AgileEVM – Earned Value Management in Scrum Projects
Tamara Sulaiman, PMP, CSM Brent Barton, CSM, CST Thomas Blackburn, PMP, CSM
SolutionsIQ SolutionsIQ InfoTech, Inc.
tsulaiman@solutionsiq.com bbarton@solutionsiq.com Thomas.blackburn@infotechfl.com
Abstract
Scrum is an Agile Project Management
Framework. This framework specifically focuses on
maximizing Return on Investment (ROI). Scrum,
however, does not define how to manage and track
costs to evaluate actual ROI against the vision. A
reasonable cost measurement that integrates with
Scrum would help provide an additional feedback
loop.
We adapted Earned Value Management (EVM),
using values defined in Scrum. The result is called
AgileEVM (Agile Earned Value Management) and is
a simplified set of earned value calculations. From
the values in Scrum, we derived a release date
estimate using mean velocity and from this equation,
generated an equivalent equation using traditional
EVM techniques, thus establishing the validity of
using EVM with the Scrum framework. Finally, we
used this technique on two projects to further test our
hypothesis. This investigation also helped us
determine the utility of AgileEVM.
1. Introduction
Scrum is an Agile Project Management
Framework. Many Agile project methods, especially
Scrum, emphasize incremental, multi-level planning
and discourage fully planning software projects down
to the finest level of decomposition in the early
stages. The basis for discouraging big up-front plans
is the amount of inherent ambiguity present in
complex software systems that makes fully defining
the requirements up front nearly impossible. Further,
Scrum focuses on frequently prioritizing
requirements to maximize Return on Investment
(ROI) [1]. In order to evaluate actual ROI, project
costs must evaluated and used to determine whether
release plans have sufficient business value or
additional re-planning is necessary. One challenge of
evaluating ROI is the Scrum framework does not
integrate costs and leaves this up to the implementers
of Scrum.
“Earned Value Management (EVM) [is] a
method for integrating scope, schedule and resources,
and measuring project performance.” [2] This
technique is used in many industries. If we can
validate a way to use this accepted practice on
Scrum, then we have the tools we need to help
provide balanced what-if scenarios for release
planning for scope, schedule and budget. EVM
techniques, however, assume complete planning of a
project to discrete work package levels, then
assigning cost and duration to these packages so
EVM’s utility has been questioned for Agile projects.
To address this, we define Agile Earned Value
Management (AgileEVM), a simplified set of earned
value calculations adapted from traditional EVM
using Scrum metrics. By demonstrating the
mathematical relationship between EVM calculations
and Scrum metrics we intend to prove that Earned
Value Management (EVM) is valid for use on Scrum
projects. It should be noted that while we believe that
these statements hold true for other Agile methods,
we focus only on Scrum projects because that is the
framework used in our research.
To demonstrate the validity and utility of
AgileEVM, we present three main areas: research,
AgileEVM development and implementation on two
projects. First, we review the available literature on
earned value methods to establish the validity of
EVM techniques on software development projects
and to document previous studies applying Earned
Value techniques on Agile projects. Second, we
define terms and a process for using AgileEVM on
Scrum projects and correlated EVM with standard
Scrum burndown methods. Finally, we introduce
AgileEVM in two very different Scrum projects so
we could validate our assumptions.
2. Research
The literature review revealed an abundance of
publications validating the use of EVM for traditional
project management, particularly on defense and
construction projects. In use since the 1960’s, EVM
is a well recognized project management technique;
included in the Project Management Institute’s
PMBOK [2]. We concentrated on publications
relating earned value to software development
projects in general, and relating earned value
specifically to Agile software projects.
In the Spring, 1995 issue of Acquisition
Quarterly, Major David S. Christensen and Daniel V.
Ferens published a paper, “Using Earned Value for
Performance Measurement on Software Development
Projects”[3]. The processes described for obtaining
and using EVM data are clearly based on a
heavyweight, high-ceremony waterfall software
development life cycle.
An early piece by Quentin W. Fleming and Joel
M. Koppelman, "Earned Value Project Management
– A Powerful Tool for Software Projects" [4],
validated the appropriateness of using EVM on
software development projects. In the
aforementioned article and in Earned Value Project
Management (2nd
edition), they reiterated their view
on the appropriateness of EVM for software
engineering projects [5]. The EVM methodology
described is based on exhaustive initial planning,
formal work breakdown structures, detailed work
packages associated with dates and dollars, and
detailed tracking and analysis.
The earliest mention of EVM together with agile
practices was a paper presented by Steven H. Lett of
Lockheed-Martin, at the European SEPG in 1998.
Mr. Lett’s paper, “An Earned Value Tracking System
for Self-Directed Software Teams” [6] describes an
earned value tracking system (EVTS) for self-
directed work teams (SDWT) that involved
traditional project management planning tasks.
Detailed reports from individual team members were
required on a regular basis and involved a metrics
engineer to collate and analyze the data obtained.
In the February, 2003 issue of PMForum [7],
Glen Alleman described a method for an Agile
project manager to use earned value techniques on
iterative projects. The method advocated the use of
‘testable requirements’ and 100% unit test coverage.
At the June 2003 Agile Conference in Salt Lake
City, Glenn Alleman, Micheal Henderson, and Ray
Seggleke presented a paper entitled “Making Agile
Development Work in a Government Contracting
Environment - Using Earned Value to Measure
Velocity” [8]. This large government-contracted
development project mandated earned value
management (EVM). In this paper they describe
introducing agility by using certain Agile methods,
including XP-like engineering practices.
In his book Crystal Clear – A Human Powered
Methodology for Small Teams, Alistair Cockburn
describes the similarity between a "burn up" chart
and an EVM chart [9]. He warns that EVM credits
tasks completed, not necessarily integrated code. He
concludes that the Agile burn up chart provides more
accurate information as to the state of the project than
the earned value chart.
We reviewed the threads from two very active
discussion groups: http://groups.yahoo.com/group/
scrumdevelopment and http://groups.yahoo.com/
groups/agilemanagement. Opinions generally
centered around two themes. There is much debate
about the meaning of the term “value” and confusion
between EVM, business value and economic value.
The second theme considers that EVM techniques
can be used on Scrum projects, but asserts that there
is no tangible utility to using them.
We found the results of the review encouraging,
validating the use of EVM on traditional software
development projects. We found articles describing
the use of Agile practices on software projects using
EVM. What we did not find was conclusive
evidence demonstrating the applicability and value of
using EVM on Agile projects.
3. Development of AgileEVM
Our implementation of AgileEVM concentrates
on measuring progress at the release level, rather than
at the sprint level or at the product level. We feel this
to be the most appropriate way to use earned value
management formulas on agile projects. It is true that
these formulas can easily be used to measure
progress of a project with multiple releases, but this
would require that the backlog of multiple releases be
identified and estimated. An example of where this
may be a good approach would be when each Sprint
has a production release and we want to use
AgileEVM for helping us with the entire product life
cycle.
In comparison with the requirements of
traditional EVM, AgileEVM leverages work items
that are integral to the Scrum process. We measure
progress at the end of each sprint when actual sprint
velocity and actual costs are known. In five key
terms below (see Table 1) Traditional EVM
applications are compared to AgileEVM applications:
Table 1: Comparison of EVM terms
Performance Measurement Baseline (PMB)
Traditional EVM The sum of all work
package schedule estimates
(duration and effort).
AgileEVM Total number of story
points planned for a release
(PRP)
Schedule Baseline - often integrated in PMB
Traditional EVM The sum of all work
packages for each time
period calculated for the
total duration.
AgileEVM The total number of planned
sprints (PS) multiplied by
sprint length.
Budget at Complete (BAC)
Traditional EVM The planned budget for the
release or project.
AgileEVM The planned budget for the
release.
Planned Percent Complete (PPC)
Traditional EVM What % complete did we
expect to be at this point in
the project? Can be a
subjective estimate, or a
calculation of the dollar
value of the cumulative
tasks planned to be
complete by this point in
time divided by the
performance baseline
AgileEVM The number of the current
sprint (n) divided by the
total number of planned
sprints (PS).
Actual Percent Complete (APC)
Traditional EVM The dollar value of work
packages actually
completed divided by total
dollar value of the budget at
complete.
AgileEVM The total number of story
points completed
(potentially shippable
increments) divided by the
total number of story points
planned.
Initial values needed for AgileEVM are
straightforward. The values in Table 2 provide the
ability to create an initial release baseline to measure
progress against.
Table 2: Initial release parameters
Name Definition
BAC The amount budgeted to be spent on the
release
L The length of time for each sprint
PS Total number of sprints planned for the
release
SD The start date for the release.
PRP Total points planned for the release
At the completion of each Sprint, we capture
four data points. This is sufficient to calculate Scrum
metrics and AgileEVM.
Table 3: Sprint data points
Name Definition
n Sprint number - starts at 1
PC Points Completed - The points of work
completed from the Release Backlog during
the Sprint
PA Points Added - The points added (or
subtracted) to the Release Backlog during
the Sprint
SC Sprint Cost - What was spent
Change control in Scrum is managed and
reviewed each Sprint cycle. Upon acceptance of the
work completed in the Sprint and the adjustments to
the release backlog, this can be considered a new
project baseline. No extra weight or ceremony is
imposed on the Scrum process except we explicitly
review the release plan in the context of the budget.
To calculate earned or planned value we must
have an accurate representation of actual and planned
percent complete. Story points, as described in Mike
Cohn's User Stories Applied [10], represent an
estimate of effort and are therefore a valid measure of
percent effort complete. This is especially true if the
release includes testable requirements (Alleman [9])
in the form of Stories that must pass and be accepted
by the Product Owner. We define actual percent
complete, APC, to be the ratio of Story points
completed to Story points planned. We further define
planned percent complete, PPC, to be the ratio of
Sprints completed to Sprints Planned. These are
summarized in Table 4.
Table 4: AgileEVM definitions
Name Definition
PRP
Planned Release Points. See (18) for
further discussion
RPC
Release Points Completed. See (19) for
further discussion
APC
Actual Percent Complete of Release. This
is the ratio of Points completed to Points
planned
PPC Planned percent complete.
We use the following EVM definitions and
equations from the PMBOK: [2]
Table 5: Standard EVM definitions and
equations
Equation Definition
BAC Budgeted Cost at Completion:
This is the initial budget for
the release
AC Actual Cost: This corresponds
to budgeted costs in PV for
release
PV = PPC * BAC Planned Value: (1)
EV = APC * BAC Earned Value (2)
CV = EV - AC Cost Variance (3)
SV = EV - PV Schedule Variance (4)
CPI = EV / AC Cost Performance Index (5)
SPI = EV/PV Schedule Performance
Index
(6)
ETC = 1/CPI *
(BAC – EV)
Estimate To Complete (7)
EAC = AC + ETC Estimate At Complete (8)
4. Demonstrating a Mathematical
Correlation of Scrum Metrics and
EVM Metrics
There is a correlation of the schedule forecasts
using Scrum compared to Estimate at Completion
(EAC) forecasts using EVM. The logical argument
starts with a presentation of the hypothesis and then
proceeds through a derivation of a Release Date (RD)
function. Following this, we derive the Release Date
using mean velocity of Sprints. Finally, we calculate
a release date using EVM from the mean velocity.
Inspecting this result, we validate a reasonable
measure for Actual Percent Complete using EAC,
thus establishing the correlation.
4.1 Hypothesis
Release date estimates using EAC calculations
provided by EVM correlate to Mean velocity
predictions provided by Scrum.
More specifically, let RDm stand for the
calculated Release Date using method m. If the
projected release date based on the mean velocity
(RDv) equals the projected release date based on
EVM (RDEV), then EVM techniques can be used on
Scrum projects to calculate EAC with equal precision
to traditional plan-driven projects described in the
PMBOK (ANSI/PMI 99-001-2004 standard) [2].
Restated, if
RDv = RDEV (9)
then EVM techniques related to EAC can be used on
Scrum projects.
4.2 General Equation of a Release Date
Deriving a release date RDm using any method m,
needs an initial position, let it be named start date
(SD). Then a release date is simply an offset from the
start date. This offset can be determined by the
number of Sprints and the Sprint length. From this
we can define the offset to be the number of sprints
multiplied by the duration of the Sprints. Thus,
LNSDRDm ⋅+= (10)
where N equals the number of Sprints and L equals
the length of each Sprint in calendar days. Note that
(10) assumes equal Sprint lengths. It is
mathematically simpler to limit this discussion to
equal Sprint lengths. Although unusual, Sprint
lengths are occasionally adjusted to accommodate
environmental situations. For these anomalies, one
can, in most cases, redefine the Sprint Length to be
equal to the Greatest Common Factor of the different
Sprint lengths without invalidating this method.
Upon inspection of (10), N is the only variable,
where SD and L are initial parameters that do not
change for a release. Thus, N is the single
independent variable. See Fig. 1: Graph of a release
date.
RDm = f(N) (11)
So RDm is a linear function dependent on N.
RDm = SD +L·N (12)
∑=
+=
n
k
kn PAPRPPRP
1
0
∑=
P
ipPRP
10/25/2005
12/14/2005
2/2/2006
3/24/2006
5/13/2006
7/2/2006
1 2 3 4 5 6 7 8 9 10 11 12 13Number of Sprints (N)
ReleaseDate(RD)
SD
0
f(n) = SD +L·N
Fig. 1: Graph of release date
4.3 Using Mean Velocity to Define the
Equation of a Release Date
Considering (12), we need to define N in terms
of an estimate of how much work can be done per
Sprint. Let v equal the average work completed per
Sprint, which is known as the mean velocity, or often
just velocity. The total number of Sprints N
decreases as velocity increases, so it is inversely
proportional to N. Let W = the total work planned to
be done in the release. Then the total work factored
by the mean velocity equals the total iterations N for
v>0.
v
W
N = (13)
For Sprint n, where n ≥ 1, let
N = n + n' (14)
where n' is the estimated Sprints after n. Also, let W'
be the work to be done in sprints n'. Then (13) can be
rewritten
v
W
n
′
=′ (15)
Combining (14) and (15), then substituting into
(12), we have





 ′
+⋅+=
v
W
nLSDRDv (16)
4.4 Using Mean Velocity to Determine
Sprints Left
Clearly, if there have been no completed Sprints,
an estimate of an initial velocity must be made. Once
underway, measures of actual velocity can be used to
estimate future velocities. Empirical measures, such
as "yesterday's weather," are effective for evaluating
what can be accomplished in Sprint Planning. For
release planning, however, applying the arithmetic
mean to determine the average velocity (work done
per Sprint) is a common practice.
To provide measures for work, we need to
introduce a valuation for sizing Release Backlog
Items (RBI). This allows us to measure how much
work is completed for velocity calculations. The
method for sizing these can be any numerical value.
A few examples are: Story Points, T-Shirt Sizes with
Ideal Team Days applied, Function Points and
Working Days
1
.
For convenience, let us define the units for these
numerical values to be points, abbreviated p. Thus,
for the items in the Release Backlog, there exists a
same-sized set P of point values, P = {p1, p2, p3,…; pi
≥ 0} where the total point value, named Planned
Release Points (PRP) can be calculated as
(17)
Before the inception of any Sprint, when n = 0,
denote the initial Planned Release Points: PRP0. For
each Sprint n, define any new RBI points added PAn
and the points completed PCn. Thus, the total release
points from inception through Sprint n can be
calculated as
(18)
Further, define RPCn as the total release points
completed through Sprint n. This can be calculated
as
∑=
=
n
k
kn PCRPC
1
(19)
Finally, let the number of points remaining at
Sprint n be denoted PRn. This can be found by
subtracting the Completed Release Points from the
Planned Release Points. Thus,
nnn RPCPRPPR −= (20)
We can now redefine W '≡ PRn from (15) , so.
v
PR
n n
=′ (21)
To calculate the number of Sprints left we need
to calculate N. Substituting (21) in (14), we have
v
PR
nN n
+= (22)
1 One needs to be cautious when using values with units such as
time or cost. These can lead to confusion and potential
misinterpretation or miscalculation.
Next, we need a more explicit way to express v
in terms of data we capture. Let n define the nth
Sprint where n>0 and let vn be the velocity of Sprint
n. Then the velocity for Sprint n is the number of
points completed in Sprint n. Thus,
nn PCv = (23)
The arithmetic mean of the velocity v can then be
calculated using the standard equation:
∑=
⋅=
n
k
kv
n
v
1
1
(24)
where n>0.
Substituting (23) into (24) yields:
∑=
⋅=
n
k
kPC
n
v
1
1
(25)
Substituting (20) and (25) into (22) generates the
following equation.
∑⋅
−
+=
=
n
k
k
nn
PC
n
RPCPRP
nN
1
1 (26)
We can simplify this equation by factoring n
from each operand and substituting RPCn from (19).






−+⋅=
n
n
n
n
RPC
RPC
RPC
PRP
nN 1 (27)
This can be immediately simplified to:






⋅=
n
n
RPC
PRP
nN (28)
From the description of Actual Percent Complete
(APC) in Table 4, we can construct APCn as the ratio
of release points completed (RPCn) and total points
(PRPn) for sprint n. Thus, let
n
n
n
PRP
RPC
APC = (29)
or
n
n
n RPC
PRP
APC
=
1
(30)
Substituting (30) into (28) causes the equation to
simplify to:
nAPC
n
N = (31)
Finally, we can calculate the Release Date from
(12) using this simplified formula:






⋅+=
n
v
APC
n
LSDRD (32)
4.5 Deriving a Release Date based on EAC
from RDv
If we can derive an equation in the form of (12)
from (32) for a release date based only on EVM
terms, we will have correlated it to mean velocity.
Considering (31), we can manipulate this equation as
follows.






−+⋅=
n
n
nn APC
APC
APC
n
APC
n 1
1 (33)
and













 −
⋅+⋅=
n
n
n APC
APC
BAC
BAC
n
APC
n 1
1 (34)
But from (2), EV = APC·BAC, so





 −
+⋅=
EV
EVBAC
n
APC
n
n
1 (35)
From (5), CPI = EV / ACn, or EV = CPI · ACn so






⋅
−
+⋅=
nn ACCPI
EVBAC
n
APC
n
1 (36)
From (7), ETC = 1/CPI * (BAC – EV), so






⋅+⋅= ETC
AC
n
APC
n
nn
1
1 (37)
or
( )ETCAC
AC
n
APC
n
n
nn
+⋅= (38)
But, from (8), EAC = AC + ETC, so
nn AC
EAC
n
APC
n
⋅= (39)
That is both (n / APCn) and (n * EAC / ACn) will
calculate total Sprints. Also, for Sprint n we have
equivalent values for determining APCn.
EAC
AC
PRP
RPC
APC n
n
n
n == (40)
Substituting (39) into (32),






⋅⋅+=
n
v
AC
EAC
nLSDRD (41)
Thus we have derived RDv solely in EVM terms
so, let us define RDEV such that RDv = RDEV. Finally,






⋅⋅+=
n
EV
AC
EAC
nLSDRD (42)
5. AgileEVM Test Implementation
With AgileEVM defined, and equipped with a
spreadsheet for tracking purposes, we were ready to
try this out on some test projects. We chose two very
different projects for the initial test set. The goals for
the test were:
1. Validating the correspondence of the
projected release dates by comparing mean
velocity and EVM analysis.
2. Determine if the EVM metrics provided
additional value beyond the established
Scrum metrics for making project decisions.
3. Analyze whether the impact of cost analysis
adds value to technical teams for making
good decisions.
Two projects using the Scrum methodology were
tracked using both the AgileEVM and the burndown
method. These projects have very different
adaptations to the Scrum framework, one utilizing
very short Sprints with a small team, and the other
being a single large team with monthly sprints. Both
projects used story points for estimation purposes. It
is important to note the larger team project is still
active at the time of this writing, however, we feel
the results of tracking the projects for nine months is
sufficiently demonstrative to report. The smaller
team, Project A, has recently been released to
production.
For both projects, a data gathering spreadsheet
was developed to collect the data and perform both
the velocity trend analysis and the AgileEVM
calculations on a Sprint-by-Sprint basis. This method
provided for lightweight data collection along with
easy comparison of the results between the burndown
metrics and the AgileEVM metrics.
Project A is a one-half million dollar web
application project. The team is developing a product
enhancement and therefore is closely monitored by
company management. The collocated team has five
to seven members and is experienced with the Scrum
process. Due to dynamic business requirements,
sprints are one week long. Both the AgileEVM and
Scrum metrics are communicated to the entire team
at the end of each sprint. Key management
stakeholders are presented with the Burndown charts
and AgileEVM metrics on a monthly basis.
Project B is a very large, externally funded
project. The project size is about three million
dollars for the first eighteen month phase. The
Project B team is much larger than usual with 15-18
members, and continues to add team members every
couple of sprints. This team is new to Scrum and
Agile development methods. They are also collocated
for the majority of the day. Sprints are 30 calendar
days long. Unlike Project A, the primary project
guide on Project B is the Scrum Burndown chart, not
the AgileEVM metrics. We were still able to validate
the correspondence of the data but circumstances
limited our ability to interpret decision support value.
5.1 AgileEVM Test Results
Our analysis of the data from both projects
demonstrated indistinguishable results between the
predicted release dates using the mean velocity
method and the earned value method (see Fig. 2 and
Fig. 3). This result was as expected; following the
mathematical analysis proving that these two
formulas are equivalent. We also tracked release date
projections based upon atypical calculations for EAC
[2]. We noticed that in the early Sprints, the atypical
calculations provided more realistic predictions. This
is consistent with the nature of discovery inherent in
Agile projects.
The velocity of both projects fluctuated each
Sprint. Project A had cyclic velocity with several
highs and lows (see Fig 4: Project A velocity).
Project B started stabilizing about Sprint 5 (see Fig.
5: Project B velocity). Because of the fluctuations in
velocity, the mean varies considerably from the
actual velocity for some Sprints; though comparing
the predicted release dates to the burndown charts
demonstrates a close relationship.
Project A Release Date Projection Com parisons
7/17/2005
9/5/2005
10/25/2005
12/14/2005
2/2/2006
3/24/2006
5/13/2006
7/2/2006
8/21/2006
10/10/2006
11/29/2006
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
Sprints Com pleted for RD estim ate
EstimatedRD
Plan
Mean Velocity
Estim ate at Complete
EAC (atypical)
Fig. 2: Project A release date projections
Project B Release Date Projection Com parisons
3/24/2006
7/2/2006
10/10/2006
1/18/2007
4/28/2007
8/6/2007
11/14/2007
2/22/2008
6/1/2008
9/9/2008
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Sprints Com pleted for RD estim ate
EstimatedRD
Plan
Mean Velocity
Estim ate at Com plete
EAC (atypical)
Fig. 3: Project B release date projections
The combined burndown and performance index
charts provide evidence of the additional value
provided by AgileEVM. Consider Project A (see
Fig. 6: Project A Burndown, CPI, and SPI). This
project had a 30% budget buffer and the CPI index
clearly shows the erosion of this buffer that the
burndown doesn't recognize. Adjusting the planned
release date in Project A at the end of Sprint 21
caused the SPI to move from an index value of 0.7 to
0.97 (see Fig. 2 and Fig. 6). This aligned the planned
and projected release dates along with the AgileEVM
indicators.
Project B has been adjusting scope down. The
SPI and CPI is registering the potential ROI of
reducing scope in Sprint nine (see Fig. 7: Project B
Burndown, CPI, and SPI). This scope reduction is
demonstrated by comparing the flattening velocity of
Sprints six through nine to the indices (see Fig. 5:
Project B velocity). Note that the same result can
also be interpreted by evaluating the burndown graph
and the velocity. This action of reducing scope has
kept the cost and schedule constraints within current
expectations.
The data also showed strong correlation in the
cost information provided by AgileEVM and manual
planning calculations. Given the expected behavior
of the indices in traditional EVM, it is clear that the
CPI, SPI and EAC behaved as expected given the
budget, schedule, and scope.
Pro ject A Velocity
0
20
40
60
80
100
120
140
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
Sprint
PointsCompleted
Velocity
Mean Velocity
Fig. 4: Project A velocity
Project B Velocity
0
50
100
150
200
250
300
350
400
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
S print
PointsCompleted
Velocity
M ean V elocity
Fig. 5: Project B velocity
An interesting aspect is the way the information
was used on Project A. The metrics providing the
most value to team members and management were
the CPI, SPI, and EAC. These metrics were
requested by both executive management and team
members alike. Given that significant change is
expected on an Agile project, it was necessary to
remind team members and management that the
forecast release date, percent complete, Effort To
Complete and Estimate At Complete are based on
what is actual “right now”. This is exactly the same
as with the burndown method.
Executive management was comfortable with the
AgileEVM metrics and found them useful in making
decisions concerning the direction of the product.
Reviewing this data helped them validate decisions
and the need for process change.
5.2 The Agility of AgileEVM
A key question of the usefulness of AgileEVM is
the level of agility. Would the implementation of the
method add "drag" to a Scrum team’s velocity? If so,
would the impact to velocity outweigh the added
value of the information?
Project A B urn do w n an d Ind ices
0
100
200
300
400
500
600
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
Sprint
PointsRemaining
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
IndexValue
Burndown
CPI
SPI
Fig. 6: Project A Burndown, CPI, SPI
Project B B urn do w n an d Ind ices
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Sprint
PointsRemaining
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
IndexValue
Burndown
CPI
SPI
Fig. 7: Project B Burndown, CPI, SPI
The question was posed to the team on Project
A: "Did the process of collecting or calculating the
AgileEVM metrics add weight to the project?" The
answer was a resounding, "No! The data used in
AgileEVM is data that is already available. The
calculation and tracking of the metrics was automated
in the spreadsheet that the ScrumMaster maintained.
Communication of the metrics to the project team
was as easy as posting the results on the wall, and
having the information available during the project
retrospective discussions."
Most of the developers reacted positively to the
availability of the data, feeling that if an analysis was
needed in order to determine a cause of a certain
issue, like a sudden loss in velocity, the data is
readily available to review. The team was able to
quickly identify changes in key metrics, and this
aided in the continuous improvement of the team.
The Product Owners for both projects felt that
the AgileEVM metrics did not provide any more
schedule insight than the burndown chart provided.
It is interesting to note that the Product Owners for
these projects do not have budget responsibility. We
agree that without the need to manage cost
performance, AgileEVM does not add significant
value above traditional burndown methods.
The ScrumMaster/project manager for Project A,
who does have budget responsibility, found the data
particularly useful for validating project status,
tracking and forecasting potential budget issues,
identifying alternative strategies by running "what if"
scenarios using AgileEVM to predict results, as well
as communicating status and issues with the product
owner and management. .
The ScrumMaster/project manager on Project B
did not use or report the AgileEVM metrics, nor were
the metrics shared with team members or
management stakeholders. Data was collected,
analyzed and compared to actual results without
impacting the team. The very fact that the process of
collecting and calculating the data did not impose on
the team at all gives further credence to the view that
the AgileEVM process passes the agility test.
6. Conclusions
In researching the validity and value of using
EVM on scrum projects several key questions needed
to be answered. First, are the metrics valid for Scrum
projects? Second, is the process lightweight? Third,
do the resulting metrics add value?
Assuming that the burndown trend analysis is
valid for Agile projects, we have shown
mathematically that the calculations for Release date
using Estimate At Complete and calculations for
Release date using the burndown trend analysis are
the same. Empirically, we have tracked the results of
two projects and have shown the indistinguishable
results of the data generated from both methods. We
feel that the validity of the AgileEVM techniques is
established.
The implementation of the AgileEVM process
has no noticeable impact on a Scrum team’s velocity.
Also, the value of the data was confirmed by the team
who had access to the metrics, as well as the
ScrumMaster and management stakeholders for the
project. Thus, we are encouraged that the AgileEVM
metrics do indeed add value to Scrum projects.
For the ScrumMaster, it is clear that metrics that
are familiar go a long way to ease the discomfort that
new, unfamiliar methodologies can induce. The
analysis that AgileEVM provides, along with the
burndown method, helps to substantiate intuition and
provides executives with quantitative data in a
consistent manner. The cost analysis, with its
forecast Estimate at Complete and Estimate to
Complete are valuable to Agile stakeholders
calculating estimated ROI. Agile stakeholders who
are responsible for making budget decisions find this
information extremely valuable.
Our recommendation is that AgileEVM be used
in conjunction with the Burndown chart and team
velocity as supporting data. One important caveat is
that change is expected on Agile projects and so the
AgileEVM metrics are derived from what is true at
each Sprint boundary.
Providing the team and Agile stakeholders with
useful and understandable data is vital to the "rudder"
with which the Scrum team steers toward better
processes and continuous improvement. By
providing the burndown and AgileEVM metrics
together, the team is better equipped to succeed.
References
[1] Schwaber Ken, Agile Project Management with
Scrum, Microsoft Press, Redmond, WA, 2004.
[2] “Guide to the Project Management Body of
Knowledge - PMBOK® Guide 2003 Edition”, Project
Management Institute, Pennsylvania, 2003.
[3] David S. Christiansen, Daniel V. Ferens, “Using
Earned Value for Performance Measurement on Software
Development Projects, Acquisition Review Quarterly,
DAU Press, Fort Belvoir, Virginia, Spring 1995, pgs 155 –
170,
http://www.suu.edu/faculty/christensend/EVonSWprojects.
pdf.
[4] Fleming, C.D., Koppelman, Joel M. Koppelman,
Earned Value Project Management – 2nd Edition, Project
Management Institute, Newtown Square, Pennsylvania,
2000.
[5] Quentin Fleming and Joel Koppelman, “Earned Value
Project Management – A Powerful Tool for Software
Projects”, Crosstalk - The Journal of Defense Software
Engineering, Ogden, UT, July 1998.
http://www.stsc.hill.af.mil/crosstalk/1998/07/value.asp
[6] Stephen H. Lett, “An Earned Value Tracking System
for Self-Directed Software Teams", European SEPG 98,
Conference Proceedings, 1998,
http://www.benchmarkqa.com/PDFs/software_teams.pdf.
[7] Glen B. Alleman, “Project Management == Herding
Cats, A Field Report, Agile Project Management”’
PMFORUM, PMFORUM.ORG, February 2003,
http://www.pmforum.org/viewpoints/2003/0203agilepm.ht
m
[8] Glen B Alleman and Michael Henderson, “Making
Agile Development Work in a Government Contracting
Environment – Using Earned Value to Measure Velocity,
Agile Development , Salt Lake City, Utah, June 25 – 27,
2003.
http://www.niwotridge.com/PDFs/ADC%20Final.pdf
[9] Cockburn, Alastair, Crystal Clear: A Human-Powered
Methodology for Small Teams, Pearson Education Inc.
Upper Saddle River, NJ, 2005
[10] Cohn Mike, User Stories Applied: For Agile Software
Development, Pearson Education, Inc. Boston, MA, 2004.
[11] Cohn Mike, Agile Estimating and Planning, Pearson
Education, Inc. Boston, MA, November 2006.
[12] Glen B Alleman, Nine Best Practices, The Software
Management Framework, 3 June 1999.
[13] David Christensen, “The Estimate At Completion
Problem: A Review of Three Studies,” Project
Management Journal, Project Management Institute, March
1993 pp24:37-42.
[14] David S Christensen, Ph.D., “Determining An
Accurate Estimate At Completion”, National Contract
Management Journal, Arlington MA, 1993, pp 25:17-25.

More Related Content

What's hot

Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzerGlen Alleman
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Glen Alleman
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resourcesGlen Alleman
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)Glen Alleman
 
Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Glen Alleman
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based PlanningGlen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contractsGlen Alleman
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Glen Alleman
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsGlen Alleman
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsGlen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Glen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Failure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementFailure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementGlen Alleman
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management HandbookGlen Alleman
 

What's hot (20)

Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzer
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
 
Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)Building work packages from requirements (from mm)(larger version)
Building work packages from requirements (from mm)(larger version)
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Failure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementFailure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value Management
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 

Similar to Agile evm earned value management in scrum projects

Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Agile Prediction Model EASE 2016 V2
Agile Prediction Model EASE 2016 V2Agile Prediction Model EASE 2016 V2
Agile Prediction Model EASE 2016 V2Mathieu Carsique
 
A Recent Encounter
A Recent EncounterA Recent Encounter
A Recent EncounterGlen Alleman
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...Glen Alleman
 
A new model for software costestimation
A new model for software costestimationA new model for software costestimation
A new model for software costestimationijfcstjournal
 
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCH
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCHA NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCH
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCHijfcstjournal
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticDIPESH30
 
Web Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationWeb Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationNosheen Qamar
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
6 Contracts And Scenarios In The Software Development Process
6 Contracts And Scenarios In The Software Development Process6 Contracts And Scenarios In The Software Development Process
6 Contracts And Scenarios In The Software Development ProcessDarian Pruitt
 
D0365030036
D0365030036D0365030036
D0365030036theijes
 
Enterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC GroupEnterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC GroupEPC Group
 

Similar to Agile evm earned value management in scrum projects (20)

Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Agile Prediction Model EASE 2016 V2
Agile Prediction Model EASE 2016 V2Agile Prediction Model EASE 2016 V2
Agile Prediction Model EASE 2016 V2
 
A Recent Encounter
A Recent EncounterA Recent Encounter
A Recent Encounter
 
DPPM1
DPPM1DPPM1
DPPM1
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...
 
A new model for software costestimation
A new model for software costestimationA new model for software costestimation
A new model for software costestimation
 
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCH
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCHA NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCH
A NEW MODEL FOR SOFTWARE COSTESTIMATION USING HARMONY SEARCH
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 
Web Engineering - Web Effort Estimation
Web Engineering - Web Effort EstimationWeb Engineering - Web Effort Estimation
Web Engineering - Web Effort Estimation
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
6 Contracts And Scenarios In The Software Development Process
6 Contracts And Scenarios In The Software Development Process6 Contracts And Scenarios In The Software Development Process
6 Contracts And Scenarios In The Software Development Process
 
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
 
D0365030036
D0365030036D0365030036
D0365030036
 
Enterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC GroupEnterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC Group
 

More from JULIO GONZALEZ SANZ

Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
Cmmi hm 2008 sepg model changes for high maturity  1v01[1]Cmmi hm 2008 sepg model changes for high maturity  1v01[1]
Cmmi hm 2008 sepg model changes for high maturity 1v01[1]JULIO GONZALEZ SANZ
 
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]JULIO GONZALEZ SANZ
 
Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]JULIO GONZALEZ SANZ
 
Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]JULIO GONZALEZ SANZ
 
The need for a balanced measurement system
The need for a balanced measurement systemThe need for a balanced measurement system
The need for a balanced measurement systemJULIO GONZALEZ SANZ
 
Just in-time and lean production
Just in-time and lean productionJust in-time and lean production
Just in-time and lean productionJULIO GONZALEZ SANZ
 
History of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrHistory of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrJULIO GONZALEZ SANZ
 
Une 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioUne 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioJULIO GONZALEZ SANZ
 
An architecture for data quality
An architecture for data qualityAn architecture for data quality
An architecture for data qualityJULIO GONZALEZ SANZ
 
Sap analytics creating smart business processes
Sap analytics   creating smart business processesSap analytics   creating smart business processes
Sap analytics creating smart business processesJULIO GONZALEZ SANZ
 
Big data analytics, research report
Big data analytics, research reportBig data analytics, research report
Big data analytics, research reportJULIO GONZALEZ SANZ
 

More from JULIO GONZALEZ SANZ (20)

Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
Cmmi hm 2008 sepg model changes for high maturity  1v01[1]Cmmi hm 2008 sepg model changes for high maturity  1v01[1]
Cmmi hm 2008 sepg model changes for high maturity 1v01[1]
 
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
Cmmi%20 model%20changes%20for%20high%20maturity%20v01[1]
 
Cmmi 26 ago_2009_
Cmmi 26 ago_2009_Cmmi 26 ago_2009_
Cmmi 26 ago_2009_
 
Creation use-of-simple-model
Creation use-of-simple-modelCreation use-of-simple-model
Creation use-of-simple-model
 
Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]Introduction to bayesian_networks[1]
Introduction to bayesian_networks[1]
 
Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]Workshop healthy ingredients ppm[1]
Workshop healthy ingredients ppm[1]
 
The need for a balanced measurement system
The need for a balanced measurement systemThe need for a balanced measurement system
The need for a balanced measurement system
 
Magic quadrant
Magic quadrantMagic quadrant
Magic quadrant
 
6 six sigma presentation
6 six sigma presentation6 six sigma presentation
6 six sigma presentation
 
Volvo csr suppliers guide vsib
Volvo csr suppliers guide vsibVolvo csr suppliers guide vsib
Volvo csr suppliers guide vsib
 
Just in-time and lean production
Just in-time and lean productionJust in-time and lean production
Just in-time and lean production
 
History of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfrHistory of manufacturing systems and lean thinking enfr
History of manufacturing systems and lean thinking enfr
 
Using minitab exec files
Using minitab exec filesUsing minitab exec files
Using minitab exec files
 
Sga iso-14001
Sga iso-14001Sga iso-14001
Sga iso-14001
 
Cslt closing plenary_portugal
Cslt closing plenary_portugalCslt closing plenary_portugal
Cslt closing plenary_portugal
 
Une 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julioUne 66175 presentacion norma 2006 por julio
Une 66175 presentacion norma 2006 por julio
 
Swebokv3
Swebokv3 Swebokv3
Swebokv3
 
An architecture for data quality
An architecture for data qualityAn architecture for data quality
An architecture for data quality
 
Sap analytics creating smart business processes
Sap analytics   creating smart business processesSap analytics   creating smart business processes
Sap analytics creating smart business processes
 
Big data analytics, research report
Big data analytics, research reportBig data analytics, research report
Big data analytics, research report
 

Recently uploaded

Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Nikki Chapple
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...itnewsafrica
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkPixlogix Infotech
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 

Recently uploaded (20)

Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App Framework
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 

Agile evm earned value management in scrum projects

  • 1. AgileEVM – Earned Value Management in Scrum Projects Tamara Sulaiman, PMP, CSM Brent Barton, CSM, CST Thomas Blackburn, PMP, CSM SolutionsIQ SolutionsIQ InfoTech, Inc. tsulaiman@solutionsiq.com bbarton@solutionsiq.com Thomas.blackburn@infotechfl.com Abstract Scrum is an Agile Project Management Framework. This framework specifically focuses on maximizing Return on Investment (ROI). Scrum, however, does not define how to manage and track costs to evaluate actual ROI against the vision. A reasonable cost measurement that integrates with Scrum would help provide an additional feedback loop. We adapted Earned Value Management (EVM), using values defined in Scrum. The result is called AgileEVM (Agile Earned Value Management) and is a simplified set of earned value calculations. From the values in Scrum, we derived a release date estimate using mean velocity and from this equation, generated an equivalent equation using traditional EVM techniques, thus establishing the validity of using EVM with the Scrum framework. Finally, we used this technique on two projects to further test our hypothesis. This investigation also helped us determine the utility of AgileEVM. 1. Introduction Scrum is an Agile Project Management Framework. Many Agile project methods, especially Scrum, emphasize incremental, multi-level planning and discourage fully planning software projects down to the finest level of decomposition in the early stages. The basis for discouraging big up-front plans is the amount of inherent ambiguity present in complex software systems that makes fully defining the requirements up front nearly impossible. Further, Scrum focuses on frequently prioritizing requirements to maximize Return on Investment (ROI) [1]. In order to evaluate actual ROI, project costs must evaluated and used to determine whether release plans have sufficient business value or additional re-planning is necessary. One challenge of evaluating ROI is the Scrum framework does not integrate costs and leaves this up to the implementers of Scrum. “Earned Value Management (EVM) [is] a method for integrating scope, schedule and resources, and measuring project performance.” [2] This technique is used in many industries. If we can validate a way to use this accepted practice on Scrum, then we have the tools we need to help provide balanced what-if scenarios for release planning for scope, schedule and budget. EVM techniques, however, assume complete planning of a project to discrete work package levels, then assigning cost and duration to these packages so EVM’s utility has been questioned for Agile projects. To address this, we define Agile Earned Value Management (AgileEVM), a simplified set of earned value calculations adapted from traditional EVM using Scrum metrics. By demonstrating the mathematical relationship between EVM calculations and Scrum metrics we intend to prove that Earned Value Management (EVM) is valid for use on Scrum projects. It should be noted that while we believe that these statements hold true for other Agile methods, we focus only on Scrum projects because that is the framework used in our research. To demonstrate the validity and utility of AgileEVM, we present three main areas: research, AgileEVM development and implementation on two projects. First, we review the available literature on earned value methods to establish the validity of EVM techniques on software development projects and to document previous studies applying Earned Value techniques on Agile projects. Second, we define terms and a process for using AgileEVM on Scrum projects and correlated EVM with standard Scrum burndown methods. Finally, we introduce AgileEVM in two very different Scrum projects so we could validate our assumptions. 2. Research The literature review revealed an abundance of publications validating the use of EVM for traditional
  • 2. project management, particularly on defense and construction projects. In use since the 1960’s, EVM is a well recognized project management technique; included in the Project Management Institute’s PMBOK [2]. We concentrated on publications relating earned value to software development projects in general, and relating earned value specifically to Agile software projects. In the Spring, 1995 issue of Acquisition Quarterly, Major David S. Christensen and Daniel V. Ferens published a paper, “Using Earned Value for Performance Measurement on Software Development Projects”[3]. The processes described for obtaining and using EVM data are clearly based on a heavyweight, high-ceremony waterfall software development life cycle. An early piece by Quentin W. Fleming and Joel M. Koppelman, "Earned Value Project Management – A Powerful Tool for Software Projects" [4], validated the appropriateness of using EVM on software development projects. In the aforementioned article and in Earned Value Project Management (2nd edition), they reiterated their view on the appropriateness of EVM for software engineering projects [5]. The EVM methodology described is based on exhaustive initial planning, formal work breakdown structures, detailed work packages associated with dates and dollars, and detailed tracking and analysis. The earliest mention of EVM together with agile practices was a paper presented by Steven H. Lett of Lockheed-Martin, at the European SEPG in 1998. Mr. Lett’s paper, “An Earned Value Tracking System for Self-Directed Software Teams” [6] describes an earned value tracking system (EVTS) for self- directed work teams (SDWT) that involved traditional project management planning tasks. Detailed reports from individual team members were required on a regular basis and involved a metrics engineer to collate and analyze the data obtained. In the February, 2003 issue of PMForum [7], Glen Alleman described a method for an Agile project manager to use earned value techniques on iterative projects. The method advocated the use of ‘testable requirements’ and 100% unit test coverage. At the June 2003 Agile Conference in Salt Lake City, Glenn Alleman, Micheal Henderson, and Ray Seggleke presented a paper entitled “Making Agile Development Work in a Government Contracting Environment - Using Earned Value to Measure Velocity” [8]. This large government-contracted development project mandated earned value management (EVM). In this paper they describe introducing agility by using certain Agile methods, including XP-like engineering practices. In his book Crystal Clear – A Human Powered Methodology for Small Teams, Alistair Cockburn describes the similarity between a "burn up" chart and an EVM chart [9]. He warns that EVM credits tasks completed, not necessarily integrated code. He concludes that the Agile burn up chart provides more accurate information as to the state of the project than the earned value chart. We reviewed the threads from two very active discussion groups: http://groups.yahoo.com/group/ scrumdevelopment and http://groups.yahoo.com/ groups/agilemanagement. Opinions generally centered around two themes. There is much debate about the meaning of the term “value” and confusion between EVM, business value and economic value. The second theme considers that EVM techniques can be used on Scrum projects, but asserts that there is no tangible utility to using them. We found the results of the review encouraging, validating the use of EVM on traditional software development projects. We found articles describing the use of Agile practices on software projects using EVM. What we did not find was conclusive evidence demonstrating the applicability and value of using EVM on Agile projects. 3. Development of AgileEVM Our implementation of AgileEVM concentrates on measuring progress at the release level, rather than at the sprint level or at the product level. We feel this to be the most appropriate way to use earned value management formulas on agile projects. It is true that these formulas can easily be used to measure progress of a project with multiple releases, but this would require that the backlog of multiple releases be identified and estimated. An example of where this may be a good approach would be when each Sprint has a production release and we want to use AgileEVM for helping us with the entire product life cycle. In comparison with the requirements of traditional EVM, AgileEVM leverages work items that are integral to the Scrum process. We measure progress at the end of each sprint when actual sprint velocity and actual costs are known. In five key terms below (see Table 1) Traditional EVM applications are compared to AgileEVM applications:
  • 3. Table 1: Comparison of EVM terms Performance Measurement Baseline (PMB) Traditional EVM The sum of all work package schedule estimates (duration and effort). AgileEVM Total number of story points planned for a release (PRP) Schedule Baseline - often integrated in PMB Traditional EVM The sum of all work packages for each time period calculated for the total duration. AgileEVM The total number of planned sprints (PS) multiplied by sprint length. Budget at Complete (BAC) Traditional EVM The planned budget for the release or project. AgileEVM The planned budget for the release. Planned Percent Complete (PPC) Traditional EVM What % complete did we expect to be at this point in the project? Can be a subjective estimate, or a calculation of the dollar value of the cumulative tasks planned to be complete by this point in time divided by the performance baseline AgileEVM The number of the current sprint (n) divided by the total number of planned sprints (PS). Actual Percent Complete (APC) Traditional EVM The dollar value of work packages actually completed divided by total dollar value of the budget at complete. AgileEVM The total number of story points completed (potentially shippable increments) divided by the total number of story points planned. Initial values needed for AgileEVM are straightforward. The values in Table 2 provide the ability to create an initial release baseline to measure progress against. Table 2: Initial release parameters Name Definition BAC The amount budgeted to be spent on the release L The length of time for each sprint PS Total number of sprints planned for the release SD The start date for the release. PRP Total points planned for the release At the completion of each Sprint, we capture four data points. This is sufficient to calculate Scrum metrics and AgileEVM. Table 3: Sprint data points Name Definition n Sprint number - starts at 1 PC Points Completed - The points of work completed from the Release Backlog during the Sprint PA Points Added - The points added (or subtracted) to the Release Backlog during the Sprint SC Sprint Cost - What was spent Change control in Scrum is managed and reviewed each Sprint cycle. Upon acceptance of the work completed in the Sprint and the adjustments to the release backlog, this can be considered a new project baseline. No extra weight or ceremony is imposed on the Scrum process except we explicitly review the release plan in the context of the budget. To calculate earned or planned value we must have an accurate representation of actual and planned percent complete. Story points, as described in Mike Cohn's User Stories Applied [10], represent an estimate of effort and are therefore a valid measure of percent effort complete. This is especially true if the release includes testable requirements (Alleman [9]) in the form of Stories that must pass and be accepted by the Product Owner. We define actual percent complete, APC, to be the ratio of Story points completed to Story points planned. We further define planned percent complete, PPC, to be the ratio of Sprints completed to Sprints Planned. These are summarized in Table 4.
  • 4. Table 4: AgileEVM definitions Name Definition PRP Planned Release Points. See (18) for further discussion RPC Release Points Completed. See (19) for further discussion APC Actual Percent Complete of Release. This is the ratio of Points completed to Points planned PPC Planned percent complete. We use the following EVM definitions and equations from the PMBOK: [2] Table 5: Standard EVM definitions and equations Equation Definition BAC Budgeted Cost at Completion: This is the initial budget for the release AC Actual Cost: This corresponds to budgeted costs in PV for release PV = PPC * BAC Planned Value: (1) EV = APC * BAC Earned Value (2) CV = EV - AC Cost Variance (3) SV = EV - PV Schedule Variance (4) CPI = EV / AC Cost Performance Index (5) SPI = EV/PV Schedule Performance Index (6) ETC = 1/CPI * (BAC – EV) Estimate To Complete (7) EAC = AC + ETC Estimate At Complete (8) 4. Demonstrating a Mathematical Correlation of Scrum Metrics and EVM Metrics There is a correlation of the schedule forecasts using Scrum compared to Estimate at Completion (EAC) forecasts using EVM. The logical argument starts with a presentation of the hypothesis and then proceeds through a derivation of a Release Date (RD) function. Following this, we derive the Release Date using mean velocity of Sprints. Finally, we calculate a release date using EVM from the mean velocity. Inspecting this result, we validate a reasonable measure for Actual Percent Complete using EAC, thus establishing the correlation. 4.1 Hypothesis Release date estimates using EAC calculations provided by EVM correlate to Mean velocity predictions provided by Scrum. More specifically, let RDm stand for the calculated Release Date using method m. If the projected release date based on the mean velocity (RDv) equals the projected release date based on EVM (RDEV), then EVM techniques can be used on Scrum projects to calculate EAC with equal precision to traditional plan-driven projects described in the PMBOK (ANSI/PMI 99-001-2004 standard) [2]. Restated, if RDv = RDEV (9) then EVM techniques related to EAC can be used on Scrum projects. 4.2 General Equation of a Release Date Deriving a release date RDm using any method m, needs an initial position, let it be named start date (SD). Then a release date is simply an offset from the start date. This offset can be determined by the number of Sprints and the Sprint length. From this we can define the offset to be the number of sprints multiplied by the duration of the Sprints. Thus, LNSDRDm ⋅+= (10) where N equals the number of Sprints and L equals the length of each Sprint in calendar days. Note that (10) assumes equal Sprint lengths. It is mathematically simpler to limit this discussion to equal Sprint lengths. Although unusual, Sprint lengths are occasionally adjusted to accommodate environmental situations. For these anomalies, one can, in most cases, redefine the Sprint Length to be equal to the Greatest Common Factor of the different Sprint lengths without invalidating this method. Upon inspection of (10), N is the only variable, where SD and L are initial parameters that do not change for a release. Thus, N is the single independent variable. See Fig. 1: Graph of a release date. RDm = f(N) (11) So RDm is a linear function dependent on N. RDm = SD +L·N (12)
  • 5. ∑= += n k kn PAPRPPRP 1 0 ∑= P ipPRP 10/25/2005 12/14/2005 2/2/2006 3/24/2006 5/13/2006 7/2/2006 1 2 3 4 5 6 7 8 9 10 11 12 13Number of Sprints (N) ReleaseDate(RD) SD 0 f(n) = SD +L·N Fig. 1: Graph of release date 4.3 Using Mean Velocity to Define the Equation of a Release Date Considering (12), we need to define N in terms of an estimate of how much work can be done per Sprint. Let v equal the average work completed per Sprint, which is known as the mean velocity, or often just velocity. The total number of Sprints N decreases as velocity increases, so it is inversely proportional to N. Let W = the total work planned to be done in the release. Then the total work factored by the mean velocity equals the total iterations N for v>0. v W N = (13) For Sprint n, where n ≥ 1, let N = n + n' (14) where n' is the estimated Sprints after n. Also, let W' be the work to be done in sprints n'. Then (13) can be rewritten v W n ′ =′ (15) Combining (14) and (15), then substituting into (12), we have       ′ +⋅+= v W nLSDRDv (16) 4.4 Using Mean Velocity to Determine Sprints Left Clearly, if there have been no completed Sprints, an estimate of an initial velocity must be made. Once underway, measures of actual velocity can be used to estimate future velocities. Empirical measures, such as "yesterday's weather," are effective for evaluating what can be accomplished in Sprint Planning. For release planning, however, applying the arithmetic mean to determine the average velocity (work done per Sprint) is a common practice. To provide measures for work, we need to introduce a valuation for sizing Release Backlog Items (RBI). This allows us to measure how much work is completed for velocity calculations. The method for sizing these can be any numerical value. A few examples are: Story Points, T-Shirt Sizes with Ideal Team Days applied, Function Points and Working Days 1 . For convenience, let us define the units for these numerical values to be points, abbreviated p. Thus, for the items in the Release Backlog, there exists a same-sized set P of point values, P = {p1, p2, p3,…; pi ≥ 0} where the total point value, named Planned Release Points (PRP) can be calculated as (17) Before the inception of any Sprint, when n = 0, denote the initial Planned Release Points: PRP0. For each Sprint n, define any new RBI points added PAn and the points completed PCn. Thus, the total release points from inception through Sprint n can be calculated as (18) Further, define RPCn as the total release points completed through Sprint n. This can be calculated as ∑= = n k kn PCRPC 1 (19) Finally, let the number of points remaining at Sprint n be denoted PRn. This can be found by subtracting the Completed Release Points from the Planned Release Points. Thus, nnn RPCPRPPR −= (20) We can now redefine W '≡ PRn from (15) , so. v PR n n =′ (21) To calculate the number of Sprints left we need to calculate N. Substituting (21) in (14), we have v PR nN n += (22) 1 One needs to be cautious when using values with units such as time or cost. These can lead to confusion and potential misinterpretation or miscalculation.
  • 6. Next, we need a more explicit way to express v in terms of data we capture. Let n define the nth Sprint where n>0 and let vn be the velocity of Sprint n. Then the velocity for Sprint n is the number of points completed in Sprint n. Thus, nn PCv = (23) The arithmetic mean of the velocity v can then be calculated using the standard equation: ∑= ⋅= n k kv n v 1 1 (24) where n>0. Substituting (23) into (24) yields: ∑= ⋅= n k kPC n v 1 1 (25) Substituting (20) and (25) into (22) generates the following equation. ∑⋅ − += = n k k nn PC n RPCPRP nN 1 1 (26) We can simplify this equation by factoring n from each operand and substituting RPCn from (19).       −+⋅= n n n n RPC RPC RPC PRP nN 1 (27) This can be immediately simplified to:       ⋅= n n RPC PRP nN (28) From the description of Actual Percent Complete (APC) in Table 4, we can construct APCn as the ratio of release points completed (RPCn) and total points (PRPn) for sprint n. Thus, let n n n PRP RPC APC = (29) or n n n RPC PRP APC = 1 (30) Substituting (30) into (28) causes the equation to simplify to: nAPC n N = (31) Finally, we can calculate the Release Date from (12) using this simplified formula:       ⋅+= n v APC n LSDRD (32) 4.5 Deriving a Release Date based on EAC from RDv If we can derive an equation in the form of (12) from (32) for a release date based only on EVM terms, we will have correlated it to mean velocity. Considering (31), we can manipulate this equation as follows.       −+⋅= n n nn APC APC APC n APC n 1 1 (33) and               − ⋅+⋅= n n n APC APC BAC BAC n APC n 1 1 (34) But from (2), EV = APC·BAC, so       − +⋅= EV EVBAC n APC n n 1 (35) From (5), CPI = EV / ACn, or EV = CPI · ACn so       ⋅ − +⋅= nn ACCPI EVBAC n APC n 1 (36) From (7), ETC = 1/CPI * (BAC – EV), so       ⋅+⋅= ETC AC n APC n nn 1 1 (37) or ( )ETCAC AC n APC n n nn +⋅= (38) But, from (8), EAC = AC + ETC, so nn AC EAC n APC n ⋅= (39) That is both (n / APCn) and (n * EAC / ACn) will calculate total Sprints. Also, for Sprint n we have equivalent values for determining APCn. EAC AC PRP RPC APC n n n n == (40) Substituting (39) into (32),       ⋅⋅+= n v AC EAC nLSDRD (41) Thus we have derived RDv solely in EVM terms so, let us define RDEV such that RDv = RDEV. Finally,       ⋅⋅+= n EV AC EAC nLSDRD (42) 5. AgileEVM Test Implementation With AgileEVM defined, and equipped with a spreadsheet for tracking purposes, we were ready to try this out on some test projects. We chose two very different projects for the initial test set. The goals for the test were:
  • 7. 1. Validating the correspondence of the projected release dates by comparing mean velocity and EVM analysis. 2. Determine if the EVM metrics provided additional value beyond the established Scrum metrics for making project decisions. 3. Analyze whether the impact of cost analysis adds value to technical teams for making good decisions. Two projects using the Scrum methodology were tracked using both the AgileEVM and the burndown method. These projects have very different adaptations to the Scrum framework, one utilizing very short Sprints with a small team, and the other being a single large team with monthly sprints. Both projects used story points for estimation purposes. It is important to note the larger team project is still active at the time of this writing, however, we feel the results of tracking the projects for nine months is sufficiently demonstrative to report. The smaller team, Project A, has recently been released to production. For both projects, a data gathering spreadsheet was developed to collect the data and perform both the velocity trend analysis and the AgileEVM calculations on a Sprint-by-Sprint basis. This method provided for lightweight data collection along with easy comparison of the results between the burndown metrics and the AgileEVM metrics. Project A is a one-half million dollar web application project. The team is developing a product enhancement and therefore is closely monitored by company management. The collocated team has five to seven members and is experienced with the Scrum process. Due to dynamic business requirements, sprints are one week long. Both the AgileEVM and Scrum metrics are communicated to the entire team at the end of each sprint. Key management stakeholders are presented with the Burndown charts and AgileEVM metrics on a monthly basis. Project B is a very large, externally funded project. The project size is about three million dollars for the first eighteen month phase. The Project B team is much larger than usual with 15-18 members, and continues to add team members every couple of sprints. This team is new to Scrum and Agile development methods. They are also collocated for the majority of the day. Sprints are 30 calendar days long. Unlike Project A, the primary project guide on Project B is the Scrum Burndown chart, not the AgileEVM metrics. We were still able to validate the correspondence of the data but circumstances limited our ability to interpret decision support value. 5.1 AgileEVM Test Results Our analysis of the data from both projects demonstrated indistinguishable results between the predicted release dates using the mean velocity method and the earned value method (see Fig. 2 and Fig. 3). This result was as expected; following the mathematical analysis proving that these two formulas are equivalent. We also tracked release date projections based upon atypical calculations for EAC [2]. We noticed that in the early Sprints, the atypical calculations provided more realistic predictions. This is consistent with the nature of discovery inherent in Agile projects. The velocity of both projects fluctuated each Sprint. Project A had cyclic velocity with several highs and lows (see Fig 4: Project A velocity). Project B started stabilizing about Sprint 5 (see Fig. 5: Project B velocity). Because of the fluctuations in velocity, the mean varies considerably from the actual velocity for some Sprints; though comparing the predicted release dates to the burndown charts demonstrates a close relationship. Project A Release Date Projection Com parisons 7/17/2005 9/5/2005 10/25/2005 12/14/2005 2/2/2006 3/24/2006 5/13/2006 7/2/2006 8/21/2006 10/10/2006 11/29/2006 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 Sprints Com pleted for RD estim ate EstimatedRD Plan Mean Velocity Estim ate at Complete EAC (atypical) Fig. 2: Project A release date projections Project B Release Date Projection Com parisons 3/24/2006 7/2/2006 10/10/2006 1/18/2007 4/28/2007 8/6/2007 11/14/2007 2/22/2008 6/1/2008 9/9/2008 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Sprints Com pleted for RD estim ate EstimatedRD Plan Mean Velocity Estim ate at Com plete EAC (atypical) Fig. 3: Project B release date projections The combined burndown and performance index charts provide evidence of the additional value provided by AgileEVM. Consider Project A (see Fig. 6: Project A Burndown, CPI, and SPI). This
  • 8. project had a 30% budget buffer and the CPI index clearly shows the erosion of this buffer that the burndown doesn't recognize. Adjusting the planned release date in Project A at the end of Sprint 21 caused the SPI to move from an index value of 0.7 to 0.97 (see Fig. 2 and Fig. 6). This aligned the planned and projected release dates along with the AgileEVM indicators. Project B has been adjusting scope down. The SPI and CPI is registering the potential ROI of reducing scope in Sprint nine (see Fig. 7: Project B Burndown, CPI, and SPI). This scope reduction is demonstrated by comparing the flattening velocity of Sprints six through nine to the indices (see Fig. 5: Project B velocity). Note that the same result can also be interpreted by evaluating the burndown graph and the velocity. This action of reducing scope has kept the cost and schedule constraints within current expectations. The data also showed strong correlation in the cost information provided by AgileEVM and manual planning calculations. Given the expected behavior of the indices in traditional EVM, it is clear that the CPI, SPI and EAC behaved as expected given the budget, schedule, and scope. Pro ject A Velocity 0 20 40 60 80 100 120 140 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 Sprint PointsCompleted Velocity Mean Velocity Fig. 4: Project A velocity Project B Velocity 0 50 100 150 200 250 300 350 400 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 S print PointsCompleted Velocity M ean V elocity Fig. 5: Project B velocity An interesting aspect is the way the information was used on Project A. The metrics providing the most value to team members and management were the CPI, SPI, and EAC. These metrics were requested by both executive management and team members alike. Given that significant change is expected on an Agile project, it was necessary to remind team members and management that the forecast release date, percent complete, Effort To Complete and Estimate At Complete are based on what is actual “right now”. This is exactly the same as with the burndown method. Executive management was comfortable with the AgileEVM metrics and found them useful in making decisions concerning the direction of the product. Reviewing this data helped them validate decisions and the need for process change. 5.2 The Agility of AgileEVM A key question of the usefulness of AgileEVM is the level of agility. Would the implementation of the method add "drag" to a Scrum team’s velocity? If so, would the impact to velocity outweigh the added value of the information? Project A B urn do w n an d Ind ices 0 100 200 300 400 500 600 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 Sprint PointsRemaining 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 IndexValue Burndown CPI SPI Fig. 6: Project A Burndown, CPI, SPI Project B B urn do w n an d Ind ices 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Sprint PointsRemaining 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 IndexValue Burndown CPI SPI Fig. 7: Project B Burndown, CPI, SPI The question was posed to the team on Project A: "Did the process of collecting or calculating the AgileEVM metrics add weight to the project?" The answer was a resounding, "No! The data used in AgileEVM is data that is already available. The calculation and tracking of the metrics was automated
  • 9. in the spreadsheet that the ScrumMaster maintained. Communication of the metrics to the project team was as easy as posting the results on the wall, and having the information available during the project retrospective discussions." Most of the developers reacted positively to the availability of the data, feeling that if an analysis was needed in order to determine a cause of a certain issue, like a sudden loss in velocity, the data is readily available to review. The team was able to quickly identify changes in key metrics, and this aided in the continuous improvement of the team. The Product Owners for both projects felt that the AgileEVM metrics did not provide any more schedule insight than the burndown chart provided. It is interesting to note that the Product Owners for these projects do not have budget responsibility. We agree that without the need to manage cost performance, AgileEVM does not add significant value above traditional burndown methods. The ScrumMaster/project manager for Project A, who does have budget responsibility, found the data particularly useful for validating project status, tracking and forecasting potential budget issues, identifying alternative strategies by running "what if" scenarios using AgileEVM to predict results, as well as communicating status and issues with the product owner and management. . The ScrumMaster/project manager on Project B did not use or report the AgileEVM metrics, nor were the metrics shared with team members or management stakeholders. Data was collected, analyzed and compared to actual results without impacting the team. The very fact that the process of collecting and calculating the data did not impose on the team at all gives further credence to the view that the AgileEVM process passes the agility test. 6. Conclusions In researching the validity and value of using EVM on scrum projects several key questions needed to be answered. First, are the metrics valid for Scrum projects? Second, is the process lightweight? Third, do the resulting metrics add value? Assuming that the burndown trend analysis is valid for Agile projects, we have shown mathematically that the calculations for Release date using Estimate At Complete and calculations for Release date using the burndown trend analysis are the same. Empirically, we have tracked the results of two projects and have shown the indistinguishable results of the data generated from both methods. We feel that the validity of the AgileEVM techniques is established. The implementation of the AgileEVM process has no noticeable impact on a Scrum team’s velocity. Also, the value of the data was confirmed by the team who had access to the metrics, as well as the ScrumMaster and management stakeholders for the project. Thus, we are encouraged that the AgileEVM metrics do indeed add value to Scrum projects. For the ScrumMaster, it is clear that metrics that are familiar go a long way to ease the discomfort that new, unfamiliar methodologies can induce. The analysis that AgileEVM provides, along with the burndown method, helps to substantiate intuition and provides executives with quantitative data in a consistent manner. The cost analysis, with its forecast Estimate at Complete and Estimate to Complete are valuable to Agile stakeholders calculating estimated ROI. Agile stakeholders who are responsible for making budget decisions find this information extremely valuable. Our recommendation is that AgileEVM be used in conjunction with the Burndown chart and team velocity as supporting data. One important caveat is that change is expected on Agile projects and so the AgileEVM metrics are derived from what is true at each Sprint boundary. Providing the team and Agile stakeholders with useful and understandable data is vital to the "rudder" with which the Scrum team steers toward better processes and continuous improvement. By providing the burndown and AgileEVM metrics together, the team is better equipped to succeed. References [1] Schwaber Ken, Agile Project Management with Scrum, Microsoft Press, Redmond, WA, 2004. [2] “Guide to the Project Management Body of Knowledge - PMBOK® Guide 2003 Edition”, Project Management Institute, Pennsylvania, 2003. [3] David S. Christiansen, Daniel V. Ferens, “Using Earned Value for Performance Measurement on Software Development Projects, Acquisition Review Quarterly, DAU Press, Fort Belvoir, Virginia, Spring 1995, pgs 155 – 170, http://www.suu.edu/faculty/christensend/EVonSWprojects. pdf. [4] Fleming, C.D., Koppelman, Joel M. Koppelman, Earned Value Project Management – 2nd Edition, Project Management Institute, Newtown Square, Pennsylvania, 2000.
  • 10. [5] Quentin Fleming and Joel Koppelman, “Earned Value Project Management – A Powerful Tool for Software Projects”, Crosstalk - The Journal of Defense Software Engineering, Ogden, UT, July 1998. http://www.stsc.hill.af.mil/crosstalk/1998/07/value.asp [6] Stephen H. Lett, “An Earned Value Tracking System for Self-Directed Software Teams", European SEPG 98, Conference Proceedings, 1998, http://www.benchmarkqa.com/PDFs/software_teams.pdf. [7] Glen B. Alleman, “Project Management == Herding Cats, A Field Report, Agile Project Management”’ PMFORUM, PMFORUM.ORG, February 2003, http://www.pmforum.org/viewpoints/2003/0203agilepm.ht m [8] Glen B Alleman and Michael Henderson, “Making Agile Development Work in a Government Contracting Environment – Using Earned Value to Measure Velocity, Agile Development , Salt Lake City, Utah, June 25 – 27, 2003. http://www.niwotridge.com/PDFs/ADC%20Final.pdf [9] Cockburn, Alastair, Crystal Clear: A Human-Powered Methodology for Small Teams, Pearson Education Inc. Upper Saddle River, NJ, 2005 [10] Cohn Mike, User Stories Applied: For Agile Software Development, Pearson Education, Inc. Boston, MA, 2004. [11] Cohn Mike, Agile Estimating and Planning, Pearson Education, Inc. Boston, MA, November 2006. [12] Glen B Alleman, Nine Best Practices, The Software Management Framework, 3 June 1999. [13] David Christensen, “The Estimate At Completion Problem: A Review of Three Studies,” Project Management Journal, Project Management Institute, March 1993 pp24:37-42. [14] David S Christensen, Ph.D., “Determining An Accurate Estimate At Completion”, National Contract Management Journal, Arlington MA, 1993, pp 25:17-25.