Project management techniques
2
Conventional methods Network methods
* Gantt bar chart * CPM-critical path method
* Mile stone chart * PERT- Programme
* Line of balance(LOB) Evaluation and
Review
Technique
Intended Learning Outcomes
Define the principles of Line of Balance
Demonstrate the application of LOB
Understand the importance of LOB
Understand the process of applying LOB
3
Line of Balance (LOB)
• Definition
A simple diagram to show location and time at
which a certain crew will be working on a given
operation.
Focuses on balancing the time taken for
individual activities by either re-distribution of
resource or by reducing process waste.
4
Line of Balance (LOB)
 LOB is a Planning methodology to optimize
resources used
LOB is a Good Visual tool that lets us see if a
construction program can be achieved with the
minimum waiting time between tasks
It is primarily used on projects that have
repeated elements like Highways, Pipelines,
High-rise buildings, hotel bedrooms, bridge etc.
5
HISTORY
The LOB scheduling Technique was originated
by the Goodyear Company in the early 1940's
and was developed by the U.S Navy in the early
1950's for the programming and control of
both repetitive projects.
LOB has been applied to resource scheduling
and co-ordination of subcontractors, to a
highway pavement construction project, to
modeling production activities for multi facility
projects and to transportation projects.
6
SCHEDULING WITH LOB
7
Prepare a logic diagram.
 To complete each operation, calculate the estimate of
man hours required.
 Select a buffer time which will lookout against the risk of
interference between operations.
 Calculate the equation outputs targets so as to meet a
given project completion date.
Complete the LOB schedule.
In order to bring more balance schedule, inspect the
schedule and access possible attentive.
8
• The above construction procedure gives a proper LOB
schedule. This basic methodology is to determine the available
resources, and evaluate the construction rates that can be
achieved.
• Consider the example of residential building project, where
five buildings are to be constructed. Following steps explain
how the line of balance technique can be used in scheduling.
• The logic diagram is drawn below showing the different
activities of the construction single building, along with
continuity of work.
Advantages
9
It allows a clear understanding of the amount of
work taking place at a certain time in a specific
place.
It is relatively easier to modify , update and
change the schedule.
 if It allows the better management of sub
contractor and resources.
 It allows problems areas to be identified in
advance.
Disadvantages
10
LOB does not shows critical activities.
A monitoring device; not as easy to use as a
planning device
Limited to production and assembly type
processes.
It could be divided only by location.
It shows only where the problem is, it does not
shows what actual problem is.
Faster planning process
Less tasks
Less links
Faster program creation
Less time to understand & interpret
Easy to try ‘what-if’ scenarios
11
12
Activity-based
Formwork
Floor 1
Reinforcement
Floor 1
Pouring Conc.
Floor 1
Finishing
Floor 1
Formwork
Floor 2
Reinforcement
Floor 2
Pouring Conc.
Floor 2
Finishing
Floor 2
Formwork
Floor 3
Reinforcement
Floor 3
Pouring Conc.
Floor 3
Finishing
Floor 3
Location-based
13
Time
Units
3
2
1
30
.
.
.
.
Superior project control
Easy to interpret
Clear uncomplicated displays
Simple to manage
Easy to monitor
Effortless progress updates
Effective control
14
Three diagrams are used in LOB
1. Production Diagram
Shows the relationships of the activities for a
single unit.
2. Objective Diagram
Used to plot the planned or actual number of
units produced vs. time.
3. Progress Diagram
Shows the number of units for which the
activity has completed . 15
THANK YOU
16

More Related Content

What's hot

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...SANJEEV Wazir
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project managementreachfirst01
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 

What's hot (20)

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Bar chart
Bar chartBar chart
Bar chart
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project management
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Contracts
ContractsContracts
Contracts
 
Construction contract
Construction contract Construction contract
Construction contract
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 

Similar to Line of balance in civil engineering

vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
 
Project management and control
Project management and controlProject management and control
Project management and controlShruti Pendharkar
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdfPabitraMitra3
 

Similar to Line of balance in civil engineering (20)

vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Dk ppt
Dk pptDk ppt
Dk ppt
 
Control techniques
Control techniquesControl techniques
Control techniques
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project management and control
Project management and controlProject management and control
Project management and control
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Line of balance in civil engineering

  • 1. Line Of Balance Presenter Name: Chothani yash (166250306511) jadeja satyadeep (166250306518) Mehta naitik (166250306527) Rathod jaydeep (166250306546) Guided By: CIVIL H.O.D. NATHANI SIR 1
  • 2. Project management techniques 2 Conventional methods Network methods * Gantt bar chart * CPM-critical path method * Mile stone chart * PERT- Programme * Line of balance(LOB) Evaluation and Review Technique
  • 3. Intended Learning Outcomes Define the principles of Line of Balance Demonstrate the application of LOB Understand the importance of LOB Understand the process of applying LOB 3
  • 4. Line of Balance (LOB) • Definition A simple diagram to show location and time at which a certain crew will be working on a given operation. Focuses on balancing the time taken for individual activities by either re-distribution of resource or by reducing process waste. 4
  • 5. Line of Balance (LOB)  LOB is a Planning methodology to optimize resources used LOB is a Good Visual tool that lets us see if a construction program can be achieved with the minimum waiting time between tasks It is primarily used on projects that have repeated elements like Highways, Pipelines, High-rise buildings, hotel bedrooms, bridge etc. 5
  • 6. HISTORY The LOB scheduling Technique was originated by the Goodyear Company in the early 1940's and was developed by the U.S Navy in the early 1950's for the programming and control of both repetitive projects. LOB has been applied to resource scheduling and co-ordination of subcontractors, to a highway pavement construction project, to modeling production activities for multi facility projects and to transportation projects. 6
  • 7. SCHEDULING WITH LOB 7 Prepare a logic diagram.  To complete each operation, calculate the estimate of man hours required.  Select a buffer time which will lookout against the risk of interference between operations.  Calculate the equation outputs targets so as to meet a given project completion date. Complete the LOB schedule. In order to bring more balance schedule, inspect the schedule and access possible attentive.
  • 8. 8 • The above construction procedure gives a proper LOB schedule. This basic methodology is to determine the available resources, and evaluate the construction rates that can be achieved. • Consider the example of residential building project, where five buildings are to be constructed. Following steps explain how the line of balance technique can be used in scheduling. • The logic diagram is drawn below showing the different activities of the construction single building, along with continuity of work.
  • 9. Advantages 9 It allows a clear understanding of the amount of work taking place at a certain time in a specific place. It is relatively easier to modify , update and change the schedule.  if It allows the better management of sub contractor and resources.  It allows problems areas to be identified in advance.
  • 10. Disadvantages 10 LOB does not shows critical activities. A monitoring device; not as easy to use as a planning device Limited to production and assembly type processes. It could be divided only by location. It shows only where the problem is, it does not shows what actual problem is.
  • 11. Faster planning process Less tasks Less links Faster program creation Less time to understand & interpret Easy to try ‘what-if’ scenarios 11
  • 12. 12 Activity-based Formwork Floor 1 Reinforcement Floor 1 Pouring Conc. Floor 1 Finishing Floor 1 Formwork Floor 2 Reinforcement Floor 2 Pouring Conc. Floor 2 Finishing Floor 2 Formwork Floor 3 Reinforcement Floor 3 Pouring Conc. Floor 3 Finishing Floor 3
  • 14. Superior project control Easy to interpret Clear uncomplicated displays Simple to manage Easy to monitor Effortless progress updates Effective control 14
  • 15. Three diagrams are used in LOB 1. Production Diagram Shows the relationships of the activities for a single unit. 2. Objective Diagram Used to plot the planned or actual number of units produced vs. time. 3. Progress Diagram Shows the number of units for which the activity has completed . 15