SlideShare a Scribd company logo
1 of 11
Download to read offline
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Techno-Economic Study of Series Current Limiting Reactor and
Its Impact in the 11KV Network with Harmonic Pollution
Y.V.SRIDHAR1*
HAITHAM SAFAR2*
NILESH MODI3
4
YOUSUF ALI
YACOUB AL-DASHTI5
* Y.V.SRIDHAR1:
ysridhar@kockw.com
* HAITHAM SAFAR2: hsafar@kockw.com
Abstract
Survey & selection of oil filled fault current limiting series reactor for limiting short circuit fault currents from
40KA to 22KA at 11KV level in an existing distribution substation due to change of source substation. The
impact of source X/R ratio variation, maximum & minimum short circuit currents on the acceleration times of
the 11KV motors and variance in voltage regulation due to change(s) in the conventional Series reactor
impedance is studied. Impact of power factor improvement capacitors on the short circuit level and on series
reactor impedance is assessed. Expected harmonic pollution due to VSD’s is estimated and its influence on the
series reactor impedances is assessed for resonant conditions. Transient Recovery Voltage and Rate of Rise of
Recovery Voltage are studied for verification of circuit breakers’ ability to isolate the fault conditions. Techno economic evaluation of series reactor(s) impedance(s) for cost effectiveness along with the ability of reputed
international testing houses for testing is assessed. The study results reflect that the constraints of test
laboratories to test the specified series reactors will have an impact on the selection of series reactor impedance.
While higher impedance selection will be useful from the short circuit point of view, it will pose difficulties with
reference to physical dimensions of the equipment, cost and other related issues.
Keywords: Current Limiting Reactor (CLR), Short Circuit Current, Harmonics, Cost
Introduction:
Ever increasing demand of electrical power [1], [2] necessitates increased power generation which in turn causes
increased short circuit current at switchboards and equipment. Also network restructuring and modifications
would pose issues related to short circuit capability of existing switchboards. Increased short circuit currents can
cause severe mechanical and thermal stresses leading to damage of the equipment and operating facility. Many
a times, it is not possible to replace the existing switchboards with higher rated short circuit capability due to
production considerations and cost reasons. When the options of dividing the bus bars and/or splitting the
network cannot be implemented due to reasons of reliability and security of power, and application of patented
current limiters would pose issues related to installation & space constraints in the existing switchboards and
substations, then the series current limiting reactor is an acceptable solution for limiting the short circuit currents.
[1],[2].
This paper intends to present the various techno-economic aspects involved in the selection of series current
limiting reactor and its application for limiting fault current from 11KV, 40KA at the source end substation to a
level of 11KV, 25KA at the receiving end substation.
Various types of series current limiting reactors are available in the market. It is noted that a revival of interest in
the application of current limiting reactors coupled with solid state electronics schemes and superconductivity
are in the various stages of development. Few of the applications appear to be successful in USA electrical
networks. It is felt that for 11KV network distribution of a hydrocarbon industry, taking into consideration cost,
familiarity and hands on aspects, the conventional type of series current limiting reactors are adequate for the
subject application.
1.

Brief Description of the electrical network:

Substation ‘X’ is rated for 72MW at 11KV and feeds to Substation ‘Y’ and Substation ‘Z’.

264
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Figure1.

Type and Nature of the connected load: Total maximum demand of Substation ‘Y’ is 55MW. Non-linear loads to
the extent of 36MW operate on Substation ‘Y’ 11KV bus. Substation ‘Z’ has maximum demand of 12MW
consisting of motors and power factor improvement capacitors at 11KV level.
The other load composition consists of induction motors of various sizes connected to 3.3KV and 440 volt level
along with associated transformers. Lighting loads and small nonlinear loads such as battery chargers, UPS
systems, Computers and Switch Mode Power Supplies (SMPS) are connected at the 440 volts level.
Presence of Harmonics and Harmonic related information:
As the nonlinear loads operate at Substation ‘Y’ 11KV, harmonic pollution is present in the network. The main
contribution of harmonics is from 11KV Variable speed drives. The Variable speed drives are of voltage source
type with high pulse rectifiers.
The capacity of UPS systems & Battery Charger(s) is much less than 15% of the corresponding transformer
capacity at the 440 volt level hence the harmonic presence is ignored.
2.

Reactor Related Preliminary Aspects:

Type of Reactor: It is noted that application of air core, dry type reactors are more common in major electrical
networks for the current limiting purposes. However taking into the consideration the existing practice and
presence of traces of Hydrogen sulphide, outdoor type, three phase, air core, oil immersed, magnetically shielded
series current limiting reactors are considered for the subject application and techno economic evaluation.
Reactor location: Based on the constraints of space availability and extent of modification required at Substation
‘Z’, it is considered that installation of reactors will be part of the Substation ‘X’. Further installation of reactors
at source end (optimum location for the reactors) has the advantage of reducing short circuit current on the
linking cables from Substation ‘X’ to Substation ‘Z’.
Manufacturer’s availability: It appeared from the survey that more number of manufacturers are available for dry
type air core reactors. However few manufacturers are also interested in the manufacture of air core, oil filled
type reactors.
3.

ETAP system Studies:

Size of the Reactor: For the purpose of limiting fault current which is at the level of 40KA at Substation ‘X’ to
the level of 25KA at Substation ‘Z’ two reactor values 0.3 ohms and 0.5 ohms are considered. For each of the
value of the reactor four varieties of system studies are conducted. They are namely
Load flow study
Short Circuit study
265
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Motor starting capability study
Harmonic Assessment study.
Load Flow Study: Initially Substation ‘Z’ was fed from the Substation ‘W’ (not indicated in the Figure 1). During
the process of network reorganization, Substation ‘Z’ is proposed to be fed from Substation ‘X’. Introducing
Series Current Limiting Reactors in the electrical network would increase the impedance of the network and
other networks parameters have also changed due to the network modifications, Load Flow study is carried out
for the verification of required power flow and voltage regulation aspects. From the ETAP Load Flow studies, it
is noted that the voltage regulation and power flow related aspects are within the acceptable range for both 0.3
and 0.5 ohm reactors [3], [4].
Short Circuit Study: Before the network modification, the short circuit level at Substation ‘Z’ was 17.0KA (Ik)
as against switchboard rating of 25KA. At the new source substation (Substation ‘X’), the calculated fault level
is in the range of 27KA (Ik) from utility without considering fault contribution from the downstream and
switchboard is rated for 40KA. To ensure that the Substation ‘Z’ fault level does not increase to 22KA, system
studies are carried out for both 0.3ohm and 0.5ohm Series Current Limiting Reactor values. It is to be noted that
the presence of capacitor banks at Substation ‘C’ will not alter the peak short circuit current (Ik”) at the 11KV
bus and hence ignored.
X/R ratio and its impact: It is known that utility undertaking fault levels are increasing and system impedances
values are expected to change due to power increase and expansion of network at the utility end. Although it is
not possible to assess how much increase in the short circuit current will be available in future and how much
variation will be there in the X/R ratio, a few calculations were carried out by varying the X/R ratio and source
short circuit currents and its impact on the load flow and short circuit currents at the Substations. The ETAP
results are mentioned hereunder in Table 1, 2, 3, 4 and 5. The below projected current values are based on the
three phase fault simulations.
Table 1

Impedance value of CLR = 0.3 ohm
Source X/R = 4.61
Substation Name

Source X/R = 6

Source X/R = 18

Source X/R = 30

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

1

Substation X

99.5

10.945

99.5

10.945

99.5

10.945

99.5

10.945

2

Substation Y

98.98

10.888

98.98

10.888

98.98

10.888

98.98

10.888

3

Substation Z

98.96

10.885

98.96

10.885

98.96

10.885

98.96

10.885

Table 2

Impedance value of CLR = 0.5 ohm
Source X/R = 4.61
Substation Name

Source X/R = 6

Source X/R = 18

Source X/R = 30

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

Voltage
(%)

Voltage
(KV)

1

Substation X

99.48

10.943

99.48

10.943

99.48

10.943

99.48

10.943

2

Substation Y

98.96

10.886

98.96

10.886

98.96

10.886

98.96

10.886

3

Substation Z

98.77

10.865

98.77

10.865

98.77

10.865

98.77

10.865

Table 3

Impedance value of CLR = 0.3 ohm; Source Fault Level (max) =2789 MVA at 132KV level
Source X/R = 4.61

Source X/R = 6

Source X/R = 18

Source X/R = 30

Substation Name

Ik”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

1

Substation X

32.524

81.824

26.331

32.483

82.574

26.298

32.424

84.435

26.258

32.417

84.839

26.256

2

Substation Y

30.332

74.032

24.556

30.302

74.648

24.532

30.265

76.173

24.51

30.262

76.503

24.511

3

Substation Z

24.108

58.027

19.237

24.092

58.382

19.224

24.074

59.257

19.217

24.073

59.446

19.218

266
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)
Table 4

Impedance value of CLR = 0.5 ohm ; Source Fault Level(max) = 2789 MVA at 132KV level
Source X/R = 4.61

Source X/R = 6

Source X/R = 18

Source X/R = 30

Substation Name

Ik”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

lk”
(KA)

lp
(KA)

lk
(KA)

1

Substation X

32.459

81.703

26.331

32.418

82.454

26.298

32.359

84.317

26.258

32.353

84.721

26.256

2

Substation Y

30.277

73.936

24.556

30.247

74.552

24.532

30.21

76.078

24.51

30.208

76.409

24.511

3

Substation Z

21.54

52.44

17.018

21.526

52.718

17.007

21.509

53.401

16.999

21.508

53.548

17

Table 5
Source X/R = 4.61
Source X/R = 6
Source X/R = 18
Source X/R = 30
Ik"
Ik"
Ik"
Ik"
Ip (KA) Ik (KA)
Ip (KA) Ik (KA)
Ip (KA) Ik (KA)
Ip (KA) Ik (KA)
(KA)
(KA)
(KA)
(KA)
Impedance value of CLR = 0.3 ohm, Source Fault level = 5000 MVA at 132KV level
Substation Z

25.319

61.514

20.532

25.309

61.743

20.523

25.297

62.303

20.518

25.297

62.423

20.519

63.794

21.120

55.874

18.010

56.934

18.472

Impedance value of CLR = 0.3 ohm, Source Fault level = 7500 MVA at 132KV level
Substation Z

25.879

63.15

21.129

25.871

63.312

21.123

25.863

63.709

21.119

25.863

Impedance value of CLR = 0.5 ohm, Source Fault level = 5000 MVA at 132KV level
Substation Z

22.462

55.175

18.022

22.453

55.350

18.015

22.442

55.781

18.009

22.442

Impedance value of CLR = 0.5 ohm, Source Fault level = 7500 MVA at 132KV level
Substation Z

22.883

56.442

18.480

22.877

56.566

18.475

22.869

56.869

18.471

22.869

Motor Starting Capability: Substation ‘Z’ has approximately 3500KW rated motors in multiple numbers that
operate at 11KV level in Direct On Line Mode. Studies were carried out for motor starting capability for both the
values of Current Limiting Reactors (CLRs) when the line voltage at Substation ‘Z’ falls down to 80% which
represents worst operating condition. Introduction of CLR did not change the motor starting times much at
Substation ‘Z’. The results are mentioned hereunder in Table 6.
Table 6

Substation C Motor Starting Time (in seconds) at Source Fault Level(minimum) = 1852 MVA at 132KV level
Impedance value of CLR = 0.3 ohm
Source X/R = 6.04
Source X/R =12
Time for Motor Starting in
Time for Motor Starting in
seconds
seconds
4.2
4.2

Impedance value of CLR = 0.5 ohm
Source X/R = 6.04
Source X/R = 12
Time for Motor Starting in
Time for Motor Starting in
seconds
seconds
4.2
4.2

Power Factor: The voltage drop at the reactor is a function of the power factor. It is mandatory to maintain 0.95
power factor at Substation ‘X’ 11KV bus bar. Substation ‘Z’ has two numbers capacitor banks each of size 1800
KVAr operating on 11KV bus. The VSD’s at Substation ‘Y’ are intended to be operated at high power factor in
the range of 0.95 to 0.97 during their continuous operation. The ETAP studies indicates power factor at 11KV
buses of various substations as indicated in the Table 7.
Table 7
Substation
Substation X
Substation Y
Substation Z

Impedance value of CLR = 0.3 ohm
3 Tr, 3 CLR
3 Tr, 4 CLR
4 Tr, 4 CLR
97.8
98
97.9
98.1
97.7
97.7
84.8
85.2
85.2

Impedance value of CLR = 0.5 ohm
3 Tr, 3 CLR
3 Tr, 4 CLR
4 Tr, 4 CLR
97.8
97.8
97.8
98.1
97.7
97.7
84.8
85.2
85.2

Harmonic Assessment Study: Substation ‘Y’ has considerable number of variable speed drives of 4MW rating.
Harmonic Assessment study indicated the following results of Voltage and current Distortion with Current
Limiting Reactors of 0.3ohm and 0.5ohm at 11KV levels of respective substations:

267
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)
Table 8

Substation Name

VTHD% for CLR 0.3 Ohm

VTHD% for CLR 0.5ohm

Substation X

0.97

0.99

Substation Y
Substation Z

0.99
1.22

1.03
1.1

Table 9

Substation Name

ITHD% for CLR 0.3 Ohm

ITHD% for CLR 0.5ohm

Substation X

xxx

xxx

Substation Y
Substation Z

xxx
xxx

xxx
xxx

From the evaluation of above system studies with both 0.3ohm and 0.5 ohm reactors, generally it appears that
0.3 ohm and 0.5 ohm reactors are acceptable for X/R ratio of 4.61 and Utility source fault level of 2789MVA at
132 KV level, at higher levels of source fault level, the Ip are marginally higher than the switchboard assigned
ratings for 0.3 ohm rated reactors. Please refer Table 10 for comparison of results:
Table 10

Evaluation basis

0.3 ohm CLR

0.5 ohm CLR

Remarks

Load Flow Study for present
value of X/R ratio 4.6 and
Utility fault level at 2789
MVA
Load flow for variations of
Utility X/R ratio variation

ETAP results are technically
Acceptable

ETAP results are technically
acceptable

Based on the results both CLR
values are acceptable.

ETAP Results are technically
acceptable

ETAP results are technically
acceptable

Short Circuit Study for present
value of X/R ratio 4.6 and
Utility fault level at 2789
MVA
Short Circuit Study for
variations of Utility X/R ratio
and projected Utility fault
level at 5000 MVA

ETAP Results are technically
acceptable

ETAP results are technically
acceptable

ETAP Results are not
technically acceptable

ETAP results are technically
acceptable

Short Circuit Study for
variations of Utility X/R ratio
and projected Utility fault
level at 7500MVA

ETAP Results are not
technically acceptable

ETAP results are technically
acceptable

Motor starting time study

ETAP Results are technically
acceptable

ETAP results are technically
acceptable

Power factor

0.95 power factor can be
maintained for various modes
of network operation

0.95 power factor can be
maintained for various modes
network operation

Harmonic Study

VTHD values are less than
acceptable 5% limit.

VTHD values are less than
acceptable 5% limit.

X/R ratio variation is
imaginary for the study
purposes.
This study represents present
situation where X/R ratio 4.6
and Fault level 2789 MVA is
obtained from Utility
With the imaginary values of
X/R and short circuit values
0.3 ohm CLR is very close to
the rated values and not
technically acceptable.
However 0.5 ohm CLR is
acceptable
With the imaginary values of
X/R and short circuit values
0.3 ohm CLR is not
acceptable. However 0.5 ohm
CLR is acceptable
Both 0.3ohm and 0.5 ohm
CLRs are acceptable. The
results projected in the table 6
are based on X/R = 4.6 and
source minimum fault level of
1852MVA.
Both 0.3 ohm and 0.5 ohm
current limiting reactors
acceptable for maintaining the
power factor at substation X.
Both 0.3 ohm and 0.5 ohm
current limit reactor values are
technically acceptable.

If so, general conclusion will be why not to opt for 0.5 ohm CLR which will ensure lower short circuit current at
Substation ‘Z’ 11KV switchboard. However, prior to conclusion of the reactor ohm value other Reactor’s critical
parameters need to be assessed.
4.

Series Current Limiting Reactor’s Critical Parameters:

For current limiting reactors, in general three phase short circuit is usually the basis for specifying various
parameters [5]. In an electrical network, three currents are that dealt with. Ip (peak short circuit current), Ik”
(initial symmetrical short circuit current) and Ik (steady state short circuit current). In numerical terms of kilo
amps, Ip is greater than Ik” and Ik” is greater than Ik. In general the Ip & Ik” current that flows in the reactor are
268
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

the parameters that would influence the design and selection of reactor. Ip current deals with mechanical bracing
requirements of reactor whereas Ik” deals with maximum short circuit current that flows in the reactor. In
general, as the substations are far from the generating stations, it is customary to take Ik” to Ik. However, where
ever the value of Ik” is known it is recommended to use Ik” value instead of Ik value.
Reactor continuous current rating: Continuous flow of current that would flow under steady state operating
conditions to deliver the Continuous power to Substation ‘Z’ is the minimum current rating of the Current
Limiting Reactor.
Reactor short circuit current time rating: In any electrical network all power components are assigned standard
time ratings based on the need to withstand short circuit currents. These standard ratings are generally for one (1)
second or three (3) seconds for the High Tension switchboards. However for current limiting reactors a
minimum of two (2) seconds time rating shall be the standard value in line with clause 8.4.3 of IEC 60076-6. In
the present context in line with the current design practice, three (3) seconds time rating is assigned for current
limiting reactors.
Reactor short circuit current rating: This is an important rating that is required to be specified by the designer.
Electrical equipment has standard short circuit ratings. For example, relevant IEC standard assigns standard
ratings for an 11KV switchboard 25KA, 31.5KA and 40KA etc. However for reactors there are no such
standard ratings assigned by IEC standards. This rating is to be determined by the designer to suit to the
electrical network requirements. Then the question arises as to what shall be basis for specifying such fault
current rating.
In the subject study following three aspects is considered:
Reactor rating of 40KA for 3 seconds: As the reactors are physically close to the Substation ‘X’ which has 11KV
switchboard with short circuit fault rating of 40KA (3seconds), is it required to assign CLR rating to be for
40KA for 3 seconds as the reactor primary terminals will see 40KA fault current ?
Reactor rating of 25KA for 3 seconds: As the reactor is limiting the fault current to 25KA at Substation ‘Z’, is it
required to be rated for 25KA for 3 seconds?
Assigning a rating of 40KA for 3 seconds or 25KA 3 seconds would make the reactors bulky and costly.
Please see the Table 11 below which does not include any space and civil construction costs:
Table 11

Reactor
value in
Ohms

Assigned
current rating

Approximate
Physical
dimensions of each reactor. L
X W X H (all in meters)

Approximate
Weight of the
reactor

Indicative
Budgetary
Cost of each reactor

0.3

40KA/3seconds

2.5 X 2.5 X 4.6

12 tons

PRICE

0.5

40KA/3seconds

7.0 X 3.5 X 4.0

50 tons

3.125 x PRICE

0.5

25KA/3seconds

5.0 X 2.5 X4.0

27 tons

1.875 x PRICE

Reactor Testing & International Testing houses: The above cost figures are non-inclusive of reactor testing costs.
It is important to note that short circuit test of current limiting reactors is a special test and will not be performed
by the manufacturer unless specifically requested for. This test will prove the ability of the reactor to with stand
short circuit current for the specified time. On survey of testing houses it is noted that 0.3 ohms 40KA/3seconds
reactors cannot be tested for full 40 KA for time period of 3 seconds due to the limitations of the test facilities at
most of the reputed testing houses. Few of the testing houses declined to indicate the costs involved and few
other testing houses suggested reduction of both time rating and short circuit current rating of the reactors for the
purpose of testing of reactors. Although 0.5 ohm value Reactor can be tested but the cost involved is very high
and is in the range of 60% to 70% of reactor cost. The cost and physical dimensions of the reactor depends on
the ohm value, short circuit current & time rating of the reactor.
Fixation of the ohm value of the Reactor: Based on the above, it can be noted that specifying higher ohm value
for a reactor is not only inappropriate and lead to other technical difficulties such as bigger foot print of the
equipment, testing problems and higher cost etc. Furthermore, higher the reactor value, higher copper content
269
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

would go into the reactor manufacture and hence the lesser the compliance to energy conservation principles as
reactor dissipates heat.
From the above analysis it is appropriate to select 0.3 ohm value of series current limiting reactor for the subject
application.
5.

IEC 60076-6 guide lines: [5]

IEC standard 60076-6 clause 8.4.2 requires thermal short circuit current Iscr to be specified by the purchaser.
Standard indicates two possible methods namely (a) Iscr shall not be less than the highest value of symmetrical
r.m.s current under recognized fault conditions, which may be seen by reactor, (b) alternatively the rated thermal
short circuit current may be derived from the specified system short circuit power, system voltage and reactor
impedance.
(a) Reactor current rating to be based on maximum symmetrical r.m.s current as seen by any reactor under
various operating conditions:
Based on the interpretation of (a) the recognized fault condition is either four reactors operating in parallel in
normal operating condition or three reactors operating in parallel for abnormal operating conditions for delivery
of 12 MW power to Substation ‘Z’. However, it can be noticed that when one reactor is in service, the Ip, and
Ik” are 34.0KA and 13.31KA respectively represent highest maximum currents through the reactor, although the
power delivered is 5.5MW, to Substation ‘Z’. Possibility of only one reactor being connected to Substation ‘Z’ is
very remote but may happen under severe abnormal operating conditions to run all the critical and essential loads
at Substation ‘Z’.
Table 12

CLR=0.3 ohms; Source X/R ratio 4.61 and Fault level = 2789MVA at 132KV level and Cable impedance between
Substation ‘X’ and Substation ‘Z’ is totally ignored ( As this would represent worst condition for Ik”)
Number of Reactors in Service

Short Circuit current at Substation ‘Z’ 11KV
Bus including down steam contributions
Ip (KA)
Ik” (KA)

Maximum Current through the Reactor
Ip (KA)

Ik” (KA)

Four Reactors in parallel
operation (power flow 12MW)

65.798

25.87

14.382

5.64

Three Reactors in parallel
operation (power flow 12MW)
Two Reactors in parallel
operation ( maximum power
flow 8.98MW)
One Reactor in operation ( Three
reactors out of service)
(maximum power flow 5.5MW )

61.825

24.247

17.8

6.98

55.306

21.618

23.36

9.16

42.642

16.605

34.0

13.31

From the above it can be noted that when only one reactor is in operation then Ik”current flow through reactor is
highest. Hence current values pertaining to this mode of operation is relevant for sizing of all the four reactors.
Accordingly, this calculated current with a safety factor can be considered as the maximum thermal short circuit
current rating of the Reactor.
(b) rated thermal short circuit current may be derived from the specified short circuit power, system voltage and
reactor impedance. On this aspect the following evaluation is carried out:
Assuming 132KV source impedance to be zero, the maximum steady state short circuit current at Substation ‘X’
11KV bus is 27KA. This corresponds to source impedance of 0.236 ohms.
Table 13
No. of reactors in service

4 reactors
3 reactors
2 reactors
1 reactor

Total Impedance (Source
impedance + Reactor
impedance + cable impedance)
(ohms)
0.236 + 0.075 +0.1 = 0.411
0.236 + 0.1+0.1 = 0.436
0.236 + 0.15 +0.1= 0.486
0.236 + 0.3 +0.1= 0.636

Fault current at Substation ‘Z’
(KA)

Current seen by each reactor
(KA)

15.45
14.57
13.07
9.9

3.86
4.86
6.53
9.9

Ignoring the cable impedance between Substation ‘X’ and Substation ‘Z’ the values are tabulated here under:

270
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)
Table 14
No. of reactors in service
Total Impedance (Source
Fault current at Substation ‘Z’
Current seen by each reactor
impedance + Reactor
(KA)
(KA)
impedance ) (ohms)
4 reactors
3 reactors
2 reactors
1 reactor

0.236 + 0.075 = 0.311
0.236 + 0.1 = 0.336
0.236 + 0.15 = 0.386
0.236 + 0.3 = 0.536

20.42
18.9
16.45
11.85

5.1
6.3
8.23
11.85

Both (a) and (b) are consistent. The values computed in (b) are steady state rms values as against values
computed in (a) are initial symmetrical r.m.s values. Hence a short circuit current rating Iscr of reactor can be
taken as Ik” value 13.31KA with a safety factor of additional 15% which equals to 16.64KA. Based on this rated
mechanical short circuit current (Imcr = 2.55Iscr) 42.42KA is assigned.
Duty Cycle: In the subject study, network does not have any auto re-closure systems. It is expected that after
occurrence of the short circuit, the general practice of fault investigation takes place before the reactor is put
back into service. Accordingly duty cycle requirement is not considered in the subject study.
6.

Insertion of Reactor into the electrical network and its impact:

Transient Recovery voltage: Presence of reactors in the electrical networks results in severe transient
phenomena during the breaker opening conditions under fault conditions [4],[6]. As the circuit breaker operates
to interrupt the fault currents (at Substation ‘X’ outgoing breaker for faults either in the reactor or on the cable
connecting to Substation Z or at Substation ‘Z’ incomer breaker for 11KV bus bar faults) current chopping takes
place leading to a transient phenomenon that may lead to restrike the arc between isolated poles of the circuit
breaker due to a very rapidly rising voltages across the poles. This is known as transient recovery voltage and
this depends upon
Circuit conditions & the parameters of the circuit
Fault current
Out of phase switching
First pole to Clear Factor and
Circuit Breaker Application
The transient recovery voltage can cause Insulation failures and/or Re-ignition and Re-strike of interrupting
mediums in the Circuit breakers. In other words TRV limits the interrupting capability of the circuit breaker. If a
circuit breaker is capable of withstanding TRV peak value and Rate of rise of voltage then Circuit breaker can
successfully interrupt the fault conditions.
In connection with transient recovery voltage the circuit breakers are assigned with the following important three
ratings:
Peak TRV in KV
Time to Peak of TRV in microseconds
Rate of Rise of Recovery Voltage (RRRV)
The TRV values are estimated in manual means by using the following formulae:
Calculation of the First Peak of TRV:
Contribution of the line side voltage (eL):
eL = d (1-M) x 0.816 x Ur
Ur is the rated maximum voltage = 11KV
M is the ratio of fault current to the rated short circuit current
d (peak factor) is dependent on ratio of surge impedance Zo/Z1, assumes a value of 1.6 which is considered to be
conservative.

271
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Contribution of source side voltage (es):
es = 2 x M ( TL -2)
The time to peak TL is determined by the following equations:
TL = eL/RL
RL = 1.414 wzMI
RL is the rate of rise (KV/µs)
TL is the time to peak (µs)
I rated short circuit current (KA) (40KA)
Z is the surge impedance considered as 50 ohms
TRV = es + eL
Applying the above equations the following values of TRV and RRRV for Substation ‘X’ (11KV, 40KA breaker)
are computed for various operating conditions:
Table 15
Number of reactors in service
Four Reactors

One reactor clearing fault
current (Rounded off) in KA
4

Transient Recovery voltage
(TRV in KV)
41.54

RRRV
KV/µs
0.287

Three Reactors

5

40.15

0.356

Two Reactors

7

37.8

0.5

One Reactor

10

34.125

0.701

Applying the above equations the following values of TRV and RRRV for Substation ‘Z’ (11KV, 25KA breaker)
are computed for various operating conditions: (in this case also surge impedance is taken as 50ohms, in reality
the surge impedance could be different as the bus bars and its configuration in Substation ‘Z’ would determine
the surge impedance).
Table 16
Number of reactors in service
Four Reactors

One reactor clearing fault
current (Rounded off) in KA
4

Transient Recovery voltage
(TRV in KV)
38.63

RRRV
KV/µs
0.454

Three Reactors

5

36.6

0.565

Two Reactors

7

32.41

0.783

One Reactor

10

26.45

1.089

From the above it can be seen that in both Substations X & Z TRV values are more than the acceptable standard
values of IEC 62271-100. A critical assessment is necessary with the aid of transient analyzer program for
quantifying other values of TRV. It is expected that in all these cases the calculated values will be more than the
standard TRV values indicated in the IEC 62271-100. It is known that as the short circuit current decreases the
TRV peak value increases and Time to peak will reduce thus increasing RRRV. As the estimated TRV values are
more than specified class S1 circuit breakers of IEC62271-100 the following are the ways of mitigation:
Provide appropriate size of capacitance to the circuit breaker terminals or across the terminals or increase the
internal capacitance of the reactor (manufacturer of the reactor can make proper proposal on appropriate method
of mitigation).
The impact of large capacitor bank at Substation ‘Z’ meant for power factor improvement at 11KV bus needs to
be assessed as to how these capacitor banks would effect TRV values and its mitigation at the circuit breakers of
the Substation ‘X’ and Substation ‘Z’. The 11KV system is resistance grounded at the transformer end. First
pole to clear factor is dependent on the system grounding. The subject study has not reviewed how the
resistance grounding at 11KV of Substation X would impact the TRV values if the terminal faults happen.
272
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Use higher voltage or higher current rating circuit breaker to handle the estimated value of TRV. This method is
costly and is not practicable in the subject study.
Resonance: The network under study has series limiting reactor between Substation ‘X’ & Substation ‘Z’ and
capacitor banks at Substation ‘Z’, there is a possibility that both series and parallel resonance may be generated.
Further harmonics are also present in the network. Harmonics present in the network may generate resonance
conditions apart from the TRV related resonance and mitigation capacitors across the reactor may also have on
resonant conditions. All the resonance issues will be studied and presented in a separate paper in due course of
time. Any resonant condition in the electrical network is detrimental as series resonance will result in high
harmonic currents and parallel resonance will result in high voltages & currents resulting in damage of
equipment.
Current Harmonics Impact on Reactor: Harmonics in the applied voltage and nonlinear magnetic characteristic
of the reactor results in harmonic currents that would cause additional heating of the reactor over and above
normal heating that would occur from the fundamental current. In the subject study, the harmonic distortion
VTHD is less than one (1) percent at Substation ‘X’, and reactor being oil filled type, it is assumed that heating
due to harmonic current will not be detrimental for the continuous operation of the series current limiting
reactors through the life of the reactors.
7.

Conclusion:

Although 0.3 ohm and 0.5 ohm value reactors appear to be acceptable from load flow, voltage regulation, short
circuit and motor starting aspects, choice of 0.5 ohm reactor is not correct that would lead to less efficient
electrical network from the energy conversation. Also, high reactor impedance means more copper content,
bigger foot print and higher cost.
In the above study it is brought out that, with the higher short circuit current rating & higher time withstand
rating of the short circuit current of the reactor, issues pertaining to testing would crop up as the reactors testing
may not be feasible due to limitations of testing houses. This is particularly the case with the reactors at 11KV
voltage level as the testing of the reactors for full rating currents may not be feasible.
After the impedance value of the reactor is finalized, evaluation of Transient Recovery Voltage related aspects is
very much necessary to verify the capability of installed circuit breaker to isolate the fault current under various
operating conditions. Where ever the calculated TRV ratings cross the limits of the installed circuit breaker
rating, mitigation measures are necessary. It can be noted that if higher impedance reactor value is chosen it is
likely that peak TRV values further increase as the short circuit current will further reduce.
Acknowledgements: Authors convey sincere thanks for the support rendered by Mr. Jasim Al Quraini Team
Leader Power Management and Mr. Abdul Rehman AL- Hujaili Team Leader Major Projects.
References:
1.

Reducing the Short Circuit Levels in Kuwait Transmission Network ( A Case Study) by Mahmoud Gilany
and Wael Al-Hasawi in World Academy of Science, Engineering Technology 53 2009 pages 592 to 596

2.

Limiting Short Circuit Currents in Oman Transmission System by Omar H. Abdalla* Senior Member IEEE
Hilal Al-Hadi, and Hisham Al Riyami, Member IEEE, Oman Electricity Transmission Company ( Sultanate
of Oman)

3.

Reducing The Short Circuit Levels in in QATAR Transmission System by Current Limiting Series Reactors.
Author: Irsahd Hussain Khramaa Qatar. GCC CIGRE 2010 Paper.

4.

Brazilian Successful Experience in the Usage of Current Limiting Reactors for Short Circuit Limitation by J.
Amon F., P.C.Femamdez, E.H.Rose, A.D’Ajuz, A Casthanheira paper presented at International conference
on Power Systems Transients (IPST’ 05) in Montreal, Canada on June 19-23, 2005 paper No. IPST05 -215

5.

IEC-60076-6

6.

Effects of Series Reactor on Short Circuit Current and Transient Recovery Voltage by GENG Zhen-Xin, XU
Jian-yuan, Tian Chi paper presented in 2008 International Conference on High Voltage Engineering and
Application, China November 9-13 2008.

273
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
This academic article was published by The International Institute for Science,
Technology and Education (IISTE). The IISTE is a pioneer in the Open Access
Publishing service based in the U.S. and Europe. The aim of the institute is
Accelerating Global Knowledge Sharing.
More information about the publisher can be found in the IISTE’s homepage:
http://www.iiste.org
CALL FOR JOURNAL PAPERS
The IISTE is currently hosting more than 30 peer-reviewed academic journals and
collaborating with academic institutions around the world. There’s no deadline for
submission. Prospective authors of IISTE journals can find the submission
instruction on the following page: http://www.iiste.org/journals/
The IISTE
editorial team promises to the review and publish all the qualified submissions in a
fast manner. All the journals articles are available online to the readers all over the
world without financial, legal, or technical barriers other than those inseparable from
gaining access to the internet itself. Printed version of the journals is also available
upon request of readers and authors.
MORE RESOURCES
Book publication information: http://www.iiste.org/book/
Recent conferences: http://www.iiste.org/conference/
IISTE Knowledge Sharing Partners
EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open
Archives Harvester, Bielefeld Academic Search Engine, Elektronische
Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial
Library , NewJour, Google Scholar

More Related Content

What's hot

TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSPower System Operation
 
Power control and power flow analysis
Power control and power flow analysisPower control and power flow analysis
Power control and power flow analysisjawaharramaya
 
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...Voltage Stability Based Formation of Voltage Control Areas Considering Impact...
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...IJAPEJOURNAL
 
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...Editor IJCATR
 
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET Journal
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_indiaganesh g
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET Journal
 
Modelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission SystemModelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission Systemijtsrd
 
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...IJERA Editor
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignLiving Online
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
High Voltage DC Transmission
High Voltage DC TransmissionHigh Voltage DC Transmission
High Voltage DC Transmissionkrishna koundinya
 
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...Franco Moriconi
 

What's hot (19)

TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
 
Mankotia ankit
Mankotia ankitMankotia ankit
Mankotia ankit
 
Power control and power flow analysis
Power control and power flow analysisPower control and power flow analysis
Power control and power flow analysis
 
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...Voltage Stability Based Formation of Voltage Control Areas Considering Impact...
Voltage Stability Based Formation of Voltage Control Areas Considering Impact...
 
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...
The DC-fault Blocking Capability by a New Hybrid Multilevel Converter in HVDC...
 
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
 
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_india
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
 
Hvdc
HvdcHvdc
Hvdc
 
Modelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission SystemModelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission System
 
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...
Control Method for Unified Power Quality Conditioner Using Fuzzy Based Nine-S...
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
High Voltage DC Transmission
High Voltage DC TransmissionHigh Voltage DC Transmission
High Voltage DC Transmission
 
report-paper-bheesette
report-paper-bheesettereport-paper-bheesette
report-paper-bheesette
 
HVDC presentation
HVDC presentationHVDC presentation
HVDC presentation
 
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
Design, Test and Demonstration of Saturable Reactor High-Temperature Supercon...
 
05 ropp sandia-epri_workshop_lrov_spod_05092016
05 ropp sandia-epri_workshop_lrov_spod_0509201605 ropp sandia-epri_workshop_lrov_spod_05092016
05 ropp sandia-epri_workshop_lrov_spod_05092016
 

Similar to Techno economic study of series current limiting reactor and its impact in the 11 kv network with harmonic pollution

THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMijiert bestjournal
 
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...Assessment of the Static Stability Margin and Voltage Profile Improvement in ...
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...Dr. Amarjeet Singh
 
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...elelijjournal
 
IRJET- A Systematic Approach to Design Single Phase Transformer Less Inve...
IRJET-  	  A Systematic Approach to Design Single Phase Transformer Less Inve...IRJET-  	  A Systematic Approach to Design Single Phase Transformer Less Inve...
IRJET- A Systematic Approach to Design Single Phase Transformer Less Inve...IRJET Journal
 
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET Journal
 
2005_A Review of Single-Phase Grid-Connected Inverters.pdf
2005_A Review of Single-Phase Grid-Connected Inverters.pdf2005_A Review of Single-Phase Grid-Connected Inverters.pdf
2005_A Review of Single-Phase Grid-Connected Inverters.pdfPKSahu6
 
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOAD
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOADSIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOAD
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOADijiert bestjournal
 
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...IRJET Journal
 
Frequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadFrequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadIAEME Publication
 
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...IRJET Journal
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...f95346
 
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEPERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEijiert bestjournal
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET Journal
 
Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...IJECEIAES
 
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...IRJET Journal
 
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATEPERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATEijiert bestjournal
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...IAEME Publication
 
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...IRJET Journal
 
fault current limiter based hybrid hvdc breaker
fault current limiter based hybrid hvdc breakerfault current limiter based hybrid hvdc breaker
fault current limiter based hybrid hvdc breakerwriteonpoint4you
 

Similar to Techno economic study of series current limiting reactor and its impact in the 11 kv network with harmonic pollution (20)

THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
 
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...Assessment of the Static Stability Margin and Voltage Profile Improvement in ...
Assessment of the Static Stability Margin and Voltage Profile Improvement in ...
 
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...
DESIGN OF THE ELECTRONIC LOAD CONTROLLER USING MICRO CONTROLLER BASED ZERO CR...
 
IRJET- A Systematic Approach to Design Single Phase Transformer Less Inve...
IRJET-  	  A Systematic Approach to Design Single Phase Transformer Less Inve...IRJET-  	  A Systematic Approach to Design Single Phase Transformer Less Inve...
IRJET- A Systematic Approach to Design Single Phase Transformer Less Inve...
 
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
 
2005_A Review of Single-Phase Grid-Connected Inverters.pdf
2005_A Review of Single-Phase Grid-Connected Inverters.pdf2005_A Review of Single-Phase Grid-Connected Inverters.pdf
2005_A Review of Single-Phase Grid-Connected Inverters.pdf
 
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOAD
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOADSIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOAD
SIMULATION STUDY OF QZSI Z-SOURCE INVERTER FOR RESISTIVE AND INDUCTIVE LOAD
 
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
 
Frequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable loadFrequency control in a microgrid including controllable load
Frequency control in a microgrid including controllable load
 
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
POWER QUALITY AND THD MITIGATION IN ELECTRIC VEHICLE CHARGING STATION BY THE ...
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
 
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEPERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
 
Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...Single core configurations of saturated core fault current limiter performanc...
Single core configurations of saturated core fault current limiter performanc...
 
A New Structure of Dynamic Voltage Restorer Based on Asymmetrical ī-source In...
A New Structure of Dynamic Voltage Restorer Based on Asymmetrical ī-source In...A New Structure of Dynamic Voltage Restorer Based on Asymmetrical ī-source In...
A New Structure of Dynamic Voltage Restorer Based on Asymmetrical ī-source In...
 
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
 
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATEPERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
PERFORMANCE OF LFAC TRANSMISSSION SYSTEM FOR TRANSIENT STATE
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
 
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...
IRJET- Controlling the Stator Flux Linkages to Improve Dynamic Behavior of Gr...
 
fault current limiter based hybrid hvdc breaker
fault current limiter based hybrid hvdc breakerfault current limiter based hybrid hvdc breaker
fault current limiter based hybrid hvdc breaker
 

More from Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inAlexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

More from Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Recently uploaded

Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Aggregage
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesAurelien Domont, MBA
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Environmental Impact Of Rotary Screw Compressors
Environmental Impact Of Rotary Screw CompressorsEnvironmental Impact Of Rotary Screw Compressors
Environmental Impact Of Rotary Screw Compressorselgieurope
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 

Recently uploaded (20)

Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and Templates
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Environmental Impact Of Rotary Screw Compressors
Environmental Impact Of Rotary Screw CompressorsEnvironmental Impact Of Rotary Screw Compressors
Environmental Impact Of Rotary Screw Compressors
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 

Techno economic study of series current limiting reactor and its impact in the 11 kv network with harmonic pollution

  • 1. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Techno-Economic Study of Series Current Limiting Reactor and Its Impact in the 11KV Network with Harmonic Pollution Y.V.SRIDHAR1* HAITHAM SAFAR2* NILESH MODI3 4 YOUSUF ALI YACOUB AL-DASHTI5 * Y.V.SRIDHAR1: ysridhar@kockw.com * HAITHAM SAFAR2: hsafar@kockw.com Abstract Survey & selection of oil filled fault current limiting series reactor for limiting short circuit fault currents from 40KA to 22KA at 11KV level in an existing distribution substation due to change of source substation. The impact of source X/R ratio variation, maximum & minimum short circuit currents on the acceleration times of the 11KV motors and variance in voltage regulation due to change(s) in the conventional Series reactor impedance is studied. Impact of power factor improvement capacitors on the short circuit level and on series reactor impedance is assessed. Expected harmonic pollution due to VSD’s is estimated and its influence on the series reactor impedances is assessed for resonant conditions. Transient Recovery Voltage and Rate of Rise of Recovery Voltage are studied for verification of circuit breakers’ ability to isolate the fault conditions. Techno economic evaluation of series reactor(s) impedance(s) for cost effectiveness along with the ability of reputed international testing houses for testing is assessed. The study results reflect that the constraints of test laboratories to test the specified series reactors will have an impact on the selection of series reactor impedance. While higher impedance selection will be useful from the short circuit point of view, it will pose difficulties with reference to physical dimensions of the equipment, cost and other related issues. Keywords: Current Limiting Reactor (CLR), Short Circuit Current, Harmonics, Cost Introduction: Ever increasing demand of electrical power [1], [2] necessitates increased power generation which in turn causes increased short circuit current at switchboards and equipment. Also network restructuring and modifications would pose issues related to short circuit capability of existing switchboards. Increased short circuit currents can cause severe mechanical and thermal stresses leading to damage of the equipment and operating facility. Many a times, it is not possible to replace the existing switchboards with higher rated short circuit capability due to production considerations and cost reasons. When the options of dividing the bus bars and/or splitting the network cannot be implemented due to reasons of reliability and security of power, and application of patented current limiters would pose issues related to installation & space constraints in the existing switchboards and substations, then the series current limiting reactor is an acceptable solution for limiting the short circuit currents. [1],[2]. This paper intends to present the various techno-economic aspects involved in the selection of series current limiting reactor and its application for limiting fault current from 11KV, 40KA at the source end substation to a level of 11KV, 25KA at the receiving end substation. Various types of series current limiting reactors are available in the market. It is noted that a revival of interest in the application of current limiting reactors coupled with solid state electronics schemes and superconductivity are in the various stages of development. Few of the applications appear to be successful in USA electrical networks. It is felt that for 11KV network distribution of a hydrocarbon industry, taking into consideration cost, familiarity and hands on aspects, the conventional type of series current limiting reactors are adequate for the subject application. 1. Brief Description of the electrical network: Substation ‘X’ is rated for 72MW at 11KV and feeds to Substation ‘Y’ and Substation ‘Z’. 264 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 2. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Figure1. Type and Nature of the connected load: Total maximum demand of Substation ‘Y’ is 55MW. Non-linear loads to the extent of 36MW operate on Substation ‘Y’ 11KV bus. Substation ‘Z’ has maximum demand of 12MW consisting of motors and power factor improvement capacitors at 11KV level. The other load composition consists of induction motors of various sizes connected to 3.3KV and 440 volt level along with associated transformers. Lighting loads and small nonlinear loads such as battery chargers, UPS systems, Computers and Switch Mode Power Supplies (SMPS) are connected at the 440 volts level. Presence of Harmonics and Harmonic related information: As the nonlinear loads operate at Substation ‘Y’ 11KV, harmonic pollution is present in the network. The main contribution of harmonics is from 11KV Variable speed drives. The Variable speed drives are of voltage source type with high pulse rectifiers. The capacity of UPS systems & Battery Charger(s) is much less than 15% of the corresponding transformer capacity at the 440 volt level hence the harmonic presence is ignored. 2. Reactor Related Preliminary Aspects: Type of Reactor: It is noted that application of air core, dry type reactors are more common in major electrical networks for the current limiting purposes. However taking into the consideration the existing practice and presence of traces of Hydrogen sulphide, outdoor type, three phase, air core, oil immersed, magnetically shielded series current limiting reactors are considered for the subject application and techno economic evaluation. Reactor location: Based on the constraints of space availability and extent of modification required at Substation ‘Z’, it is considered that installation of reactors will be part of the Substation ‘X’. Further installation of reactors at source end (optimum location for the reactors) has the advantage of reducing short circuit current on the linking cables from Substation ‘X’ to Substation ‘Z’. Manufacturer’s availability: It appeared from the survey that more number of manufacturers are available for dry type air core reactors. However few manufacturers are also interested in the manufacture of air core, oil filled type reactors. 3. ETAP system Studies: Size of the Reactor: For the purpose of limiting fault current which is at the level of 40KA at Substation ‘X’ to the level of 25KA at Substation ‘Z’ two reactor values 0.3 ohms and 0.5 ohms are considered. For each of the value of the reactor four varieties of system studies are conducted. They are namely Load flow study Short Circuit study 265 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 3. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Motor starting capability study Harmonic Assessment study. Load Flow Study: Initially Substation ‘Z’ was fed from the Substation ‘W’ (not indicated in the Figure 1). During the process of network reorganization, Substation ‘Z’ is proposed to be fed from Substation ‘X’. Introducing Series Current Limiting Reactors in the electrical network would increase the impedance of the network and other networks parameters have also changed due to the network modifications, Load Flow study is carried out for the verification of required power flow and voltage regulation aspects. From the ETAP Load Flow studies, it is noted that the voltage regulation and power flow related aspects are within the acceptable range for both 0.3 and 0.5 ohm reactors [3], [4]. Short Circuit Study: Before the network modification, the short circuit level at Substation ‘Z’ was 17.0KA (Ik) as against switchboard rating of 25KA. At the new source substation (Substation ‘X’), the calculated fault level is in the range of 27KA (Ik) from utility without considering fault contribution from the downstream and switchboard is rated for 40KA. To ensure that the Substation ‘Z’ fault level does not increase to 22KA, system studies are carried out for both 0.3ohm and 0.5ohm Series Current Limiting Reactor values. It is to be noted that the presence of capacitor banks at Substation ‘C’ will not alter the peak short circuit current (Ik”) at the 11KV bus and hence ignored. X/R ratio and its impact: It is known that utility undertaking fault levels are increasing and system impedances values are expected to change due to power increase and expansion of network at the utility end. Although it is not possible to assess how much increase in the short circuit current will be available in future and how much variation will be there in the X/R ratio, a few calculations were carried out by varying the X/R ratio and source short circuit currents and its impact on the load flow and short circuit currents at the Substations. The ETAP results are mentioned hereunder in Table 1, 2, 3, 4 and 5. The below projected current values are based on the three phase fault simulations. Table 1 Impedance value of CLR = 0.3 ohm Source X/R = 4.61 Substation Name Source X/R = 6 Source X/R = 18 Source X/R = 30 Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) 1 Substation X 99.5 10.945 99.5 10.945 99.5 10.945 99.5 10.945 2 Substation Y 98.98 10.888 98.98 10.888 98.98 10.888 98.98 10.888 3 Substation Z 98.96 10.885 98.96 10.885 98.96 10.885 98.96 10.885 Table 2 Impedance value of CLR = 0.5 ohm Source X/R = 4.61 Substation Name Source X/R = 6 Source X/R = 18 Source X/R = 30 Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) Voltage (%) Voltage (KV) 1 Substation X 99.48 10.943 99.48 10.943 99.48 10.943 99.48 10.943 2 Substation Y 98.96 10.886 98.96 10.886 98.96 10.886 98.96 10.886 3 Substation Z 98.77 10.865 98.77 10.865 98.77 10.865 98.77 10.865 Table 3 Impedance value of CLR = 0.3 ohm; Source Fault Level (max) =2789 MVA at 132KV level Source X/R = 4.61 Source X/R = 6 Source X/R = 18 Source X/R = 30 Substation Name Ik” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) 1 Substation X 32.524 81.824 26.331 32.483 82.574 26.298 32.424 84.435 26.258 32.417 84.839 26.256 2 Substation Y 30.332 74.032 24.556 30.302 74.648 24.532 30.265 76.173 24.51 30.262 76.503 24.511 3 Substation Z 24.108 58.027 19.237 24.092 58.382 19.224 24.074 59.257 19.217 24.073 59.446 19.218 266 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 4. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Table 4 Impedance value of CLR = 0.5 ohm ; Source Fault Level(max) = 2789 MVA at 132KV level Source X/R = 4.61 Source X/R = 6 Source X/R = 18 Source X/R = 30 Substation Name Ik” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) lk” (KA) lp (KA) lk (KA) 1 Substation X 32.459 81.703 26.331 32.418 82.454 26.298 32.359 84.317 26.258 32.353 84.721 26.256 2 Substation Y 30.277 73.936 24.556 30.247 74.552 24.532 30.21 76.078 24.51 30.208 76.409 24.511 3 Substation Z 21.54 52.44 17.018 21.526 52.718 17.007 21.509 53.401 16.999 21.508 53.548 17 Table 5 Source X/R = 4.61 Source X/R = 6 Source X/R = 18 Source X/R = 30 Ik" Ik" Ik" Ik" Ip (KA) Ik (KA) Ip (KA) Ik (KA) Ip (KA) Ik (KA) Ip (KA) Ik (KA) (KA) (KA) (KA) (KA) Impedance value of CLR = 0.3 ohm, Source Fault level = 5000 MVA at 132KV level Substation Z 25.319 61.514 20.532 25.309 61.743 20.523 25.297 62.303 20.518 25.297 62.423 20.519 63.794 21.120 55.874 18.010 56.934 18.472 Impedance value of CLR = 0.3 ohm, Source Fault level = 7500 MVA at 132KV level Substation Z 25.879 63.15 21.129 25.871 63.312 21.123 25.863 63.709 21.119 25.863 Impedance value of CLR = 0.5 ohm, Source Fault level = 5000 MVA at 132KV level Substation Z 22.462 55.175 18.022 22.453 55.350 18.015 22.442 55.781 18.009 22.442 Impedance value of CLR = 0.5 ohm, Source Fault level = 7500 MVA at 132KV level Substation Z 22.883 56.442 18.480 22.877 56.566 18.475 22.869 56.869 18.471 22.869 Motor Starting Capability: Substation ‘Z’ has approximately 3500KW rated motors in multiple numbers that operate at 11KV level in Direct On Line Mode. Studies were carried out for motor starting capability for both the values of Current Limiting Reactors (CLRs) when the line voltage at Substation ‘Z’ falls down to 80% which represents worst operating condition. Introduction of CLR did not change the motor starting times much at Substation ‘Z’. The results are mentioned hereunder in Table 6. Table 6 Substation C Motor Starting Time (in seconds) at Source Fault Level(minimum) = 1852 MVA at 132KV level Impedance value of CLR = 0.3 ohm Source X/R = 6.04 Source X/R =12 Time for Motor Starting in Time for Motor Starting in seconds seconds 4.2 4.2 Impedance value of CLR = 0.5 ohm Source X/R = 6.04 Source X/R = 12 Time for Motor Starting in Time for Motor Starting in seconds seconds 4.2 4.2 Power Factor: The voltage drop at the reactor is a function of the power factor. It is mandatory to maintain 0.95 power factor at Substation ‘X’ 11KV bus bar. Substation ‘Z’ has two numbers capacitor banks each of size 1800 KVAr operating on 11KV bus. The VSD’s at Substation ‘Y’ are intended to be operated at high power factor in the range of 0.95 to 0.97 during their continuous operation. The ETAP studies indicates power factor at 11KV buses of various substations as indicated in the Table 7. Table 7 Substation Substation X Substation Y Substation Z Impedance value of CLR = 0.3 ohm 3 Tr, 3 CLR 3 Tr, 4 CLR 4 Tr, 4 CLR 97.8 98 97.9 98.1 97.7 97.7 84.8 85.2 85.2 Impedance value of CLR = 0.5 ohm 3 Tr, 3 CLR 3 Tr, 4 CLR 4 Tr, 4 CLR 97.8 97.8 97.8 98.1 97.7 97.7 84.8 85.2 85.2 Harmonic Assessment Study: Substation ‘Y’ has considerable number of variable speed drives of 4MW rating. Harmonic Assessment study indicated the following results of Voltage and current Distortion with Current Limiting Reactors of 0.3ohm and 0.5ohm at 11KV levels of respective substations: 267 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 5. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Table 8 Substation Name VTHD% for CLR 0.3 Ohm VTHD% for CLR 0.5ohm Substation X 0.97 0.99 Substation Y Substation Z 0.99 1.22 1.03 1.1 Table 9 Substation Name ITHD% for CLR 0.3 Ohm ITHD% for CLR 0.5ohm Substation X xxx xxx Substation Y Substation Z xxx xxx xxx xxx From the evaluation of above system studies with both 0.3ohm and 0.5 ohm reactors, generally it appears that 0.3 ohm and 0.5 ohm reactors are acceptable for X/R ratio of 4.61 and Utility source fault level of 2789MVA at 132 KV level, at higher levels of source fault level, the Ip are marginally higher than the switchboard assigned ratings for 0.3 ohm rated reactors. Please refer Table 10 for comparison of results: Table 10 Evaluation basis 0.3 ohm CLR 0.5 ohm CLR Remarks Load Flow Study for present value of X/R ratio 4.6 and Utility fault level at 2789 MVA Load flow for variations of Utility X/R ratio variation ETAP results are technically Acceptable ETAP results are technically acceptable Based on the results both CLR values are acceptable. ETAP Results are technically acceptable ETAP results are technically acceptable Short Circuit Study for present value of X/R ratio 4.6 and Utility fault level at 2789 MVA Short Circuit Study for variations of Utility X/R ratio and projected Utility fault level at 5000 MVA ETAP Results are technically acceptable ETAP results are technically acceptable ETAP Results are not technically acceptable ETAP results are technically acceptable Short Circuit Study for variations of Utility X/R ratio and projected Utility fault level at 7500MVA ETAP Results are not technically acceptable ETAP results are technically acceptable Motor starting time study ETAP Results are technically acceptable ETAP results are technically acceptable Power factor 0.95 power factor can be maintained for various modes of network operation 0.95 power factor can be maintained for various modes network operation Harmonic Study VTHD values are less than acceptable 5% limit. VTHD values are less than acceptable 5% limit. X/R ratio variation is imaginary for the study purposes. This study represents present situation where X/R ratio 4.6 and Fault level 2789 MVA is obtained from Utility With the imaginary values of X/R and short circuit values 0.3 ohm CLR is very close to the rated values and not technically acceptable. However 0.5 ohm CLR is acceptable With the imaginary values of X/R and short circuit values 0.3 ohm CLR is not acceptable. However 0.5 ohm CLR is acceptable Both 0.3ohm and 0.5 ohm CLRs are acceptable. The results projected in the table 6 are based on X/R = 4.6 and source minimum fault level of 1852MVA. Both 0.3 ohm and 0.5 ohm current limiting reactors acceptable for maintaining the power factor at substation X. Both 0.3 ohm and 0.5 ohm current limit reactor values are technically acceptable. If so, general conclusion will be why not to opt for 0.5 ohm CLR which will ensure lower short circuit current at Substation ‘Z’ 11KV switchboard. However, prior to conclusion of the reactor ohm value other Reactor’s critical parameters need to be assessed. 4. Series Current Limiting Reactor’s Critical Parameters: For current limiting reactors, in general three phase short circuit is usually the basis for specifying various parameters [5]. In an electrical network, three currents are that dealt with. Ip (peak short circuit current), Ik” (initial symmetrical short circuit current) and Ik (steady state short circuit current). In numerical terms of kilo amps, Ip is greater than Ik” and Ik” is greater than Ik. In general the Ip & Ik” current that flows in the reactor are 268 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 6. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) the parameters that would influence the design and selection of reactor. Ip current deals with mechanical bracing requirements of reactor whereas Ik” deals with maximum short circuit current that flows in the reactor. In general, as the substations are far from the generating stations, it is customary to take Ik” to Ik. However, where ever the value of Ik” is known it is recommended to use Ik” value instead of Ik value. Reactor continuous current rating: Continuous flow of current that would flow under steady state operating conditions to deliver the Continuous power to Substation ‘Z’ is the minimum current rating of the Current Limiting Reactor. Reactor short circuit current time rating: In any electrical network all power components are assigned standard time ratings based on the need to withstand short circuit currents. These standard ratings are generally for one (1) second or three (3) seconds for the High Tension switchboards. However for current limiting reactors a minimum of two (2) seconds time rating shall be the standard value in line with clause 8.4.3 of IEC 60076-6. In the present context in line with the current design practice, three (3) seconds time rating is assigned for current limiting reactors. Reactor short circuit current rating: This is an important rating that is required to be specified by the designer. Electrical equipment has standard short circuit ratings. For example, relevant IEC standard assigns standard ratings for an 11KV switchboard 25KA, 31.5KA and 40KA etc. However for reactors there are no such standard ratings assigned by IEC standards. This rating is to be determined by the designer to suit to the electrical network requirements. Then the question arises as to what shall be basis for specifying such fault current rating. In the subject study following three aspects is considered: Reactor rating of 40KA for 3 seconds: As the reactors are physically close to the Substation ‘X’ which has 11KV switchboard with short circuit fault rating of 40KA (3seconds), is it required to assign CLR rating to be for 40KA for 3 seconds as the reactor primary terminals will see 40KA fault current ? Reactor rating of 25KA for 3 seconds: As the reactor is limiting the fault current to 25KA at Substation ‘Z’, is it required to be rated for 25KA for 3 seconds? Assigning a rating of 40KA for 3 seconds or 25KA 3 seconds would make the reactors bulky and costly. Please see the Table 11 below which does not include any space and civil construction costs: Table 11 Reactor value in Ohms Assigned current rating Approximate Physical dimensions of each reactor. L X W X H (all in meters) Approximate Weight of the reactor Indicative Budgetary Cost of each reactor 0.3 40KA/3seconds 2.5 X 2.5 X 4.6 12 tons PRICE 0.5 40KA/3seconds 7.0 X 3.5 X 4.0 50 tons 3.125 x PRICE 0.5 25KA/3seconds 5.0 X 2.5 X4.0 27 tons 1.875 x PRICE Reactor Testing & International Testing houses: The above cost figures are non-inclusive of reactor testing costs. It is important to note that short circuit test of current limiting reactors is a special test and will not be performed by the manufacturer unless specifically requested for. This test will prove the ability of the reactor to with stand short circuit current for the specified time. On survey of testing houses it is noted that 0.3 ohms 40KA/3seconds reactors cannot be tested for full 40 KA for time period of 3 seconds due to the limitations of the test facilities at most of the reputed testing houses. Few of the testing houses declined to indicate the costs involved and few other testing houses suggested reduction of both time rating and short circuit current rating of the reactors for the purpose of testing of reactors. Although 0.5 ohm value Reactor can be tested but the cost involved is very high and is in the range of 60% to 70% of reactor cost. The cost and physical dimensions of the reactor depends on the ohm value, short circuit current & time rating of the reactor. Fixation of the ohm value of the Reactor: Based on the above, it can be noted that specifying higher ohm value for a reactor is not only inappropriate and lead to other technical difficulties such as bigger foot print of the equipment, testing problems and higher cost etc. Furthermore, higher the reactor value, higher copper content 269 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 7. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) would go into the reactor manufacture and hence the lesser the compliance to energy conservation principles as reactor dissipates heat. From the above analysis it is appropriate to select 0.3 ohm value of series current limiting reactor for the subject application. 5. IEC 60076-6 guide lines: [5] IEC standard 60076-6 clause 8.4.2 requires thermal short circuit current Iscr to be specified by the purchaser. Standard indicates two possible methods namely (a) Iscr shall not be less than the highest value of symmetrical r.m.s current under recognized fault conditions, which may be seen by reactor, (b) alternatively the rated thermal short circuit current may be derived from the specified system short circuit power, system voltage and reactor impedance. (a) Reactor current rating to be based on maximum symmetrical r.m.s current as seen by any reactor under various operating conditions: Based on the interpretation of (a) the recognized fault condition is either four reactors operating in parallel in normal operating condition or three reactors operating in parallel for abnormal operating conditions for delivery of 12 MW power to Substation ‘Z’. However, it can be noticed that when one reactor is in service, the Ip, and Ik” are 34.0KA and 13.31KA respectively represent highest maximum currents through the reactor, although the power delivered is 5.5MW, to Substation ‘Z’. Possibility of only one reactor being connected to Substation ‘Z’ is very remote but may happen under severe abnormal operating conditions to run all the critical and essential loads at Substation ‘Z’. Table 12 CLR=0.3 ohms; Source X/R ratio 4.61 and Fault level = 2789MVA at 132KV level and Cable impedance between Substation ‘X’ and Substation ‘Z’ is totally ignored ( As this would represent worst condition for Ik”) Number of Reactors in Service Short Circuit current at Substation ‘Z’ 11KV Bus including down steam contributions Ip (KA) Ik” (KA) Maximum Current through the Reactor Ip (KA) Ik” (KA) Four Reactors in parallel operation (power flow 12MW) 65.798 25.87 14.382 5.64 Three Reactors in parallel operation (power flow 12MW) Two Reactors in parallel operation ( maximum power flow 8.98MW) One Reactor in operation ( Three reactors out of service) (maximum power flow 5.5MW ) 61.825 24.247 17.8 6.98 55.306 21.618 23.36 9.16 42.642 16.605 34.0 13.31 From the above it can be noted that when only one reactor is in operation then Ik”current flow through reactor is highest. Hence current values pertaining to this mode of operation is relevant for sizing of all the four reactors. Accordingly, this calculated current with a safety factor can be considered as the maximum thermal short circuit current rating of the Reactor. (b) rated thermal short circuit current may be derived from the specified short circuit power, system voltage and reactor impedance. On this aspect the following evaluation is carried out: Assuming 132KV source impedance to be zero, the maximum steady state short circuit current at Substation ‘X’ 11KV bus is 27KA. This corresponds to source impedance of 0.236 ohms. Table 13 No. of reactors in service 4 reactors 3 reactors 2 reactors 1 reactor Total Impedance (Source impedance + Reactor impedance + cable impedance) (ohms) 0.236 + 0.075 +0.1 = 0.411 0.236 + 0.1+0.1 = 0.436 0.236 + 0.15 +0.1= 0.486 0.236 + 0.3 +0.1= 0.636 Fault current at Substation ‘Z’ (KA) Current seen by each reactor (KA) 15.45 14.57 13.07 9.9 3.86 4.86 6.53 9.9 Ignoring the cable impedance between Substation ‘X’ and Substation ‘Z’ the values are tabulated here under: 270 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 8. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Table 14 No. of reactors in service Total Impedance (Source Fault current at Substation ‘Z’ Current seen by each reactor impedance + Reactor (KA) (KA) impedance ) (ohms) 4 reactors 3 reactors 2 reactors 1 reactor 0.236 + 0.075 = 0.311 0.236 + 0.1 = 0.336 0.236 + 0.15 = 0.386 0.236 + 0.3 = 0.536 20.42 18.9 16.45 11.85 5.1 6.3 8.23 11.85 Both (a) and (b) are consistent. The values computed in (b) are steady state rms values as against values computed in (a) are initial symmetrical r.m.s values. Hence a short circuit current rating Iscr of reactor can be taken as Ik” value 13.31KA with a safety factor of additional 15% which equals to 16.64KA. Based on this rated mechanical short circuit current (Imcr = 2.55Iscr) 42.42KA is assigned. Duty Cycle: In the subject study, network does not have any auto re-closure systems. It is expected that after occurrence of the short circuit, the general practice of fault investigation takes place before the reactor is put back into service. Accordingly duty cycle requirement is not considered in the subject study. 6. Insertion of Reactor into the electrical network and its impact: Transient Recovery voltage: Presence of reactors in the electrical networks results in severe transient phenomena during the breaker opening conditions under fault conditions [4],[6]. As the circuit breaker operates to interrupt the fault currents (at Substation ‘X’ outgoing breaker for faults either in the reactor or on the cable connecting to Substation Z or at Substation ‘Z’ incomer breaker for 11KV bus bar faults) current chopping takes place leading to a transient phenomenon that may lead to restrike the arc between isolated poles of the circuit breaker due to a very rapidly rising voltages across the poles. This is known as transient recovery voltage and this depends upon Circuit conditions & the parameters of the circuit Fault current Out of phase switching First pole to Clear Factor and Circuit Breaker Application The transient recovery voltage can cause Insulation failures and/or Re-ignition and Re-strike of interrupting mediums in the Circuit breakers. In other words TRV limits the interrupting capability of the circuit breaker. If a circuit breaker is capable of withstanding TRV peak value and Rate of rise of voltage then Circuit breaker can successfully interrupt the fault conditions. In connection with transient recovery voltage the circuit breakers are assigned with the following important three ratings: Peak TRV in KV Time to Peak of TRV in microseconds Rate of Rise of Recovery Voltage (RRRV) The TRV values are estimated in manual means by using the following formulae: Calculation of the First Peak of TRV: Contribution of the line side voltage (eL): eL = d (1-M) x 0.816 x Ur Ur is the rated maximum voltage = 11KV M is the ratio of fault current to the rated short circuit current d (peak factor) is dependent on ratio of surge impedance Zo/Z1, assumes a value of 1.6 which is considered to be conservative. 271 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 9. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Contribution of source side voltage (es): es = 2 x M ( TL -2) The time to peak TL is determined by the following equations: TL = eL/RL RL = 1.414 wzMI RL is the rate of rise (KV/µs) TL is the time to peak (µs) I rated short circuit current (KA) (40KA) Z is the surge impedance considered as 50 ohms TRV = es + eL Applying the above equations the following values of TRV and RRRV for Substation ‘X’ (11KV, 40KA breaker) are computed for various operating conditions: Table 15 Number of reactors in service Four Reactors One reactor clearing fault current (Rounded off) in KA 4 Transient Recovery voltage (TRV in KV) 41.54 RRRV KV/µs 0.287 Three Reactors 5 40.15 0.356 Two Reactors 7 37.8 0.5 One Reactor 10 34.125 0.701 Applying the above equations the following values of TRV and RRRV for Substation ‘Z’ (11KV, 25KA breaker) are computed for various operating conditions: (in this case also surge impedance is taken as 50ohms, in reality the surge impedance could be different as the bus bars and its configuration in Substation ‘Z’ would determine the surge impedance). Table 16 Number of reactors in service Four Reactors One reactor clearing fault current (Rounded off) in KA 4 Transient Recovery voltage (TRV in KV) 38.63 RRRV KV/µs 0.454 Three Reactors 5 36.6 0.565 Two Reactors 7 32.41 0.783 One Reactor 10 26.45 1.089 From the above it can be seen that in both Substations X & Z TRV values are more than the acceptable standard values of IEC 62271-100. A critical assessment is necessary with the aid of transient analyzer program for quantifying other values of TRV. It is expected that in all these cases the calculated values will be more than the standard TRV values indicated in the IEC 62271-100. It is known that as the short circuit current decreases the TRV peak value increases and Time to peak will reduce thus increasing RRRV. As the estimated TRV values are more than specified class S1 circuit breakers of IEC62271-100 the following are the ways of mitigation: Provide appropriate size of capacitance to the circuit breaker terminals or across the terminals or increase the internal capacitance of the reactor (manufacturer of the reactor can make proper proposal on appropriate method of mitigation). The impact of large capacitor bank at Substation ‘Z’ meant for power factor improvement at 11KV bus needs to be assessed as to how these capacitor banks would effect TRV values and its mitigation at the circuit breakers of the Substation ‘X’ and Substation ‘Z’. The 11KV system is resistance grounded at the transformer end. First pole to clear factor is dependent on the system grounding. The subject study has not reviewed how the resistance grounding at 11KV of Substation X would impact the TRV values if the terminal faults happen. 272 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 10. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Use higher voltage or higher current rating circuit breaker to handle the estimated value of TRV. This method is costly and is not practicable in the subject study. Resonance: The network under study has series limiting reactor between Substation ‘X’ & Substation ‘Z’ and capacitor banks at Substation ‘Z’, there is a possibility that both series and parallel resonance may be generated. Further harmonics are also present in the network. Harmonics present in the network may generate resonance conditions apart from the TRV related resonance and mitigation capacitors across the reactor may also have on resonant conditions. All the resonance issues will be studied and presented in a separate paper in due course of time. Any resonant condition in the electrical network is detrimental as series resonance will result in high harmonic currents and parallel resonance will result in high voltages & currents resulting in damage of equipment. Current Harmonics Impact on Reactor: Harmonics in the applied voltage and nonlinear magnetic characteristic of the reactor results in harmonic currents that would cause additional heating of the reactor over and above normal heating that would occur from the fundamental current. In the subject study, the harmonic distortion VTHD is less than one (1) percent at Substation ‘X’, and reactor being oil filled type, it is assumed that heating due to harmonic current will not be detrimental for the continuous operation of the series current limiting reactors through the life of the reactors. 7. Conclusion: Although 0.3 ohm and 0.5 ohm value reactors appear to be acceptable from load flow, voltage regulation, short circuit and motor starting aspects, choice of 0.5 ohm reactor is not correct that would lead to less efficient electrical network from the energy conversation. Also, high reactor impedance means more copper content, bigger foot print and higher cost. In the above study it is brought out that, with the higher short circuit current rating & higher time withstand rating of the short circuit current of the reactor, issues pertaining to testing would crop up as the reactors testing may not be feasible due to limitations of testing houses. This is particularly the case with the reactors at 11KV voltage level as the testing of the reactors for full rating currents may not be feasible. After the impedance value of the reactor is finalized, evaluation of Transient Recovery Voltage related aspects is very much necessary to verify the capability of installed circuit breaker to isolate the fault current under various operating conditions. Where ever the calculated TRV ratings cross the limits of the installed circuit breaker rating, mitigation measures are necessary. It can be noted that if higher impedance reactor value is chosen it is likely that peak TRV values further increase as the short circuit current will further reduce. Acknowledgements: Authors convey sincere thanks for the support rendered by Mr. Jasim Al Quraini Team Leader Power Management and Mr. Abdul Rehman AL- Hujaili Team Leader Major Projects. References: 1. Reducing the Short Circuit Levels in Kuwait Transmission Network ( A Case Study) by Mahmoud Gilany and Wael Al-Hasawi in World Academy of Science, Engineering Technology 53 2009 pages 592 to 596 2. Limiting Short Circuit Currents in Oman Transmission System by Omar H. Abdalla* Senior Member IEEE Hilal Al-Hadi, and Hisham Al Riyami, Member IEEE, Oman Electricity Transmission Company ( Sultanate of Oman) 3. Reducing The Short Circuit Levels in in QATAR Transmission System by Current Limiting Series Reactors. Author: Irsahd Hussain Khramaa Qatar. GCC CIGRE 2010 Paper. 4. Brazilian Successful Experience in the Usage of Current Limiting Reactors for Short Circuit Limitation by J. Amon F., P.C.Femamdez, E.H.Rose, A.D’Ajuz, A Casthanheira paper presented at International conference on Power Systems Transients (IPST’ 05) in Montreal, Canada on June 19-23, 2005 paper No. IPST05 -215 5. IEC-60076-6 6. Effects of Series Reactor on Short Circuit Current and Transient Recovery Voltage by GENG Zhen-Xin, XU Jian-yuan, Tian Chi paper presented in 2008 International Conference on High Voltage Engineering and Application, China November 9-13 2008. 273 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 11. This academic article was published by The International Institute for Science, Technology and Education (IISTE). The IISTE is a pioneer in the Open Access Publishing service based in the U.S. and Europe. The aim of the institute is Accelerating Global Knowledge Sharing. More information about the publisher can be found in the IISTE’s homepage: http://www.iiste.org CALL FOR JOURNAL PAPERS The IISTE is currently hosting more than 30 peer-reviewed academic journals and collaborating with academic institutions around the world. There’s no deadline for submission. Prospective authors of IISTE journals can find the submission instruction on the following page: http://www.iiste.org/journals/ The IISTE editorial team promises to the review and publish all the qualified submissions in a fast manner. All the journals articles are available online to the readers all over the world without financial, legal, or technical barriers other than those inseparable from gaining access to the internet itself. Printed version of the journals is also available upon request of readers and authors. MORE RESOURCES Book publication information: http://www.iiste.org/book/ Recent conferences: http://www.iiste.org/conference/ IISTE Knowledge Sharing Partners EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial Library , NewJour, Google Scholar