The document outlines a module assembly factory acceptance test procedure with 7 steps: 1) The project manager determines representatives for inspection; 2) Schedules inspections with client and vendor; 3) Compiles drawings and specifications for inspection; 4) Representatives take inspection package and conduct factory acceptance test; 5) Representatives issue punch list after each visit; 6) Repeat steps until unit is acceptable for shipment; 7) KMPS signs acceptance document upon successful completion.