4 + LDOV reset + Rx Permissive Overreach Weak Infeed Trip Scheme
  • 27.  Provides better resistive coverage, especially on short lines, where MHO measuring elements are used  For cases where one line terminal is open, open breaker echo logic can be used  For cases of weak or zero infeed at one line terminal weak infeed logic can be used (reverse looking zone required) Permissive Overreach Transfer Trip - Advantages
  • 28.  Duplex signalling channel required  Scheme is theoretically less secure then PUR as signalling channel is keyed for external faults  If signalling channel fails then only Basic scheme logic will apply Permissive Overreach Transfer Trip - Disadvantages
  • 32. Blocking Scheme - Advantages  Only simplex signalling channel required  Provides better resistive coverage than PUR on short lines where MHO elements are used  Fast tripping will still be possible at closed end of line for all fault positions with remote breaker open  Fast tripping will still be possible at strong infeed terminal for all fault positions where remote terminal has no or weak infeed
  • 33.  Only 2 forward zones of protection available (unless relay has >3 Zones)  If signalling channel fails then only Basic scheme logic will apply  Current sensitivity is lower as tripping elements (Z2) are controlled by high set current level detectors (to ensure blocking elements (Z3/Z4) are more sensitive than tripping elements) Blocking Scheme - Disadvantages
  • 34.  Permissive less reliable - require a signal from remote relay plus local operation to trip  Blocking less secure - require a signal from remote relay to prevent a trip  Permissive schemes are marginally faster and more sensitive (timer plus high set current elements on Blocking scheme) Permissive Schemes vs Blocking Schemes
  • 36. B A C' A' B' B' A' C A-A’ - Zone 1 reach of relay at A B-B’ - Zone 1 reach of relay at B C-C’ - Zone 1 reach of relay at C A’B’C’ Zone not covered by Zone 1 from any terminal. Hence schemes reliant on Zone 1 operation would not work (Z1 ext, PUR) Teed Feeders - No Zone 1 Coverage
  • 37. B A C Zc Zb Za Ia Ic  Actual impedance to fault from terminal A = Za + Zb  Measured voltage at terminal A V = Ia.Za + (Ia + Ic).Zb  Measured current at terminal A I = Ia  Impedance measured by relay A V/I = Za + Zb + (Ic/Ia).Zb  Relay therefore measures a greater impedance than the actual impedance and underreaches. Must allow for this underreach when setting Zone 2 elements to ensure correct scheme operation Teed Feeders - Underreaching
  • 38. No infeed from terminal B. Fault therefore not covered by Zone 1 from any terminal. Hence schemes reliant on Zone 1 operation would not work (Z1 ext, PUR) B A C Teed Feeders - No/Weak Infeed at One Terminal
  • 39. Relay at terminal B sees a reverse fault. No scheme will operate at this terminal. Fault clearance will be sequential following opening of breaker A from relay A Zone 1 element. B A C Teed Feeders - Problems (1)
  • 41.  DEF schemes are identical to Distance schemes  DEF Forward replaces Zone 2, DEF Reverse replaces Zone 3/4 Reverse  No equivalent to Zone 1 as the DEF elements can not have a defined reach, hence no schemes using Zone 1 can be replicated (Z1 ext, PUR) Directional Earth Fault Schemes
  • 42. 21 Ea E b 67N 21 RF Independent signalling channel Independent signalling channels allows the use of different schemes for the distance and DEF elements, for example PUR distance with POR DEF Directional Earth Fault Schemes 67N
  • 43. Shared signalling channels limits the use of schemes for the distance and DEF elements. Both use the same scheme logic. Directional Earth Fault Schemes 21 Ea Eb 67N 21 RF Shared Channel 67N