6. Incident Fundamentals
Tectonic Plates of Japan
‐ 1500 Earthquakes Annually
‐ 10% of the world’s volcano’s
‐
‐
‐
‐
Eurasian Plate
North American Plate
Pacific Plate
Philippine Plate
Fukushima ●
Epicenter of Tōhoku
Earthquake
6
7. Great East Japan Earthquake
o
o
o
o
o
March 11, 2011
Magnitude 9.0
Power fails in northern Japan
Units 1, 2 & 3 shutdown automatically
Units 4, 5 & 6 already shutdown (defueled)
7
8. Tsunami
Friday, March 11th at 14:46
• No significant Rx
damage due to earthquake
•
Diesel generators start
(13 generators total)
•
Emergency core cooling
system initiate
•
Plant is stable
Tsunami Hits NPP at 15:41
• ≈ 50+’ Fukushima NPP
•
•
Cooling Systems
• All cooling systems fail
•
Floods diesel generators
Station blackout
- Only Battery Power
Remains
Steam from decay heat creates high pressure
8
16. Fundamentals of the Emergency
o
o
o
o
o
Phase 1 - Cesium Removal – SARRY System
Phase 2 – Multinuclide Removal
Phase 3 - Strontium Removal
Phase 4 - Groundwater Treatment
Phase 5 - Car Wash
16
18. Phase 1 - The Technical Challenge
Removal of radioisotopes in a Seawater
Solution
Deliver it in less than 8 weeks
Start-up in less than 12 weeks
Ensure its safe!
Dose Rates
Thermal
Operational Safety
Failure means Radioactive Wastewater
into the Pacific Ocean
18
19. Phase 1: The AVANTech Solution
Challenge 1 – Activity Capture
Challenge 2 – Shielding
Engineered Zeolite
Primary Ion Exchange
Distribution Coefficient (Kd) ≈ 2,000 in
seawater
Good Axial Cesium Distribution
Crystalline Silicotitanate
Polishing Ion Exchange
Distribution Coefficient (Kd) > 20,000
Needed to achieve complete activity
removal with a single pass
Axial
Cesium
Loading
Cs Limited to
200,000 Ci
(7.5E+15 Bq)
Integral Shielding
≈ 6” Pb Equiv.
Loaded Wt.:
≈ 23 mt (50,000 lb)
Challenge 3 – Heat Generation
Temperature
Profile
Passive Cooling
Contact Handled
Long Term Storage
855 °F
Centerline
Centerline/ Core
Temperature
Safely Managing 200,000 Curies of Radioactive Material
19
20. Phase 1 – The AVANTech Solution
SARRY
Pipe Racks
SIXMs
Flexible Hoses
H2 Vents
Automatic Alignment
DP (kPad)
Throughput (m3)
Rad Loading (TBq)
Trending
Process Optimizes Media and Decontamination Factor
20
21. The Implementation Challenge
Rigors of Working at the Fukushima Site
Exclusion Zone - 20 to 30 km Around Fukushima Site
21