Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Bob Prieto
In this paper we will look at the cost impact of delay without a change in project scope
or project rework. This condition is most closely associated with general delay as a
result of:



Extended decision making time frames by the project owner
Project wide stop work orders from any of a variety of causes.

No loss of productivity from project disruption has been reflected except in the case
considered at the end of this paper (Figure 13) where lost productivity from retrograde
behavior of the site labor’s learning curve or production curve is specifically considered.
This differs from the so called “measured mile” approach often used in calculating
disruption impacts.
In actual project situations the cause of delay is often associated with changed scope
or rework and disruption and concomitant loss of productivity are real factors. The
simplified analysis presented here is intended to influence project decision making
processes by better dimensioning the cost of delay in establishing evaluation and
decision making time frames. The cost of a lack of timely decision making is seldom
reflected in project governance processes.

“Ask of me anything but time”
- Napoleon

The analyses in this paper have been based on unconstrained labor, equipment and
material factors which would act to further exacerbate the cost of delay. In general this
analysis represents likely minimum costs to be experienced by delay of a project.

© 2014 Bob Prieto

www.pmworldlibrary.net

1
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 1- Monthly Cost of Delay
0.70%
Monthly Cost of Delay

0.60%
0.50%
0.40%
0.30%
0.20%
0.10%

100.00%

95.00%

90.00%

85.00%

80.00%

75.00%

70.00%

65.00%

60.00%

55.00%

50.00%

45.00%

40.00%

35.00%

30.00%

25.00%

20.00%

15.00%

10.00%

5.00%

0.00%

Figure 1 illustrates the monthly cost of delay, at the point in time such a delay occurs,
normalized as a function of the project’s initial estimate and duration. It considers the
impacts of escalation and general condition costs, which persist during the delay period.
In this example escalation throughout the project period was assumed to be
constant. This would represent the general contractor’s view on cost growth
associated with delay, excluding any impacts from disruption including lost learning
curve.
In evaluating the impact of delay, construction progress was assumed to follow a
traditional “S”-curve, with no progress made during the delay period. General conditions
cost were assumed to follow “S”-curve expenditure rates at a level equal to 10% of the
expenditure rate. During the delay period general conditions costs were assumed to
persist at the most recent monthly rate. Escalation was applied to uninstalled balances
for simplicity in modeling.

© 2014 Bob Prieto

www.pmworldlibrary.net

2
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Table 1
Causes of Delay

Timely decision making by owner
Changed owner performance requirements (fit for purpose
redefined)
Intentional delay of project driven by business factors (market
conditions; competing factors requiring management attention;
cash flow or other financial market constraints)
Delayed or withheld regulatory approvals or changed regulatory
requirements
Technical challenges not anticipated
Events anywhere in the supply chain broadly impacting
progress

Figure 1 illustrates that the cost of delay, without disruption or loss of learning curve, is
greatest at the initial stages of the project when the greatest balance to be escalated
remains. The greatest impact actually comes at about 15% of original project duration
as general conditions costs ramp up faster than the remaining value subject to
escalation is reduced. The exact point in time is a function of the shape of the “S”-curve,
assumed escalation rate and general conditions costs.
Figure 2 considers the case where escalation grows throughout the project period.
Overall costs are significantly greater (nearly 2X) and the peak cost is realized
later (25% of original project duration) than that associated with level escalation
throughout the project period. As in Figure 1, the interplay between general conditions
cost, “S”-curve progress and escalation on the uninstalled amounts can be seen. All
other assumptions are consistent with the case illustrated in Figure 1.

© 2014 Bob Prieto

www.pmworldlibrary.net

3
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 2 - Monthly Cost of delay
(Growing Escalation)
1.40%
1.20%
Monthly Cost of delay
1.00%
0.80%
0.60%
0.40%
0.20%
0.00%

Figure 3 illustrates the impact of project delay as a function of when the delay occurs (%
of original project schedule) for the case of declining escalation during the project
period. In this example peak delay cost is shifted to project initiation in part due to
the higher initial escalation rate used in this model (6% declining to 3.5%).

© 2014 Bob Prieto

www.pmworldlibrary.net

4
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 3 - Monthly Cost of Delay
(Decreasing Escalation)
1.20%
Monthly Cost of Delay

1.00%

0.80%

0.60%

0.40%

0.20%

0.00%

Each of these first three cases adopts a cost view akin to that seen by a general
contractor. In reality though, owner’s delay costs are much more and must include the
weighted average cost of the capital they have committed to the project. These next
three cases include the owner’s cost of capital in assessing the total cost of project
delay. All other assumptions are consistent with those associated with Figures 1
through 3. Owner’s cost of capital is assumed to be applied to the installed project value
and thus tracks the project’s cumulative “S”-curve.

© 2014 Bob Prieto

www.pmworldlibrary.net

5
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 4 - Monthly Cost of Delay
with Financing
1.60%
1.40%
1.20%
1.00%
Monthly Cost of Delay with Financing
0.80%
0.60%
0.40%
0.20%
0.00%

Figure 4 relooks at the cost of a month’s delay as a function of when the delay occurs
(as a % of original project schedule) but now including the owner’s cost of finance.
Escalation is level in this case at 3% annually (compounded monthly). The weighted
average cost of capital (WACC) was based on a financing structure consisting of 15%
equity and 85% debt with 15% and 8% annual cost, respectively.
Several significant changes relative to the case illustrated in Figure 1 are important to
note:




Overall cost of delay is significantly higher
Peak delay cost shifts significantly in time to approximately 60% of the projects
original schedule versus a peak at about 15% of the project’s original schedule
when financing costs are not included.
Cost of delay essentially does not reduce over time, rather it rises to just after the
midpoint of construction and remains at a high level as more installed project
cost must be carried until project startup.

© 2014 Bob Prieto

www.pmworldlibrary.net

6
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 5 - Monthly Cost of Delay
with Financing
(Growing Escalation)
2.50%

2.00%

1.50%
Monthly Cost of Delay with Financing
1.00%

0.50%

0.00%

Figure 5 relooks at the case shown in Figure 2 with the owner’s cost of financing
included. The earlier in time that a delay occurs, the more the total project cost
escalates versus an undelayed case. Peak monthly cost of delay is brought forward
versus the levelized escalation example shown in Figure 4 (40% of original project
schedule versus 60%) but still later than that seen in Figure 2 (25% of original project
schedule) where financing costs were excluded. While we do see some drop-off in
project delay cost over time it is not as significant as that reflected in Figure 2.
In this example we can also see the impact of overall higher project escalation versus
Figure 4 with peak values reaching 2.19% versus 1.45% of original project cost per
month of delay.

© 2014 Bob Prieto

www.pmworldlibrary.net

7
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 6 - Monthly Cost of Delay
with Financing
(Decreasing Escalation)

1.90%
1.85%
1.80%

Monthly Cost of Delay with Financing

1.75%
1.70%
1.65%
1.60%
1.55%
1.50%
1.45%
1.40%

Figure 6 updates the case shown in Figure 3 to include the addition of the owner’s cost
of financing during a period of declining escalation. The sawtooth behavior is driven by
step changes in escalation rates that become less significant in driving the overall
shape of the curve as escalation builds. Overall delay costs measurably exceed those
observed in Figure 3.
It is worth directly comparing the monthly cost of delay for levelized escalation and
growing escalation (starting at the same level) with owner’s financing costs included.

© 2014 Bob Prieto

www.pmworldlibrary.net

8
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 7 illustrates the importance of carefully modeling escalation for the entire project
period in order to better appreciate the true cost of delay that may be experienced.

Figure 7 - Monthly Cost of Delay
with Financing
2.50%

2.00%

1.50%

1.00%

0.50%

0.00%

Levelized Escalation

Growing Escalation

The importance of more accurate escalation modeling is particular acute in the first half
of the project period but remains important in all cases considered.
Sensitivity to Delay Duration
Let us return now to the contractor’s perspective where escalation and general
conditions costs are considered but the owner’s cost of finance is not included. Looking
at a project example where escalation is level throughout the project period we can now
test the cost of delay for longer duration delays. In Figure 8, the cost of delay curves are
plotted for two, four and six month delays.

© 2014 Bob Prieto

www.pmworldlibrary.net

9
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 8 - Total Delay Cost
4.50%
4.00%
3.50%
3.00%
2.50%
2.00%
1.50%
1.00%
0.50%
0.00%

2 Month Delay

4 Month Delay

6 Month Delay

Delay costs associated with longer durations are higher, driven by continuing general
conditions costs and an extended escalation period.
Figure 9 provides a different perspective on extended duration delays by looking at the
average monthly cost of delay during the delay period in relation to the cost of a single
month of delay. While these costs have been plotted against original schedule
durations, these delay periods extend measurably beyond the original schedule and
thus the results reflected in Figure 8 are more useful in my view. Importantly, longer
duration delays are more deleterious especially when they occur at later stages of
project execution.

© 2014 Bob Prieto

www.pmworldlibrary.net

10
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 9 - Normalized Monthly Cost of Delay
2.00

1.80

1.60

1.40

1.20

1.00

0.80

1 Month Delay

4 Month Delay

6 Month Delay

Sensitivity to Escalation Rate
We have seen the interplay of extended general conditions costs, escalation on
uninstalled balances and in the case of the owner’s perspective on the cost of delay, the
cost of extended financing period before revenue service. Figure 10 now looks at
sensitivity of the cost of delay to escalation rate. The particular case analyzed assumed
a constant delta between escalation rate and the weighted average cost of capital, in
effect reflecting a “real cost” of money. Escalation was assumed to be level throughout
the project period but a constant 3% escalation rate was used between the time of the
project estimate and the start of the project one year later in all cases.

© 2014 Bob Prieto

www.pmworldlibrary.net

11
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 10 - Sensitivity of Delay Cost to Escalation
Rates
4.00%

3.50%

3.00%

Delay Cost

2.50%

2.00%

1.50%

1.00%

0.50%

0.00%
2%

3%

4%

6%

7%

8%

Escalation %
25%

50%

75%

Three different points of delay have been considered, 25%, 50% and 75% of original
project schedule. As expected, delay costs rise with increasing escalation rates (2% to
8%), with earlier project phases (25%) more sensitive to escalation rate increase
than later project phases (75%). The interplay of general conditions cost, escalation
rate and WACC level influence the level and shape of the delay cost curves at each
project time point.

© 2014 Bob Prieto

www.pmworldlibrary.net

12
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Sensitivity to Schedule Duration
In each of the cases considered to this point an original project schedule of 10 years
was assumed. Figure 11 now looks at the sensitivity of the monthly cost of delay to
original project schedule adopting the owner’s perspective with the cost of finance
included. The difference is significant and acts to highlight the importance of timely
decision making by the owner at all stages of the project. In that many project schedules
are shorter than the 10 years assumed in the prior analyses, the impact of delay is even
greater than that previously outlined.
The relationship of escalation and financing rates creates a maximum impact for a 6
year schedule duration given all other assumptions with a cost of delay approximately
5X what is seen in the 10 year schedule which was used in all prior cases evaluated.
From the owner’s perspective, the point in time at which the delay occurs is less
significant than the original schedule duration of the project.

Figure 11 - Monthly Cost of Delay
(Owner's Perspective)
Cost of 1 Month's Delay to Owner

8.00%
7.00%
6.00%
5.00%
4.00%
3.00%
2.00%
1.00%
0.00%
4

6

8

10

Original Schedule Duration (Years)
25% of Original Schedule

© 2014 Bob Prieto

50% of Original Schedule

www.pmworldlibrary.net

75% of Original Schedule

13
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

The General Contractor’s view of delay cost as a function of original schedule duration
differs from that of the owner since he does not experience the financing costs that the
owner incurs. Figure 12 looks at the comparable delay cost versus schedule duration
from the contractor’s point of view. The absence of financing costs in delay cost
considerations eliminates the duration related maxima observed by the owner. For the
contractor, the cost of a month’s delay decreases as a percentage of original project
cost as project schedule grows in duration.
Unlike the owner, the contractor’s view is more sensitive to when the delay occurs with
early delays being more significant (ignoring impacts on productivity) because of the
higher levels of escalation he experiences. These differing views are reflected in the
contractor’s desire to receive necessary approvals from the owner to proceed full speed
ahead.

Figure 12 - Monthly Cost of Delay
(Contractor's Perspective)
2.00%

Cost of 1 Month's Delay to Owner

1.80%
1.60%
1.40%
1.20%
1.00%
0.80%
0.60%
0.40%
0.20%
0.00%
4

6

8

10

Original Schedule Duration (Years)
25% of Original Schedule

© 2014 Bob Prieto

50% of Original Schedule

www.pmworldlibrary.net

75% of Original Schedule

14
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Estimating the Impact of Delay on Productivity from Retrograde Learning Curve
Estimating the impact of delay on productivity is the subject of extensive research in the
engineering and construction industry. In such estimates principal factors to be
considered include:




The traditional learning curve or production function that best characterizes
uninterrupted productivity improvement as the project progresses
The maximum productivity rates realized as it relates to average productivity
The amount of learning curve and therefore associated productivity rates during
the delay period

For purposes of better dimensioning the cost of delay by including the increased cost
associated with lost productivity from a retrograde learning curve we constructed a
simple model of productivity over the project’s duration. It is not intended to suggest that
this is an accurate representation applicable to all major engineering and construction
projects but rather a reasonable first approximation for purposes of this cost of delayed
decision making analysis. The approach used differs from the so called “measured mile”
approach by specifically including a loss of learning curve during the delay period. For
purposes of this analysis we assumed:



Productivity during the first 5% of the project was at 50% of average productivity
Maximum productivity is 150% of average and was reached at 50% of the project
schedule

Average productivity was calculated as being achieved at 43% of the project’s original
schedule based on the above assumptions
The impact of delay on productivity was calculated as the loss of productivity based on
50% of the difference between the productivity rate at the time the project delay began
and the productivity rate at an earlier period of time determined by subtracting the delay
duration to model a loss of learning curve. This lost productivity factor was then
modeled as increased labor costs over a period of time equal to the delay duration.
Labor costs were assumed to represent 40% of period expenditures based on
experience in the heavy civil industry.
Project delays within the first 5% of project duration were assumed to have no impact
while those after peak production had been reached assumed to decline to values
associated with the period prior to peak production being reached.
© 2014 Bob Prieto

www.pmworldlibrary.net

15
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Figure 13 illustrates the percentage growth in delay cost as viewed by the owner (cost
of financing included) as a function of delay duration and timing. The modest values
reflect the conservative modeling of disruption and an absence of rework or constraints.

Figure 13 - Delay Cost Growth to Owner from
Lost Productivity
105.00%

104.00%

103.00%

102.00%

101.00%

100.00%

1 Month delay

2 Month Delay

4 Month Delay

6 Month Delay

The cost of delay growth experienced by the contractor will be a higher percentage
since it will be added to a smaller cost of delay that ignores growth in financing cost. By
comparison, the contractor will experience a 6.45% growth in the cost of delay at the
midpoint of the original schedule in the case of a 6 month delay. This compares with the
4.37% growth as seen from the owner’s perspective.

“…loose not an hour”
- Nelson

© 2014 Bob Prieto

www.pmworldlibrary.net

16
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

Summary
Timely decision making is essential to effective project execution and lack of strong risk
and cost based governance processes can have significant impacts in overall costs
experienced by both the general contractor and owner. These impacts are a function of
many factors including:









Baseline project cost
General escalation level
Change in escalation rate over the project performance period
Level of general condition costs
Proportion of project costs subject to learning curve effects
Weighted average cost of capital
Delay duration
Point in time when delay occurs

The perspectives of the contractor and owner differ significantly on the total cost of
delay but governance processes intended to promote the owner’s interests would be
well served by adopting the more comprehensive cost view of the owner as described in
this paper.
A $ 4 billion project (not uncommon in the world of large infrastructure and industrial
projects) subject to a delay of one day in decision making would increase an owner’s
cost by $10 million. Was the day lost in decision making worth it?

© 2014 Bob Prieto

www.pmworldlibrary.net

17
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

References
1. The Cost Of Delay And Disruption; Roger Knowles
2. Understanding the causes and consequences of disruption and delay in complex
projects: how system dynamics can help; Susan Howick, Fran Ackermann, Colin
Eden and Terry Williams
3. Delay and Disruption Analysis on Technology-Driven Projects; Clay Ryals;
Navigant
4. Delay, Disruption and Acceleration Costs; Patrick Weaver FAICD, MCIOB, PMP
5. Lost Productivity: Claims for the Cumulative Impact of Multiple Change Orders;
Reginald M. Jones
6. The effects of design changes and delays on project costs; WILLIAMS, Eden,
Ackermann, and Tait (1995); Journal of the Operational Research Society 46, 7,
809-818
7. Use of a Production Function to estimate the impact of work fragmentation on
labor productivity; Gerald H. Williams, Jr.; Construction Research, Inc.
8. The GIGA Factor; Program Management in the Engineering & Construction
Industry; Robert Prieto; CMAA; ISBN 978-1-938014-99-4; 2011

© 2014 Bob Prieto

www.pmworldlibrary.net

18
PM World Journal
Vol. III, Issue II – February 2014
www.pmworldjournal.net

Perspective on the Cost of Delayed Decision Making
in Large Project Execution
Featured Paper
by Bob Prieto

About the Author

Bob Prieto
Senior Vice President
Fluor
Princeton, NJ, USA
Bob Prieto is a senior vice president of Fluor, one of the
largest, publicly traded engineering and construction
companies in the world. He is responsible for strategy for the
firm’s Industrial & Infrastructure group which focuses on the development and delivery
of large, complex projects worldwide. The group encompasses three major business
lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining;
and Industrial Services. Bob consults with owners of large engineering & construction
capital construction programs across all market sectors in the development of
programmatic delivery strategies encompassing planning, engineering, procurement,
construction and financing. He is author of “Strategic Program Management”, “The Giga
Factor: Program Management in the Engineering and Construction Industry” and
“Application of Life Cycle Analysis in the Capital Assets Industry” published by the
Construction Management Association of America (CMAA) and “Topics in Strategic
Program Management” as well as over 475 other papers and presentations.
Bob is a member of the ASCE Industry Leaders Council, National Academy of
Construction and a Fellow of the Construction Management Association of America.
Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific
Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S.
and Asia-Pacific business leaders to shape the framework for trade and economic
growth and had previously served as both as Chairman of the Engineering and
Construction Governors of the World Economic Forum and co-chair of the infrastructure
task force formed after September 11th by the New York City Chamber of Commerce.
Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s
leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.

© 2014 Bob Prieto

www.pmworldlibrary.net

19

More Related Content

What's hot

PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesRicardo Leite
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementShyam Kerkar
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 

What's hot (8)

PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
029 FAST TRACKING CONSTRUCTION
029 FAST TRACKING CONSTRUCTION029 FAST TRACKING CONSTRUCTION
029 FAST TRACKING CONSTRUCTION
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Chap007
Chap007Chap007
Chap007
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Chap006
Chap006Chap006
Chap006
 

Similar to Cost of delayed decision making

Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)FahadHasan36
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Timesproject management
 
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docx
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docxSheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docx
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docxlesleyryder69361
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
Calculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laCalculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laTawnaDelatorrejs
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project ReportRISHABHSIINGH
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementdrdej19
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxRebeccaEdwards88
 

Similar to Cost of delayed decision making (20)

Self Financing Strategy
Self Financing StrategySelf Financing Strategy
Self Financing Strategy
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
PMBOK7-201-300.pdf
PMBOK7-201-300.pdfPMBOK7-201-300.pdf
PMBOK7-201-300.pdf
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docx
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docxSheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docx
Sheet1LMH10090H80M70L605040302010COMPANT ASSESSMENT MATRIXNumberRi.docx
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Communication 1
Communication 1Communication 1
Communication 1
 
Calculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laCalculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the la
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 

Recently uploaded

The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 

Recently uploaded (20)

The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 

Cost of delayed decision making

  • 1. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Perspective on the Cost of Delayed Decision Making in Large Project Execution Bob Prieto In this paper we will look at the cost impact of delay without a change in project scope or project rework. This condition is most closely associated with general delay as a result of:   Extended decision making time frames by the project owner Project wide stop work orders from any of a variety of causes. No loss of productivity from project disruption has been reflected except in the case considered at the end of this paper (Figure 13) where lost productivity from retrograde behavior of the site labor’s learning curve or production curve is specifically considered. This differs from the so called “measured mile” approach often used in calculating disruption impacts. In actual project situations the cause of delay is often associated with changed scope or rework and disruption and concomitant loss of productivity are real factors. The simplified analysis presented here is intended to influence project decision making processes by better dimensioning the cost of delay in establishing evaluation and decision making time frames. The cost of a lack of timely decision making is seldom reflected in project governance processes. “Ask of me anything but time” - Napoleon The analyses in this paper have been based on unconstrained labor, equipment and material factors which would act to further exacerbate the cost of delay. In general this analysis represents likely minimum costs to be experienced by delay of a project. © 2014 Bob Prieto www.pmworldlibrary.net 1
  • 2. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 1- Monthly Cost of Delay 0.70% Monthly Cost of Delay 0.60% 0.50% 0.40% 0.30% 0.20% 0.10% 100.00% 95.00% 90.00% 85.00% 80.00% 75.00% 70.00% 65.00% 60.00% 55.00% 50.00% 45.00% 40.00% 35.00% 30.00% 25.00% 20.00% 15.00% 10.00% 5.00% 0.00% Figure 1 illustrates the monthly cost of delay, at the point in time such a delay occurs, normalized as a function of the project’s initial estimate and duration. It considers the impacts of escalation and general condition costs, which persist during the delay period. In this example escalation throughout the project period was assumed to be constant. This would represent the general contractor’s view on cost growth associated with delay, excluding any impacts from disruption including lost learning curve. In evaluating the impact of delay, construction progress was assumed to follow a traditional “S”-curve, with no progress made during the delay period. General conditions cost were assumed to follow “S”-curve expenditure rates at a level equal to 10% of the expenditure rate. During the delay period general conditions costs were assumed to persist at the most recent monthly rate. Escalation was applied to uninstalled balances for simplicity in modeling. © 2014 Bob Prieto www.pmworldlibrary.net 2
  • 3. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Table 1 Causes of Delay Timely decision making by owner Changed owner performance requirements (fit for purpose redefined) Intentional delay of project driven by business factors (market conditions; competing factors requiring management attention; cash flow or other financial market constraints) Delayed or withheld regulatory approvals or changed regulatory requirements Technical challenges not anticipated Events anywhere in the supply chain broadly impacting progress Figure 1 illustrates that the cost of delay, without disruption or loss of learning curve, is greatest at the initial stages of the project when the greatest balance to be escalated remains. The greatest impact actually comes at about 15% of original project duration as general conditions costs ramp up faster than the remaining value subject to escalation is reduced. The exact point in time is a function of the shape of the “S”-curve, assumed escalation rate and general conditions costs. Figure 2 considers the case where escalation grows throughout the project period. Overall costs are significantly greater (nearly 2X) and the peak cost is realized later (25% of original project duration) than that associated with level escalation throughout the project period. As in Figure 1, the interplay between general conditions cost, “S”-curve progress and escalation on the uninstalled amounts can be seen. All other assumptions are consistent with the case illustrated in Figure 1. © 2014 Bob Prieto www.pmworldlibrary.net 3
  • 4. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 2 - Monthly Cost of delay (Growing Escalation) 1.40% 1.20% Monthly Cost of delay 1.00% 0.80% 0.60% 0.40% 0.20% 0.00% Figure 3 illustrates the impact of project delay as a function of when the delay occurs (% of original project schedule) for the case of declining escalation during the project period. In this example peak delay cost is shifted to project initiation in part due to the higher initial escalation rate used in this model (6% declining to 3.5%). © 2014 Bob Prieto www.pmworldlibrary.net 4
  • 5. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 3 - Monthly Cost of Delay (Decreasing Escalation) 1.20% Monthly Cost of Delay 1.00% 0.80% 0.60% 0.40% 0.20% 0.00% Each of these first three cases adopts a cost view akin to that seen by a general contractor. In reality though, owner’s delay costs are much more and must include the weighted average cost of the capital they have committed to the project. These next three cases include the owner’s cost of capital in assessing the total cost of project delay. All other assumptions are consistent with those associated with Figures 1 through 3. Owner’s cost of capital is assumed to be applied to the installed project value and thus tracks the project’s cumulative “S”-curve. © 2014 Bob Prieto www.pmworldlibrary.net 5
  • 6. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 4 - Monthly Cost of Delay with Financing 1.60% 1.40% 1.20% 1.00% Monthly Cost of Delay with Financing 0.80% 0.60% 0.40% 0.20% 0.00% Figure 4 relooks at the cost of a month’s delay as a function of when the delay occurs (as a % of original project schedule) but now including the owner’s cost of finance. Escalation is level in this case at 3% annually (compounded monthly). The weighted average cost of capital (WACC) was based on a financing structure consisting of 15% equity and 85% debt with 15% and 8% annual cost, respectively. Several significant changes relative to the case illustrated in Figure 1 are important to note:    Overall cost of delay is significantly higher Peak delay cost shifts significantly in time to approximately 60% of the projects original schedule versus a peak at about 15% of the project’s original schedule when financing costs are not included. Cost of delay essentially does not reduce over time, rather it rises to just after the midpoint of construction and remains at a high level as more installed project cost must be carried until project startup. © 2014 Bob Prieto www.pmworldlibrary.net 6
  • 7. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 5 - Monthly Cost of Delay with Financing (Growing Escalation) 2.50% 2.00% 1.50% Monthly Cost of Delay with Financing 1.00% 0.50% 0.00% Figure 5 relooks at the case shown in Figure 2 with the owner’s cost of financing included. The earlier in time that a delay occurs, the more the total project cost escalates versus an undelayed case. Peak monthly cost of delay is brought forward versus the levelized escalation example shown in Figure 4 (40% of original project schedule versus 60%) but still later than that seen in Figure 2 (25% of original project schedule) where financing costs were excluded. While we do see some drop-off in project delay cost over time it is not as significant as that reflected in Figure 2. In this example we can also see the impact of overall higher project escalation versus Figure 4 with peak values reaching 2.19% versus 1.45% of original project cost per month of delay. © 2014 Bob Prieto www.pmworldlibrary.net 7
  • 8. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 6 - Monthly Cost of Delay with Financing (Decreasing Escalation) 1.90% 1.85% 1.80% Monthly Cost of Delay with Financing 1.75% 1.70% 1.65% 1.60% 1.55% 1.50% 1.45% 1.40% Figure 6 updates the case shown in Figure 3 to include the addition of the owner’s cost of financing during a period of declining escalation. The sawtooth behavior is driven by step changes in escalation rates that become less significant in driving the overall shape of the curve as escalation builds. Overall delay costs measurably exceed those observed in Figure 3. It is worth directly comparing the monthly cost of delay for levelized escalation and growing escalation (starting at the same level) with owner’s financing costs included. © 2014 Bob Prieto www.pmworldlibrary.net 8
  • 9. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 7 illustrates the importance of carefully modeling escalation for the entire project period in order to better appreciate the true cost of delay that may be experienced. Figure 7 - Monthly Cost of Delay with Financing 2.50% 2.00% 1.50% 1.00% 0.50% 0.00% Levelized Escalation Growing Escalation The importance of more accurate escalation modeling is particular acute in the first half of the project period but remains important in all cases considered. Sensitivity to Delay Duration Let us return now to the contractor’s perspective where escalation and general conditions costs are considered but the owner’s cost of finance is not included. Looking at a project example where escalation is level throughout the project period we can now test the cost of delay for longer duration delays. In Figure 8, the cost of delay curves are plotted for two, four and six month delays. © 2014 Bob Prieto www.pmworldlibrary.net 9
  • 10. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 8 - Total Delay Cost 4.50% 4.00% 3.50% 3.00% 2.50% 2.00% 1.50% 1.00% 0.50% 0.00% 2 Month Delay 4 Month Delay 6 Month Delay Delay costs associated with longer durations are higher, driven by continuing general conditions costs and an extended escalation period. Figure 9 provides a different perspective on extended duration delays by looking at the average monthly cost of delay during the delay period in relation to the cost of a single month of delay. While these costs have been plotted against original schedule durations, these delay periods extend measurably beyond the original schedule and thus the results reflected in Figure 8 are more useful in my view. Importantly, longer duration delays are more deleterious especially when they occur at later stages of project execution. © 2014 Bob Prieto www.pmworldlibrary.net 10
  • 11. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 9 - Normalized Monthly Cost of Delay 2.00 1.80 1.60 1.40 1.20 1.00 0.80 1 Month Delay 4 Month Delay 6 Month Delay Sensitivity to Escalation Rate We have seen the interplay of extended general conditions costs, escalation on uninstalled balances and in the case of the owner’s perspective on the cost of delay, the cost of extended financing period before revenue service. Figure 10 now looks at sensitivity of the cost of delay to escalation rate. The particular case analyzed assumed a constant delta between escalation rate and the weighted average cost of capital, in effect reflecting a “real cost” of money. Escalation was assumed to be level throughout the project period but a constant 3% escalation rate was used between the time of the project estimate and the start of the project one year later in all cases. © 2014 Bob Prieto www.pmworldlibrary.net 11
  • 12. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 10 - Sensitivity of Delay Cost to Escalation Rates 4.00% 3.50% 3.00% Delay Cost 2.50% 2.00% 1.50% 1.00% 0.50% 0.00% 2% 3% 4% 6% 7% 8% Escalation % 25% 50% 75% Three different points of delay have been considered, 25%, 50% and 75% of original project schedule. As expected, delay costs rise with increasing escalation rates (2% to 8%), with earlier project phases (25%) more sensitive to escalation rate increase than later project phases (75%). The interplay of general conditions cost, escalation rate and WACC level influence the level and shape of the delay cost curves at each project time point. © 2014 Bob Prieto www.pmworldlibrary.net 12
  • 13. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Sensitivity to Schedule Duration In each of the cases considered to this point an original project schedule of 10 years was assumed. Figure 11 now looks at the sensitivity of the monthly cost of delay to original project schedule adopting the owner’s perspective with the cost of finance included. The difference is significant and acts to highlight the importance of timely decision making by the owner at all stages of the project. In that many project schedules are shorter than the 10 years assumed in the prior analyses, the impact of delay is even greater than that previously outlined. The relationship of escalation and financing rates creates a maximum impact for a 6 year schedule duration given all other assumptions with a cost of delay approximately 5X what is seen in the 10 year schedule which was used in all prior cases evaluated. From the owner’s perspective, the point in time at which the delay occurs is less significant than the original schedule duration of the project. Figure 11 - Monthly Cost of Delay (Owner's Perspective) Cost of 1 Month's Delay to Owner 8.00% 7.00% 6.00% 5.00% 4.00% 3.00% 2.00% 1.00% 0.00% 4 6 8 10 Original Schedule Duration (Years) 25% of Original Schedule © 2014 Bob Prieto 50% of Original Schedule www.pmworldlibrary.net 75% of Original Schedule 13
  • 14. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto The General Contractor’s view of delay cost as a function of original schedule duration differs from that of the owner since he does not experience the financing costs that the owner incurs. Figure 12 looks at the comparable delay cost versus schedule duration from the contractor’s point of view. The absence of financing costs in delay cost considerations eliminates the duration related maxima observed by the owner. For the contractor, the cost of a month’s delay decreases as a percentage of original project cost as project schedule grows in duration. Unlike the owner, the contractor’s view is more sensitive to when the delay occurs with early delays being more significant (ignoring impacts on productivity) because of the higher levels of escalation he experiences. These differing views are reflected in the contractor’s desire to receive necessary approvals from the owner to proceed full speed ahead. Figure 12 - Monthly Cost of Delay (Contractor's Perspective) 2.00% Cost of 1 Month's Delay to Owner 1.80% 1.60% 1.40% 1.20% 1.00% 0.80% 0.60% 0.40% 0.20% 0.00% 4 6 8 10 Original Schedule Duration (Years) 25% of Original Schedule © 2014 Bob Prieto 50% of Original Schedule www.pmworldlibrary.net 75% of Original Schedule 14
  • 15. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Estimating the Impact of Delay on Productivity from Retrograde Learning Curve Estimating the impact of delay on productivity is the subject of extensive research in the engineering and construction industry. In such estimates principal factors to be considered include:    The traditional learning curve or production function that best characterizes uninterrupted productivity improvement as the project progresses The maximum productivity rates realized as it relates to average productivity The amount of learning curve and therefore associated productivity rates during the delay period For purposes of better dimensioning the cost of delay by including the increased cost associated with lost productivity from a retrograde learning curve we constructed a simple model of productivity over the project’s duration. It is not intended to suggest that this is an accurate representation applicable to all major engineering and construction projects but rather a reasonable first approximation for purposes of this cost of delayed decision making analysis. The approach used differs from the so called “measured mile” approach by specifically including a loss of learning curve during the delay period. For purposes of this analysis we assumed:   Productivity during the first 5% of the project was at 50% of average productivity Maximum productivity is 150% of average and was reached at 50% of the project schedule Average productivity was calculated as being achieved at 43% of the project’s original schedule based on the above assumptions The impact of delay on productivity was calculated as the loss of productivity based on 50% of the difference between the productivity rate at the time the project delay began and the productivity rate at an earlier period of time determined by subtracting the delay duration to model a loss of learning curve. This lost productivity factor was then modeled as increased labor costs over a period of time equal to the delay duration. Labor costs were assumed to represent 40% of period expenditures based on experience in the heavy civil industry. Project delays within the first 5% of project duration were assumed to have no impact while those after peak production had been reached assumed to decline to values associated with the period prior to peak production being reached. © 2014 Bob Prieto www.pmworldlibrary.net 15
  • 16. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Figure 13 illustrates the percentage growth in delay cost as viewed by the owner (cost of financing included) as a function of delay duration and timing. The modest values reflect the conservative modeling of disruption and an absence of rework or constraints. Figure 13 - Delay Cost Growth to Owner from Lost Productivity 105.00% 104.00% 103.00% 102.00% 101.00% 100.00% 1 Month delay 2 Month Delay 4 Month Delay 6 Month Delay The cost of delay growth experienced by the contractor will be a higher percentage since it will be added to a smaller cost of delay that ignores growth in financing cost. By comparison, the contractor will experience a 6.45% growth in the cost of delay at the midpoint of the original schedule in the case of a 6 month delay. This compares with the 4.37% growth as seen from the owner’s perspective. “…loose not an hour” - Nelson © 2014 Bob Prieto www.pmworldlibrary.net 16
  • 17. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto Summary Timely decision making is essential to effective project execution and lack of strong risk and cost based governance processes can have significant impacts in overall costs experienced by both the general contractor and owner. These impacts are a function of many factors including:         Baseline project cost General escalation level Change in escalation rate over the project performance period Level of general condition costs Proportion of project costs subject to learning curve effects Weighted average cost of capital Delay duration Point in time when delay occurs The perspectives of the contractor and owner differ significantly on the total cost of delay but governance processes intended to promote the owner’s interests would be well served by adopting the more comprehensive cost view of the owner as described in this paper. A $ 4 billion project (not uncommon in the world of large infrastructure and industrial projects) subject to a delay of one day in decision making would increase an owner’s cost by $10 million. Was the day lost in decision making worth it? © 2014 Bob Prieto www.pmworldlibrary.net 17
  • 18. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto References 1. The Cost Of Delay And Disruption; Roger Knowles 2. Understanding the causes and consequences of disruption and delay in complex projects: how system dynamics can help; Susan Howick, Fran Ackermann, Colin Eden and Terry Williams 3. Delay and Disruption Analysis on Technology-Driven Projects; Clay Ryals; Navigant 4. Delay, Disruption and Acceleration Costs; Patrick Weaver FAICD, MCIOB, PMP 5. Lost Productivity: Claims for the Cumulative Impact of Multiple Change Orders; Reginald M. Jones 6. The effects of design changes and delays on project costs; WILLIAMS, Eden, Ackermann, and Tait (1995); Journal of the Operational Research Society 46, 7, 809-818 7. Use of a Production Function to estimate the impact of work fragmentation on labor productivity; Gerald H. Williams, Jr.; Construction Research, Inc. 8. The GIGA Factor; Program Management in the Engineering & Construction Industry; Robert Prieto; CMAA; ISBN 978-1-938014-99-4; 2011 © 2014 Bob Prieto www.pmworldlibrary.net 18
  • 19. PM World Journal Vol. III, Issue II – February 2014 www.pmworldjournal.net Perspective on the Cost of Delayed Decision Making in Large Project Execution Featured Paper by Bob Prieto About the Author Bob Prieto Senior Vice President Fluor Princeton, NJ, USA Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He is responsible for strategy for the firm’s Industrial & Infrastructure group which focuses on the development and delivery of large, complex projects worldwide. The group encompasses three major business lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and Industrial Services. Bob consults with owners of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry” and “Application of Life Cycle Analysis in the Capital Assets Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 475 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com. © 2014 Bob Prieto www.pmworldlibrary.net 19