7. Underground Work- Hawthorne May 2017
Underground Work- West End May 2017
Hawthorne Lane Bridge Work Begins July 2017
Underground Work – Uptown Jan. 2018
Reopening of Hawthorne Lane Bridge Jan. 2019
Construction Complete March 2020
7
Milestones
8. The order in which work will occur within each of the work corridors…
1. Underground work
– (Storm Water, Water, Sewer, Conduit, and
drilling for OCS foundations).
2. Trackwork
3. Overhead Catenary System Installation
4. Systems and vehicle testing
8
Sequencing
10. Hawthorne Bridge
Hawthorne Bridge
• Replace bridge deck and
center pier
Hawthorne Lane closed
between Central Avenue and
7th Street
• 18 months to construct
• Detour: 7th to Central
10
13. 13
• Turner Avenue Streetscape
• State Street Pedestrian Improvements
• Stewart Avenue to Chamberlain Avenue
Street Connectivity
• Yellowstone Drive to Zebulon Drive
Street Connectivity
• State Street & Stewart Creek Pedestrian
Crossing Improvements
• Frazier Avenue Realignment
• West Fourth Street Improvements
• Five Points Plaza
• I-77 Underpass Enhancement
Project at West Trade Street
• www.CharlotteFuture.com
CNIP Projects
14. 14
Charlotte Gateway
Station
• Multi-modal transportation
facility
• Provide connections to
• Future regional rail
• Streetcar
• Inter-city rail & bus
Gold Line project
coordinating with new CGS
bridge over Trade Street.
16. Begin Construction February 2017
- Begin Vehicle Production March 2017
- Vehicle Testing on Blue Line August 2019
- Receive last vehicle October 2019
Complete Construction March 2020
- Vehicle Testing on Gold Line March - Aug 2020
Open for Service August 2020
16
Vehicle Schedule
17. 2030 plan
2030 Transit Corridor System Plan:
• Supports mixture of land uses
• Enhances quality of life
• Supports sustainable growth
• Enhances pedestrian environment
• Reduces road dependence
• Contributes to attainment of air
quality standards
Streetcar will help accomplish
these goals.
17
23. 23
Communication
• Visit RideTransit.org
• Under CATS
General
Information select
CityLYNX Gold Line
• Receive email
notices
• Road Closure
• Project Updates
• Newsletters
24. Social Media
@CityLYNXgoldLineUpdates
@CityLYNXupdates
– Road Closures
– Project Updates
– Photos
– Newsletters
24
Communication
Door-to-door
Canvassing
Occurs with businesses and
residents directly affected by
construction.
Example: Coordination on
driveway access, service outage,
etc…
25. o Email alerts - Notify Me
o www.ridetransit.org
How You Can Stay Informed on Gold Line
Stay Connected
25
Editor's Notes
We need a picture added.
CityLYNX Gold Line Phase 2
Extends Phase 1 by 2.5 miles creating a 4 mile operating system with 8 miles of track
$150M project -50% federal funding with 50% local match
February 19, 2014 began Project Development
May 2016, FTA Approved the Small Starts Grant Agreement
November 2016, City Council Awarded two contracts
Vehicles: Siemens – six S70 hybrid modern streetcars
Construction: The Johnson Bros. Corporation of Roanoke, Texas
Project Opened in July 2015
Thank you
Talk about platform raising. At end of construction/no streetcar service.
Transition slide utils- copnstruction
The westside CNIP (Comprehensive Neighborhood Improvement Program) group is partnering with the project to realign Frazier Avenue to line up with Wesley Heights Way. The two projects will be built simultaneously. This will allow access from Wesley Heights Way to 5th Street. This road will be used during construction to allow local access for the Wesley Heights area. This will also include a traffic signal at the newly created intersection of Wesley Heights Way/Trade & Frazier.
Hawthorne Lane at current elevation and alignment
8 foot sidewalks and pedestrian scale lighting
4.5 foot high bridge railing for bicycle safety
Decorative concrete detail on railings
Landscaping and noise walls relative to the Independence Widening
Hawthorne Lane at current elevation and alignment
8 foot sidewalks and pedestrian scale lighting
4.5 foot high bridge railing for bicycle safety
Decorative concrete detail on railings
Landscaping and noise walls relative to the Independence Widening
Continue with their public outreach. Unrelated to the Gold Line project, but we are working with them. Please continue to attend their charrettes and public meetings.
RFI,
Actual Vehicles
RFP Schedule
Fare & Fare Collection
Notice the streetcar connects the commuter and light rail lines.
Branding
Siemens – Seated 56, Standees 151, Total 207 AW2 (4/m2)
Seated 56, Standees 199, Total 255 AW3 (6/m2)
Stay up to date on Gold Line Phase 2 through various ways.