SlideShare a Scribd company logo
1 of 9
TEST REPORT FOR ALSTOM MAKE MICOM P546 LINE DIFFERENTIAL RELAY
1. RELAY CHARACTERISTICS:
Type No.: MiCOM P546 Designation : **
Model No : P54631NH7M0710M Nominal Current : 1 A
Serial Number : 32178851/06/12 Nominal Voltage :Vn 100- 120 VAC – 50/60 HZ
Make : ALSTOM Aux. Volts : Vx 110-250 VDC 100-240 VAC
Note: This particular relay is configured according to the site schematic provided.
2. CT & VT DATA:
3. PRELIMINARY CHECKS:
4. GENERAL CHECKS
Checking Results
Dry cell battery voltage (Remove battery isolation strip)
Auxiliary voltage value on terminals M2 ( + ) and M1 ( - )
Watchdog contact
when relay OFF
Terminals M11 and M12 Closed
Terminals M13 and M14 Open
Watchdog contact
when relay ON
Terminals M11 and M12 Open
Terminals M13 and M14 Closed
Check if the frequency is set on required value
Healthy relay LED operation check
CT rated primary current set as 2000 A
CT rated secondary current set as 1.0A
Ignd-CT rated primary current set as 2000 A
Ignd-CT rated secondary current set as 1.0A
Rated primary voltage (L-L) set as 132 KV
Rated secondary voltage (L-L) set as 110 V
Case earth installed?
LCD front panel display
Clock set to local time?
5. DISPLAY READINGS
Circuit Injected Value Phases Expected Value
Displayed Value
Primary
Voltage
63.5
Phase A / 0°
Phase B / -120°
Phase C / 120°
VAN 76.21 kV 76.23 kV
VBN 76.21 kV 76.25 kV
VCN 76.21 kV 76.30 kV
VAB 132.0 kV 132.1 kV
VBC 132.0 kV 132.1 kV
VCA 132.0 kV 132.1 kV
Current
1.0 A
Phase A / 0°
Phase B / -120°
Phase C / 120°
IA 2000 A 2002 A
IB 2000 A 1999 A
IC 2000 A 2007 A
IN 0.00 A 10.39 A
Frequency 60.0 Hz - 60.0 Hz 60.0 Hz
MW Va, Vb, Vc = 57.74V
Ia, Ib, Ic =1A
Angle between V&I = 0.0 degree
- 457.3 MVA 458.1 MVA
MVAR - 0.0 MVAR -0.12 MVAr
MVA - 457.3 MW 458.3 MW
6. FUNCTIONAL TESTS
6.1 Current differential bias characteristic (87-1)
Setting:
Item Description Setting
1 IS1 0.20 A
2 Is2 2.0 A
3 K1 30 %
4 K2 150 %
5 T 0 Sec
Pick-up & Time test:-
*NOTE: The Relay will be tested at loopback internal mode
It should be noted that the minimum operating current is related, but not equal to the Is1 SETTING
Consider a single end fed fault with no load but fault current, I:-
|Idiff| = I
|Ibias| = ½I
Assuming |Ibias| < Is2, then, using the equations from section 2.1( from manual ), the relay will operate if:-
|Idiff| > k1.| Ibias| + Is1 or
I > k1.½I + Is1 or
I> Is1 / (1 - 0.5 k1)
The minimum operating current is therefore a function of the Is1 and k1 settings. Since k1 is recommended to be
set to 30%, the minimum operating current will be:-
Imin = 1.176 1s1
I Diff I > ( k1 * I I Bias I+ Is1 )/2 = 0.118 A
Fault Type
Expected Pickup
In Amp
Actual Pickup
In Amp
Drop-off
In Amp
Expected Trip
Time
in m-sec
Actual Trip Time
in m-sec at
2 x I Pickup
A-N 0.118 A 0.120 0.088 <40 ms 31
B-N 0.118 A 0.120 0.089 <40 ms 28
C-N 0.118 A 0.120 0.088 <40 ms 35
Lower slope test (Injected current < Is2)
|Ιdiff| >( k1.| Ιbias| + Ιs1)/2=0.25 A
Bias current
injected in phase
(Amps)
Differential
current injected
in phase
Expected
differential current
for tripping
(Amp)
Measured
value of diff.
current
(Amp)
Expected Trip
Time
in m-sec
Actual Trip Time
in m-sec at
2 x I Pickup
A B C A B C
00 1.0 00 X 00 00 0.25 0.254 <40 ms 32
00 00 1.0 00 X 00 0.25 0.253 <40 ms 28
1.0 00 00 00 00 X 0.25 0.252 <40 ms 29
Upper slope test (Injected current > Is2)
|Ιdiff| > (k2.| Ιbias| - (k2 - k1). Ιs2 + Ιs1)/2=1.15A
Bias current
injected in phase
(Amps)
Differential
current injected
in phase
Expected
differential current
for tripping
(Amp)
Measured
value of diff.
current
(Amp)
Expected Trip
Time
in m-sec
Actual Trip Time
in m-sec at
2 x I Pickup
A B C A B C
00 3.0 00 X 00 00 1.15 1.158 <40 ms 24
00 00 3.0 00 X 00 1.15 1.159 <40 ms 25
3.0 00 00 00 00 X 1.15 1.155 <40 ms 25
7.1 Distance protection (21-1) – Attachments-
Resistive Zone Reach check (quadrilateral characteristics only)
Item Description Checked
1 Print out from FREJA attached
Impedance tolerance: +/- 5% for zone 1 and +/- 10 % for other zones.
PH-E (G) : - Resistive reach: Rn (Ω/Loop) = RGn (Ω)/ (1+Kz).
- Reactive reach: Xn (Ω/Loop) = Zn (Ω) * sin (ΦLG)
- Compensation factor KZ = 1/3((Zo-Z1)/Z1).
- Line impedance ZLG = RLG+J XLG = 1/3(2*ZLph +ZOL)
PH-PH (PH): - Resistive reach: Rphn (Ω/ph) = Rphn (Ω/Loop) / 2.
- Reactive reach: Xn (Ω) = Zn (Ω) * sin (ΦLph).
- Line impedance ZLph = RLph+J XLph.
7.2 Distance OPERATING TIME TESTING:
Item Description Checked
1 Print out from FREJA attached
7.3 Distance protection SCHEME TESTING:
Setting:
§ Aid Dist delay =0.0 m sec
I. Permissive Over Reach Scheme:
Send logic: Carrier Send = Z2 : 34 m sec
Trip logic: Trip = Z2 + CR : 38.0 m sec (Aid Dist Delay + Trip Time = 0+35 msec)
Trip logic: Trip = Z2 w/o CR : 434 m sec
II. Current Reversal Logic Check (Permissive Over Reach Scheme):
§ Apply a reverse / forward fault to check: For All Zone
Fault type t rev guard setting (m sec) t rev guard measured (m sec) (trev+Aid Delay)
Reverse/ forward 70 86 (70+Trip)
Test : Reverse zone in sequence 1, Iin sequence 2 = Z2+ carreier receive
7.4 Distance protection Power Swing Blocking - PSB
Setting : Enable Slow Swing
Blocked zone for Power Swing Blocking Z1-Z2-Z3-Z4 = OK
Power swing blocking delay time
Set Measured
---- ----
7.5 Distance protection Switch On To Fault - SOTF
SOTF BY C.B CLOSING BI:
Zone concerned by SOTE: Z1
SOTF pulse time set = 500 ms
SOTF pulse time measured = 539 ms
Check SOTF work with concerned zone= [ Z1 - OK ]
Check SOTF trip time at fault at Z1 = 24 ms
Check SOTF trip time at fault at Z2 = 436 ms
Check SOTF trip time at fault at Z3 = 835 Sec
Check SOTF trip time at fault at Z4 = 1.228 Sec
Configure BI. (set SOTF) DDB# 488 as CB manual close command to check first state
To measure SOTF pulse time configure BO as SOTF ACTIVE and use it as dual contact
7.6 VT Supervision Test:
7.6.1 Loss of one or two phases test:
Fixed setting V2=10V
-Apply 3 Phase rated voltage (Ur V) with balanced angles.
-Apply 3 Phase rated current (Ir A) with balanced angles.
-for the phase under test start decrease the voltage on one phase and / or two phases
till you get Internal fuse fail (fuse fail without time lag).
- For time test inject voltage more than V2.and stop freja BO. VTF alarm
Fixed setting: V2 = 10 volt, I2> inhibit less than setting.=50 mA
Phase Normal Voltage Pick up Drop off Set Time (Sec) Measured Time (Sec)
One phase 63.5 33.58 35.12
5.0
5.022
Two phase 63.5 33.58 35.10 5.024
- CHECK THE FUSE FAIL BLOCKING BY I2> inhibit (simulate 3 phase voltage to get fuse Fail,
for I2> Apply 3 Phase equal current (Ir A) with balanced angles and increase one phase to get I2 more than the setting
Value it will inhibit fuse fail then decrease again phase till you get fuse fail
-Check the relay trip unblocking during the internal fuse fail by any fault : [ ok ]
Simulate 2 stages: - stage 1; inject 3 phase voltage to get fuse fail and zero current.
- stage 2; inject the same voltage as in stage 1, inject 3 phase current to get a value greater than I2> inhibit.
7.6.2 Loss of all 3 phase voltages under load condition test (detect 3p):
Fixed Setting: a- for fuse fail pick up; V1=10 volts.
b- for fuse fail reset; V1=30 volts.
Pick up (v) Reset (v)
10.0 30.03
Check the blocking of the relay when the general block functions (VT MCB TRIP) is activated [ ok ]
7.7.1 Distance Directional Test:
Fixed Direction Measured Direction
Forward 330° - 150° Forward 329.6 – 149.6
Reverse 150° - 330° Reverse 149.7 – 329.5
7.7.2 Distance Minimum Pick up current Test:
Zones
Current setting for
Phase Fault (mA)
Measured Pick up
current(mA)
Current setting for
Ground Fault (mA)
Measured Pick up
current(mA)
Z1 500 505 250 254
Z2 500 504 250 252
Z3 500 504 250 252
ZP --- --- --- ---
Z4 500 504 250 255
8. Fault Locator Function:
Line Length: 21.51 Km Line impedance: 15.32 Ω ФL: 76.0 degree
Fault Type Fault Impedance Z (Ω) Expected display (km) Actual display (km)
A-N(25)% 3.83 5.38 5.374
A-B(50)% 7.66 10.75 10.76
A-B(75)% 11.49 16.13 16.16
A-B-C(100)% 15.32 21.51 21.44
*We inject Z with line angle
9. Directional earth fault protection - DEF (67N-1)
DEF status : Enabled DEF polarizing : Zero sequence
DEF VNpol set : 5.0 V DEF Forward threshold : 150.0 mA
DEF Char angle : -60° DEF Reverse threshold : 100.0 mA
9.1 Pick up current 3Io:
Phases
Pick-up Current mA Drop-off Current ma
Expected Set
Measured
Expected
Measured
Forward Reverse Forward Reverse
A
±5%
149 101
95% set ±5%
146 97
B 150 100 143 96
C 149 99 145 96
-Apply 3 phase volts of rated value (63.51 volt) with balanced angles.
-for the phase under test start reducing voltage till you get Vn more thane vpolarizing
Apply 3 phase current with balanced angles for the phase under test start increasing current till you get pick-up; then
decrease again till you get reset.
9.2 Directional Test
RCA Angle (Degree) Forward Operating Area (from-to in Degree) Reverse Operating area (from-to in Degree)
-60° 209.3 – 29.8 29.9 – 209.2
9.3 Polarizing Voltage (3V0) Pick up and Drop off Test:
Vn(3V0) setting
Vn (3V0) measured
Pick up Drop off
5.0 V 4.98 4.93
NOTE: -Apply balanced current at 3 phase for phase under testing up slowly till get In more than 3Io setting
-Apply 3 phase volts of rated value (57.73 volt) with balanced angles.
-for the phase under test start reducing voltage till you get pick-up; then increase again till you get reset
9.3 DEF Scheme check:
§ Aid DEF delay = 20 m sec
I. Scheme: permissive over reach
SEND : DEF STFW : 42.0 m sec
DEF AIDED TRIP : DEF STFW + CR : 65.0 m sec
DEF AIDED TRIP : DEF STFW w/o CR: infinity SEC
II. Current Reversal Logic Check (Permissive Over Reach Scheme):
§ Apply a reverse / forward fault to check: t rev guard:
Fault type t rev guard setting (m sec) t rev guard measured (m sec)
Reverse/ forward 20.0 94.0 (DEF Trip+ trev Guard)
Note: This measured value included Delay Time and DEF Pick up time
10. Over Current/ Earth Fault Protection ( Non Directional ) :
10.1 Pickup/Drop off/ Timing Test: Definite Time
Phase Setting Pick up Drop off DT time at 2xpick up
A
1.0 A.& 2.5 Sec
0.999 0.950 2.530
B 0.998 0.950 2.528
C 0.997 0.948 2.522
N 0.25 A.& 2.5 Sec 0.248 0.229 2.520
11. Auto Reclose Start and Block Test
Zone Fault Auto Reclose Start Auto Reclose Block Remarks
ZONE 1
R-N ok X ok
Y-N ok X ok
B-N ok X ok
R-Y X ok ok
Y-B X ok ok
B-R X ok ok
R-Y-B X ok ok
ZONE 2
R-N X ok ok
Y-N X ok ok
B-N X ok ok
R-Y X ok ok
Y-B X ok ok
B-R X ok ok
R-Y-B X ok ok
ZONE 3
R-N X ok ok
Y-N X ok ok
B-N X ok ok
R-Y X ok ok
Y-B X ok ok
B-R X ok ok
R-Y-B X ok ok
ZONE 4
R-N X ok ok
Y-N X ok ok
B-N X ok ok
R-Y X ok ok
Y-B X ok ok
B-R X ok ok
R-Y-B X ok ok
12. Logic Input check:-
Input Terminal Circuit Result
BI-1 E1 − E2 DIFF PROTN. IN OK
BI-2 E3 − E4 DIFF PROTN. OUT OK
BI-3 E5 − E6 DIST RECEIVED OK
BI-4 E7 − E8 DEF RECEIVED OK
BI-5 E9 – E10 DTT FAULTY OK
BI-6 E11 − E12 TELEPROTN. FAULT OK
BI-7 E13 − E14 LR1 SWITCH LOCAL OK
BI-8 E15 − E16 LR1 SWITC REMOTE OK
BI-9 C1 − C2 CB Q0 CLOSED OK
BI-10 C3 − C4 CB Q0 OPEN OK
BI-11 C5 − C6 VT MCB TRIP OK
BI-12 C7 − C8 SET1 VT FUSE FAIL OK
BI-13 C9 – C10 CB MANUAL CLOSE OK
BI-14 C11 − C12 SET2 PROTN. DC FAIL OK
BI-15 C13 − C14 SPARE OK
BI-16 C15 − C16 SPARE OK
BI-17 G1 − G2 SET-1 25A FAULTY OK
BI-18 G3 − G4 SET-1 25A TEST MODE OK
BI-19 G5 − G6 SET-1 94-1 OPTD OK
BI-20 G7 − G8 SET-1 94-1 FAIL OK
BI-21 G9 – G10 DTT RECEIVED OK
BI-22 G11 − G12 TC1 FAULTY OK
BI-23 G13 − G14 SET-1 AC FAIL OK
BI-24 G15 − G16 SPARE OK
13. Output Relay check :
Relay Terminal Contact Circuit Result
RL1 L1 – L2 NO GENTRL TRIP-94-1 OK
RL2 L3 – L4 NO DIST SIGNAL SEND OK
RL3 L5 – L6 NO DEF SIGNAL SEND OK
RL4 L7 – L8 NO A/R START OK
RL5 L9 – L10 NO A/R BLOCK OK
RL6 L11 – L12 NO VT FAIL -25A BLK OK
RL7 L13–L14–L15 C/O DIFF PROTN. IN OK
RL8 L16–L17–L18 C/O DIFF PROTN. OUT OK
RL9 K1 – K2 NO DIFF PROTN. OPTD OK
RL10 K3 – K4 NO DIST PROTN. OPTD OK
RL11 K5 – K6 NO SPARE OK
RL12 K7 – K8 NO SPARE OK
RL13 K9 – K10 NO SPARE OK
RL14 K11 – K12 NO SPARE OK
RL15 K13–K14–K15 C/O SPARE OK
RL16 K16–K17–K18 C/O SPARE OK
RL17 J1 – J2 NO SPARE OK
RL18 J3 – J4 NO SPARE OK
RL19 J5 – J6 NO SPARE OK
RL20 J7 – J8 NO SPARE OK
RL21 J9 – J10 NO SPARE OK
RL22 J11 – J12 NO SPARE OK
RL23 J13–J14–J15 C/O SPARE OK
RL24 J16–J17–J18 C/O SPARE OK
RL25 H1 – H2 NO SPARE OK
RL26 H3 – H4 NO SPARE OK
RL27 H5 – H6 NO SPARE OK
RL28 H7 – H8 NO SPARE OK
RL29 H9 – H10 NO SPARE OK
RL30 H11 – H12 NO SPARE OK
RL31 H13–H14–H15 C/O SPARE OK
RL32 H16–H17–H18 C/O SPARE OK
14. LED check :
Relay Lables Color Status Result
LED1 R-PHASE TRIP RED Latch OK
LED2 Y-PHASE TRIP RED Latch OK
LED3 B-PHASE TRIP RED Latch OK
LED4 DIFF. TRIP RED Latch OK
LED5 ZONE 1 TRIP RED Latch OK
LED6 ZONE DELAYED(Z2/Z3/Z4) TRIP RED Latch OK
LED7 ZONE AIDED TRIP RED Latch OK
LED8 DEF TRIP RED Latch OK
FnKey LED1 O/C or E/F TRIP RED Latch OK
FnKey LED2 DIST SEND RED Latch OK
FnKey LED3 DIST RECEIVE RED Latch OK
FnKey LED4 DEF SEND RED Latch OK
FnKey LED5 DEF RECEIVE RED Latch OK
FnKey LED6 SOTF RED Latch OK
FnKey LED7 POWER SWING RED Latch OK
FnKey LED8 TELE PROTN. FAULTY RED Non - Latch OK
FnKey LED9 VT MCB TRIP / FUSE FAIL RED Non - Latch OK
FnKey LED10 DIFF. BLOCK / COMM FAIL RED Non - Latch OK

More Related Content

What's hot

Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601SARAVANAN A
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]moiz89
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsPower System Operation
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformerSantu Mondal
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
transmission-line-protection.ppt
transmission-line-protection.ppttransmission-line-protection.ppt
transmission-line-protection.pptssuser0132001
 
Differential protection
Differential protectionDifferential protection
Differential protectionRishi Tandon
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
RELAY ETTING CALCULATION REV-A (DG-298).pdf
RELAY ETTING CALCULATION REV-A (DG-298).pdfRELAY ETTING CALCULATION REV-A (DG-298).pdf
RELAY ETTING CALCULATION REV-A (DG-298).pdfJayWin2
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector groupShyamkant Vasekar
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1Siswoyo Edo
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrentmichaeljmack
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protectionsrini09
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 

What's hot (20)

Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformer
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
transmission-line-protection.ppt
transmission-line-protection.ppttransmission-line-protection.ppt
transmission-line-protection.ppt
 
Differential protection
Differential protectionDifferential protection
Differential protection
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
RELAY ETTING CALCULATION REV-A (DG-298).pdf
RELAY ETTING CALCULATION REV-A (DG-298).pdfRELAY ETTING CALCULATION REV-A (DG-298).pdf
RELAY ETTING CALCULATION REV-A (DG-298).pdf
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector group
 
Reactors
ReactorsReactors
Reactors
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrent
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 

Viewers also liked

Cable installation book
Cable installation bookCable installation book
Cable installation bookBHAGWAN PRASAD
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar reportRahul Aman
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignLiving Online
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 

Viewers also liked (7)

Cable installation book
Cable installation bookCable installation book
Cable installation book
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar report
 
360 dgree
360 dgree 360 dgree
360 dgree
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 

Similar to Line Differential - Test report for Alstom make Micom P546 relay

Komponen ecu lm393 d
Komponen ecu lm393 dKomponen ecu lm393 d
Komponen ecu lm393 dRochimunaja
 
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...SANTIAGO PABLO ALBERTO
 
Power Electronics Lab Manual Spring 2017
Power Electronics Lab Manual Spring 2017Power Electronics Lab Manual Spring 2017
Power Electronics Lab Manual Spring 2017Zeeshan Ahmed
 
132kv-substation-settings_compress.pdf
132kv-substation-settings_compress.pdf132kv-substation-settings_compress.pdf
132kv-substation-settings_compress.pdfssuser4d1f4f
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protectionHakim Futra
 
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 New
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 NewOriginal Digital Transistor KRC105 C105M C105 100mA 50V TO-92 New
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 NewAUTHELECTRONIC
 
Original NPN Transistor KRC106M C106 106 TO-92 New KEC
Original NPN Transistor KRC106M C106 106 TO-92 New KECOriginal NPN Transistor KRC106M C106 106 TO-92 New KEC
Original NPN Transistor KRC106M C106 106 TO-92 New KECAUTHELECTRONIC
 
Lab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersLab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersKatrina Little
 
Flyback Converter using PWM IC(LTspice Version)
Flyback Converter using PWM IC(LTspice Version)Flyback Converter using PWM IC(LTspice Version)
Flyback Converter using PWM IC(LTspice Version)Tsuyoshi Horigome
 
uA741 General Purpose Operational Amplifier
uA741 General Purpose Operational AmplifieruA741 General Purpose Operational Amplifier
uA741 General Purpose Operational AmplifierYong Heui Cho
 
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...authelectroniccom
 
238218643 jit final-manual-of-power-elx
238218643 jit final-manual-of-power-elx238218643 jit final-manual-of-power-elx
238218643 jit final-manual-of-power-elxhomeworkping3
 

Similar to Line Differential - Test report for Alstom make Micom P546 relay (20)

Anexo reporte_SEL 487E.pdf
Anexo reporte_SEL 487E.pdfAnexo reporte_SEL 487E.pdf
Anexo reporte_SEL 487E.pdf
 
Komponen ecu lm393 d
Komponen ecu lm393 dKomponen ecu lm393 d
Komponen ecu lm393 d
 
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...
Electrónica: U2510B IC de amplificador de audio y receptor AM / FM para todas...
 
Dc circuit-breaker
Dc circuit-breakerDc circuit-breaker
Dc circuit-breaker
 
Power Electronics Lab Manual Spring 2017
Power Electronics Lab Manual Spring 2017Power Electronics Lab Manual Spring 2017
Power Electronics Lab Manual Spring 2017
 
Datasheet
DatasheetDatasheet
Datasheet
 
132kv-substation-settings_compress.pdf
132kv-substation-settings_compress.pdf132kv-substation-settings_compress.pdf
132kv-substation-settings_compress.pdf
 
Ref 615
Ref 615Ref 615
Ref 615
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protection
 
Datasheet
DatasheetDatasheet
Datasheet
 
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 New
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 NewOriginal Digital Transistor KRC105 C105M C105 100mA 50V TO-92 New
Original Digital Transistor KRC105 C105M C105 100mA 50V TO-92 New
 
Original NPN Transistor KRC106M C106 106 TO-92 New KEC
Original NPN Transistor KRC106M C106 106 TO-92 New KECOriginal NPN Transistor KRC106M C106 106 TO-92 New KEC
Original NPN Transistor KRC106M C106 106 TO-92 New KEC
 
Lab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersLab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational Amplifiers
 
Flyback Converter using PWM IC(LTspice Version)
Flyback Converter using PWM IC(LTspice Version)Flyback Converter using PWM IC(LTspice Version)
Flyback Converter using PWM IC(LTspice Version)
 
Lm555
Lm555Lm555
Lm555
 
uA741 General Purpose Operational Amplifier
uA741 General Purpose Operational AmplifieruA741 General Purpose Operational Amplifier
uA741 General Purpose Operational Amplifier
 
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
 
Spx29300 t 2.5-tr
Spx29300 t 2.5-trSpx29300 t 2.5-tr
Spx29300 t 2.5-tr
 
RT7257E Datasheet PDF
RT7257E Datasheet PDFRT7257E Datasheet PDF
RT7257E Datasheet PDF
 
238218643 jit final-manual-of-power-elx
238218643 jit final-manual-of-power-elx238218643 jit final-manual-of-power-elx
238218643 jit final-manual-of-power-elx
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 

Line Differential - Test report for Alstom make Micom P546 relay

  • 1. TEST REPORT FOR ALSTOM MAKE MICOM P546 LINE DIFFERENTIAL RELAY 1. RELAY CHARACTERISTICS: Type No.: MiCOM P546 Designation : ** Model No : P54631NH7M0710M Nominal Current : 1 A Serial Number : 32178851/06/12 Nominal Voltage :Vn 100- 120 VAC – 50/60 HZ Make : ALSTOM Aux. Volts : Vx 110-250 VDC 100-240 VAC Note: This particular relay is configured according to the site schematic provided. 2. CT & VT DATA: 3. PRELIMINARY CHECKS: 4. GENERAL CHECKS Checking Results Dry cell battery voltage (Remove battery isolation strip) Auxiliary voltage value on terminals M2 ( + ) and M1 ( - ) Watchdog contact when relay OFF Terminals M11 and M12 Closed Terminals M13 and M14 Open Watchdog contact when relay ON Terminals M11 and M12 Open Terminals M13 and M14 Closed Check if the frequency is set on required value Healthy relay LED operation check CT rated primary current set as 2000 A CT rated secondary current set as 1.0A Ignd-CT rated primary current set as 2000 A Ignd-CT rated secondary current set as 1.0A Rated primary voltage (L-L) set as 132 KV Rated secondary voltage (L-L) set as 110 V Case earth installed? LCD front panel display Clock set to local time?
  • 2. 5. DISPLAY READINGS Circuit Injected Value Phases Expected Value Displayed Value Primary Voltage 63.5 Phase A / 0° Phase B / -120° Phase C / 120° VAN 76.21 kV 76.23 kV VBN 76.21 kV 76.25 kV VCN 76.21 kV 76.30 kV VAB 132.0 kV 132.1 kV VBC 132.0 kV 132.1 kV VCA 132.0 kV 132.1 kV Current 1.0 A Phase A / 0° Phase B / -120° Phase C / 120° IA 2000 A 2002 A IB 2000 A 1999 A IC 2000 A 2007 A IN 0.00 A 10.39 A Frequency 60.0 Hz - 60.0 Hz 60.0 Hz MW Va, Vb, Vc = 57.74V Ia, Ib, Ic =1A Angle between V&I = 0.0 degree - 457.3 MVA 458.1 MVA MVAR - 0.0 MVAR -0.12 MVAr MVA - 457.3 MW 458.3 MW 6. FUNCTIONAL TESTS 6.1 Current differential bias characteristic (87-1) Setting: Item Description Setting 1 IS1 0.20 A 2 Is2 2.0 A 3 K1 30 % 4 K2 150 % 5 T 0 Sec Pick-up & Time test:- *NOTE: The Relay will be tested at loopback internal mode It should be noted that the minimum operating current is related, but not equal to the Is1 SETTING Consider a single end fed fault with no load but fault current, I:- |Idiff| = I |Ibias| = ½I Assuming |Ibias| < Is2, then, using the equations from section 2.1( from manual ), the relay will operate if:- |Idiff| > k1.| Ibias| + Is1 or I > k1.½I + Is1 or I> Is1 / (1 - 0.5 k1) The minimum operating current is therefore a function of the Is1 and k1 settings. Since k1 is recommended to be set to 30%, the minimum operating current will be:- Imin = 1.176 1s1 I Diff I > ( k1 * I I Bias I+ Is1 )/2 = 0.118 A Fault Type Expected Pickup In Amp Actual Pickup In Amp Drop-off In Amp Expected Trip Time in m-sec Actual Trip Time in m-sec at 2 x I Pickup A-N 0.118 A 0.120 0.088 <40 ms 31 B-N 0.118 A 0.120 0.089 <40 ms 28 C-N 0.118 A 0.120 0.088 <40 ms 35
  • 3. Lower slope test (Injected current < Is2) |Ιdiff| >( k1.| Ιbias| + Ιs1)/2=0.25 A Bias current injected in phase (Amps) Differential current injected in phase Expected differential current for tripping (Amp) Measured value of diff. current (Amp) Expected Trip Time in m-sec Actual Trip Time in m-sec at 2 x I Pickup A B C A B C 00 1.0 00 X 00 00 0.25 0.254 <40 ms 32 00 00 1.0 00 X 00 0.25 0.253 <40 ms 28 1.0 00 00 00 00 X 0.25 0.252 <40 ms 29 Upper slope test (Injected current > Is2) |Ιdiff| > (k2.| Ιbias| - (k2 - k1). Ιs2 + Ιs1)/2=1.15A Bias current injected in phase (Amps) Differential current injected in phase Expected differential current for tripping (Amp) Measured value of diff. current (Amp) Expected Trip Time in m-sec Actual Trip Time in m-sec at 2 x I Pickup A B C A B C 00 3.0 00 X 00 00 1.15 1.158 <40 ms 24 00 00 3.0 00 X 00 1.15 1.159 <40 ms 25 3.0 00 00 00 00 X 1.15 1.155 <40 ms 25 7.1 Distance protection (21-1) – Attachments- Resistive Zone Reach check (quadrilateral characteristics only) Item Description Checked 1 Print out from FREJA attached Impedance tolerance: +/- 5% for zone 1 and +/- 10 % for other zones. PH-E (G) : - Resistive reach: Rn (Ω/Loop) = RGn (Ω)/ (1+Kz). - Reactive reach: Xn (Ω/Loop) = Zn (Ω) * sin (ΦLG) - Compensation factor KZ = 1/3((Zo-Z1)/Z1). - Line impedance ZLG = RLG+J XLG = 1/3(2*ZLph +ZOL) PH-PH (PH): - Resistive reach: Rphn (Ω/ph) = Rphn (Ω/Loop) / 2. - Reactive reach: Xn (Ω) = Zn (Ω) * sin (ΦLph). - Line impedance ZLph = RLph+J XLph. 7.2 Distance OPERATING TIME TESTING: Item Description Checked 1 Print out from FREJA attached 7.3 Distance protection SCHEME TESTING: Setting: § Aid Dist delay =0.0 m sec I. Permissive Over Reach Scheme: Send logic: Carrier Send = Z2 : 34 m sec Trip logic: Trip = Z2 + CR : 38.0 m sec (Aid Dist Delay + Trip Time = 0+35 msec) Trip logic: Trip = Z2 w/o CR : 434 m sec
  • 4. II. Current Reversal Logic Check (Permissive Over Reach Scheme): § Apply a reverse / forward fault to check: For All Zone Fault type t rev guard setting (m sec) t rev guard measured (m sec) (trev+Aid Delay) Reverse/ forward 70 86 (70+Trip) Test : Reverse zone in sequence 1, Iin sequence 2 = Z2+ carreier receive 7.4 Distance protection Power Swing Blocking - PSB Setting : Enable Slow Swing Blocked zone for Power Swing Blocking Z1-Z2-Z3-Z4 = OK Power swing blocking delay time Set Measured ---- ---- 7.5 Distance protection Switch On To Fault - SOTF SOTF BY C.B CLOSING BI: Zone concerned by SOTE: Z1 SOTF pulse time set = 500 ms SOTF pulse time measured = 539 ms Check SOTF work with concerned zone= [ Z1 - OK ] Check SOTF trip time at fault at Z1 = 24 ms Check SOTF trip time at fault at Z2 = 436 ms Check SOTF trip time at fault at Z3 = 835 Sec Check SOTF trip time at fault at Z4 = 1.228 Sec Configure BI. (set SOTF) DDB# 488 as CB manual close command to check first state To measure SOTF pulse time configure BO as SOTF ACTIVE and use it as dual contact 7.6 VT Supervision Test: 7.6.1 Loss of one or two phases test: Fixed setting V2=10V -Apply 3 Phase rated voltage (Ur V) with balanced angles. -Apply 3 Phase rated current (Ir A) with balanced angles. -for the phase under test start decrease the voltage on one phase and / or two phases till you get Internal fuse fail (fuse fail without time lag). - For time test inject voltage more than V2.and stop freja BO. VTF alarm Fixed setting: V2 = 10 volt, I2> inhibit less than setting.=50 mA Phase Normal Voltage Pick up Drop off Set Time (Sec) Measured Time (Sec) One phase 63.5 33.58 35.12 5.0 5.022 Two phase 63.5 33.58 35.10 5.024 - CHECK THE FUSE FAIL BLOCKING BY I2> inhibit (simulate 3 phase voltage to get fuse Fail, for I2> Apply 3 Phase equal current (Ir A) with balanced angles and increase one phase to get I2 more than the setting Value it will inhibit fuse fail then decrease again phase till you get fuse fail -Check the relay trip unblocking during the internal fuse fail by any fault : [ ok ] Simulate 2 stages: - stage 1; inject 3 phase voltage to get fuse fail and zero current. - stage 2; inject the same voltage as in stage 1, inject 3 phase current to get a value greater than I2> inhibit. 7.6.2 Loss of all 3 phase voltages under load condition test (detect 3p): Fixed Setting: a- for fuse fail pick up; V1=10 volts. b- for fuse fail reset; V1=30 volts. Pick up (v) Reset (v) 10.0 30.03 Check the blocking of the relay when the general block functions (VT MCB TRIP) is activated [ ok ]
  • 5. 7.7.1 Distance Directional Test: Fixed Direction Measured Direction Forward 330° - 150° Forward 329.6 – 149.6 Reverse 150° - 330° Reverse 149.7 – 329.5 7.7.2 Distance Minimum Pick up current Test: Zones Current setting for Phase Fault (mA) Measured Pick up current(mA) Current setting for Ground Fault (mA) Measured Pick up current(mA) Z1 500 505 250 254 Z2 500 504 250 252 Z3 500 504 250 252 ZP --- --- --- --- Z4 500 504 250 255 8. Fault Locator Function: Line Length: 21.51 Km Line impedance: 15.32 Ω ФL: 76.0 degree Fault Type Fault Impedance Z (Ω) Expected display (km) Actual display (km) A-N(25)% 3.83 5.38 5.374 A-B(50)% 7.66 10.75 10.76 A-B(75)% 11.49 16.13 16.16 A-B-C(100)% 15.32 21.51 21.44 *We inject Z with line angle 9. Directional earth fault protection - DEF (67N-1) DEF status : Enabled DEF polarizing : Zero sequence DEF VNpol set : 5.0 V DEF Forward threshold : 150.0 mA DEF Char angle : -60° DEF Reverse threshold : 100.0 mA 9.1 Pick up current 3Io: Phases Pick-up Current mA Drop-off Current ma Expected Set Measured Expected Measured Forward Reverse Forward Reverse A ±5% 149 101 95% set ±5% 146 97 B 150 100 143 96 C 149 99 145 96 -Apply 3 phase volts of rated value (63.51 volt) with balanced angles. -for the phase under test start reducing voltage till you get Vn more thane vpolarizing Apply 3 phase current with balanced angles for the phase under test start increasing current till you get pick-up; then decrease again till you get reset. 9.2 Directional Test RCA Angle (Degree) Forward Operating Area (from-to in Degree) Reverse Operating area (from-to in Degree) -60° 209.3 – 29.8 29.9 – 209.2
  • 6. 9.3 Polarizing Voltage (3V0) Pick up and Drop off Test: Vn(3V0) setting Vn (3V0) measured Pick up Drop off 5.0 V 4.98 4.93 NOTE: -Apply balanced current at 3 phase for phase under testing up slowly till get In more than 3Io setting -Apply 3 phase volts of rated value (57.73 volt) with balanced angles. -for the phase under test start reducing voltage till you get pick-up; then increase again till you get reset 9.3 DEF Scheme check: § Aid DEF delay = 20 m sec I. Scheme: permissive over reach SEND : DEF STFW : 42.0 m sec DEF AIDED TRIP : DEF STFW + CR : 65.0 m sec DEF AIDED TRIP : DEF STFW w/o CR: infinity SEC II. Current Reversal Logic Check (Permissive Over Reach Scheme): § Apply a reverse / forward fault to check: t rev guard: Fault type t rev guard setting (m sec) t rev guard measured (m sec) Reverse/ forward 20.0 94.0 (DEF Trip+ trev Guard) Note: This measured value included Delay Time and DEF Pick up time 10. Over Current/ Earth Fault Protection ( Non Directional ) : 10.1 Pickup/Drop off/ Timing Test: Definite Time Phase Setting Pick up Drop off DT time at 2xpick up A 1.0 A.& 2.5 Sec 0.999 0.950 2.530 B 0.998 0.950 2.528 C 0.997 0.948 2.522 N 0.25 A.& 2.5 Sec 0.248 0.229 2.520 11. Auto Reclose Start and Block Test Zone Fault Auto Reclose Start Auto Reclose Block Remarks ZONE 1 R-N ok X ok Y-N ok X ok B-N ok X ok R-Y X ok ok Y-B X ok ok B-R X ok ok R-Y-B X ok ok ZONE 2 R-N X ok ok Y-N X ok ok B-N X ok ok R-Y X ok ok Y-B X ok ok B-R X ok ok R-Y-B X ok ok
  • 7. ZONE 3 R-N X ok ok Y-N X ok ok B-N X ok ok R-Y X ok ok Y-B X ok ok B-R X ok ok R-Y-B X ok ok ZONE 4 R-N X ok ok Y-N X ok ok B-N X ok ok R-Y X ok ok Y-B X ok ok B-R X ok ok R-Y-B X ok ok 12. Logic Input check:- Input Terminal Circuit Result BI-1 E1 − E2 DIFF PROTN. IN OK BI-2 E3 − E4 DIFF PROTN. OUT OK BI-3 E5 − E6 DIST RECEIVED OK BI-4 E7 − E8 DEF RECEIVED OK BI-5 E9 – E10 DTT FAULTY OK BI-6 E11 − E12 TELEPROTN. FAULT OK BI-7 E13 − E14 LR1 SWITCH LOCAL OK BI-8 E15 − E16 LR1 SWITC REMOTE OK BI-9 C1 − C2 CB Q0 CLOSED OK BI-10 C3 − C4 CB Q0 OPEN OK BI-11 C5 − C6 VT MCB TRIP OK BI-12 C7 − C8 SET1 VT FUSE FAIL OK BI-13 C9 – C10 CB MANUAL CLOSE OK BI-14 C11 − C12 SET2 PROTN. DC FAIL OK BI-15 C13 − C14 SPARE OK BI-16 C15 − C16 SPARE OK BI-17 G1 − G2 SET-1 25A FAULTY OK BI-18 G3 − G4 SET-1 25A TEST MODE OK BI-19 G5 − G6 SET-1 94-1 OPTD OK BI-20 G7 − G8 SET-1 94-1 FAIL OK BI-21 G9 – G10 DTT RECEIVED OK BI-22 G11 − G12 TC1 FAULTY OK BI-23 G13 − G14 SET-1 AC FAIL OK BI-24 G15 − G16 SPARE OK 13. Output Relay check :
  • 8. Relay Terminal Contact Circuit Result RL1 L1 – L2 NO GENTRL TRIP-94-1 OK RL2 L3 – L4 NO DIST SIGNAL SEND OK RL3 L5 – L6 NO DEF SIGNAL SEND OK RL4 L7 – L8 NO A/R START OK RL5 L9 – L10 NO A/R BLOCK OK RL6 L11 – L12 NO VT FAIL -25A BLK OK RL7 L13–L14–L15 C/O DIFF PROTN. IN OK RL8 L16–L17–L18 C/O DIFF PROTN. OUT OK RL9 K1 – K2 NO DIFF PROTN. OPTD OK RL10 K3 – K4 NO DIST PROTN. OPTD OK RL11 K5 – K6 NO SPARE OK RL12 K7 – K8 NO SPARE OK RL13 K9 – K10 NO SPARE OK RL14 K11 – K12 NO SPARE OK RL15 K13–K14–K15 C/O SPARE OK RL16 K16–K17–K18 C/O SPARE OK RL17 J1 – J2 NO SPARE OK RL18 J3 – J4 NO SPARE OK RL19 J5 – J6 NO SPARE OK RL20 J7 – J8 NO SPARE OK RL21 J9 – J10 NO SPARE OK RL22 J11 – J12 NO SPARE OK RL23 J13–J14–J15 C/O SPARE OK RL24 J16–J17–J18 C/O SPARE OK RL25 H1 – H2 NO SPARE OK RL26 H3 – H4 NO SPARE OK RL27 H5 – H6 NO SPARE OK RL28 H7 – H8 NO SPARE OK RL29 H9 – H10 NO SPARE OK RL30 H11 – H12 NO SPARE OK RL31 H13–H14–H15 C/O SPARE OK RL32 H16–H17–H18 C/O SPARE OK 14. LED check : Relay Lables Color Status Result LED1 R-PHASE TRIP RED Latch OK LED2 Y-PHASE TRIP RED Latch OK LED3 B-PHASE TRIP RED Latch OK LED4 DIFF. TRIP RED Latch OK
  • 9. LED5 ZONE 1 TRIP RED Latch OK LED6 ZONE DELAYED(Z2/Z3/Z4) TRIP RED Latch OK LED7 ZONE AIDED TRIP RED Latch OK LED8 DEF TRIP RED Latch OK FnKey LED1 O/C or E/F TRIP RED Latch OK FnKey LED2 DIST SEND RED Latch OK FnKey LED3 DIST RECEIVE RED Latch OK FnKey LED4 DEF SEND RED Latch OK FnKey LED5 DEF RECEIVE RED Latch OK FnKey LED6 SOTF RED Latch OK FnKey LED7 POWER SWING RED Latch OK FnKey LED8 TELE PROTN. FAULTY RED Non - Latch OK FnKey LED9 VT MCB TRIP / FUSE FAIL RED Non - Latch OK FnKey LED10 DIFF. BLOCK / COMM FAIL RED Non - Latch OK