SlideShare a Scribd company logo
1 of 29
A Case Study of Delay Analysis in Construction
Project : Al kut Olympic Stadium
Gaurav Verma
Final Year Civil Engineering,
Dayalbagh Educational Institute,
Dayalbagh, Agra
May, 2021
https://www.linkedin.com/in/
gaurav-verma-5663b0174
gaurav170350@dei.ac.in
Outlines
 Construction Delays.
 Types of Delays in Construction Projects.
 Effects of Construction Delays.
 Location of Al Kut Olympic Stadium.
 Scope of Study.
 Objectives of study.
 Research Methodology.
 Result Analysis.
 Summary.
Construction Delays
 Construction delays are considered as time lag in completion of activities from its specified time as per
contract or can be defined as late completion or late start of activities to the baseline schedule, directly
affecting specified cost. As a result, there will be extensions of time required which will further result
in fine, increased cost due to inflation, termination of contract, court cases etc. or combinations of
above stated factors, resulting in delay damages.
 Construction delays are often result of a mismanaged event/s and can be seen as a risk for the projects,
which if identified, analyzed and managed in a systematic process at inception, could be managed,
minimized, shared, mitigated or accepted to give some good results and minimize chances of further
delay.
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 Delay in construction project has a negative effect on clients, contractors, and consultants in terms of
growth in adversarial relationships, mistrust, litigation, arbitration, and cash-flow problems. A
construction project may be regarded as a successful endeavor until it satisfies the cost, time, and
quality limitations applied to it.
Types of Delays in Construction Projects
Types
of
Delays
Critical & Non Critical Delays
Excusable & Non-Excusable Delays
Concurrent Delays
Expansable & Non-Expansable Delays
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
4
Types of Delays in Construction Projects
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 A delay that is responsible for extending project duration is a critical delay.
1. Critical & Non-Critical Delay
 Few results are mentioned below:
• Extended Field Overhead.
• Unabsorbed home office overhead.
• Liquidated Damage.
• Idle labor & equipment cost.
• Labor & Material Cost Escalation and many more.
 A delay that is not the cause of extended project duration is a non-critical delay;
however, it will have an effect in terms of activities getting completed late than
scheduled completion.
Types of Delays in Construction Projects
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 A delay where the contractor is entitled for extension of time or compensation or
both, under the terms & conditions of contract is excusable delay.
2. Excusable & Non-Excusable Delay
 In this case, contractor does not have any control on the activity getting delayed.
The causes may be:
• Force Measure Clause
• Natural Calamities
• Political/Social Unrest
• Terrorist Attacks
• Delay from Client (Approvals, Decisions, etc.), etc.
Types of Delays in Construction Projects
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 A delay where the contractor is fully responsible for the activities getting delayed
and resulted in extending project duration (responsible for critical delays)
are non-excusable delays.
2. Excusable & Non-Excusable Delay
 In this case, the contractor has to bear the risk of cost consequences including the
liability to pay damages for itself but possibly for the other parties as well. The
causes may be:
• Delayed Mobilization
• Delayed Procurement
• Delayed submission of important documents
• Planning & Scheduling
• Critical events that were not highlighted to client on right time, etc.
Types of Delays in Construction Projects
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 A situation where more than one delay event occurs at the same time affecting
multiple activities simultaneously/independently affecting the completion
is concurrent delay.
3. Concurrent Delays
 However, not all those events enable the contractor to be entitled for extension of
time & cost claim. Importantly, it is the causes of delay rather the delay
themselves, that must overlap.
Types of Delays in Construction Projects
Source: https://theconstructor.org/construction/delays-construction-projects/13465/
 Scenario where contractor is liable for Time Extension & Cost compensation
is compensable delays.
4. Compensable & Non-Compensable Delay
 All compensable delays fall under excusable delays.
 If the contractor is solely at fault for a delay event, it is termed as non-
compensable delay.
 Non-compensable may fall under critical, non-critical, excusable or non-
excusable; depending upon the situation it has created and conditions of contract.
Effects of Construction Delays
Source: https://www.irjet.net/archives/V3/i10/IRJET-V3I10108.pdf
Effects
Dispute
Cost
Overrun
Time
Overrun
Negotiati
on
Total
Desertion
Litigatio
n
Abandon
ment
Lawsuit
Location of Al Kut Olympic Stadium
Source:https://www.google.com/maps/place/Al+Kut+Olympic+Stadium/@32.4990045,45.8279046,12z/data=!4m5!3m4!1s0x3fe3bf51d7aa06ff:0xbef5b1f15e30c39b!8m2!3d32.5022143
!4d45.8337427?hl=en
Scope of Study
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 This study focuses on a literature review of previous studies of research,
published and unpublished papers, books dealing with the subject of delay
analysis in construction projects or subjects close to this title as well as field data
include reports issued by the competent authorities for projects in Iraq, in
particular the project of demolition and rebuilding of Al kut Olympic Stadium
with a capacity of 20,000 spectators.
 The study identified the main reasons for the delay of this project as well as the
effect of this delay and methods to minimize the impact of this delay and avoid
delays for similar projects in the future.
Objectives of Study
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 The major aim of this research is to identifying the major issues of delay, effect of delay
and method of minimizing delay in project of demolition old stadium of Al kut and
constructing new stadium in Waist state in Iraq and to giving responsibility amongst the
project groups for delays.
 Objectives have been identified as following:
• To find the general issues of construction delays according to literature survey.
• To use the MSP in planning and scheduling activates in Al kut stadium project to
minimize delay.
• To observe the main issue of construction delay in construction of Al kut stadium
project in Waist state in Iraq.
• To allocate responsibility amongst the projects parties of construction delay.
• To identify the methods of minimizing constructions delay in the Al kut stadium
project.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
Collection
of Project
Data
Preparation
of Schedule
using MSP
Software
Assigning of
Resources
Setting of
Baseline
Tracking a
Schedule
using MS
Project
Comparing
Schedules
Identifying
Variances
Identifying
Revisions
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 In the Al kut stadium project, initially all the relevant data has been collected like stadium Drawings,
Specifications, types of resources, quantities, planned schedule, photographs, etc.
 Al kut project is demolition and removal and the establishment of Al kut Olympic stadium with a
capacity of 20,000 spectators on a total area of 73000 square meters.
1. Collection of Project Data
2. Preparation of Schedule using MSP Software
 Before preparing the schedule initially different activities are identified with the help of data given by
the organization and resources required for the project by rate analysis.
 It has been found that in all there are around 250 activities required for this sport facilities. With the help
of relevant data from the ministry of youth and sport of Iraq for the project.
 Using MSP i.e. by linking all the activities and after linking all the activities, with the help of different
linking options, total duration of the project was found i.e. 750 days.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 Assigning of resources is done so that actual cost of project can be known.
 After this assignment, project feasibility can be known that if the project is actually within budget
and time.
3. Assigning of Resources
4. Setting of Baseline
 As the baseline is set for the project, progress for the project could be summarized by comparing
it with actual schedule i.e. planned schedule is compared with actual schedule with the help of
milestone and by setting baseline to the project.
 Baseline is to show that how that project is differing from its planned to actual scenario, and
hence one can get their project scenario, if the project is achieving its milestone or not.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 Tracking progress is all about data gathering: tasks completed, hours worked, and costs incurred.
 So with the help of tracking, project status can be found out as now baseline is set for the project.
Tracking of the project can be done in different ways:
5. Tracking a Schedule with MS Project
• Percentage of work complete (% Work Complete).
• Actual duration.
• Remaining duration.
• Actual start.
• Actual finish.
• Actual work.
• Remaining work.
• Actual work by time period.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 It is realized that the schedule argument as well as the planned progress and changes to the
difference between real progress will be important.
 Planned change amendment arguments and schedule durations are to schedule and their
status date back to status date to the right will be calculated to take place in the future.
6. Comparing Schedules
7. Identifying Variances
 To identify variances in performance, Start Variance and Finish Variance columns can be
used.
 In addition, trace displays and custom styles in a single view baseline information to
schedule updates can make the strip.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 MSP has a Compare Project Versions utility to review differences between two similar MSP
schedules. Compare Project Versions utility only compares tasks and resources and resource
assignment does not compare.
 Implementation of spectators filled the two types:
8. Identifying Revisions
• Spectators terraced capacity of 13200 Spectators.
• Cabin Terraced capacity of 6785 spectators.
 Supplying and erection transformer of electricity with capacity of 1250 kva and electrical
generator with capacity of 1259 kva build up on two services buildings:
• Outside of field boundaries contain station for pumping and storage for drink water and also
for purpose of irrigation and firefighting, this building contain security room and reception.
• The second building contain Locker rooms, Warm-up halls, sports hall and its parts, Mosque,
sound control rooms, press rooms, kitchen, Cafeteria, etc.
Research Methodology
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 Supplying and installation of Electronic screen (6*4 square meters) 2 screens.
 Executing parking for 2 and 4 wheels (5 parks).
8. Identifying Revisions
 Supplying and installation of seats fixing in the spectator’s positions (750 seats) in VIP
area and VVIP (65) also fixed seats (600) and at least the ordinary seats (13200 seats).
 Supplying and installation lighting columns in different types.
 Construct entrance gates (2) to enter the field and another main gates (2) and a grid of
roads inside the boundaries of the stadium.
 Constructing pipeline grid for different purpose.
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
1. Additional Days
135
days
10
days
120
days
265
days
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
2. Additional Works
 It has been added to work under an order parts no.1 with amount 1,668,025,000 in
1232012.
 It has been added to work under an order parts no.2 with amount 18,378,729,000 IQD in
162014.
 The condition of the construction until 15/3/2015 is according to the plan submitted by the
contractor who was executing the project and ratified by the ministry of youth and sports
(client) that the work should be completed till 22/11/2013 but the actual percent of done
work is 63.5% in 15/3/2015 so the deviation in the plan is 36.5% until the 15/3/2015.
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
3. Problems & Obstacles
 The following are the most important problems that have caused delays:
1. Change the design of the foundation from raft foundation to deep foundation (piles).
Based on soil investigations report that stipulated the actual bearing capacity of the soil
is not (10 kg/cm2) but it is (4.5 kg/cm2) that would be taken in the primary design.
2. The absence of the design because of the end of the decade, including the Ministry of
Youth and Sports, which has affected negatively on the technical solution to the
problems facing the design and work through the stages of implementation.
3. Not resolve the issue of the iron structure that holds terrace the stadium cover and make
change in the initial design and make new design has more strength than old one.
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
A weakness in the integration of the integrated design vision of the project Which impact
on the integration of technical and architectural specifications for certain paragraphs of
the project An example of such an agreement with the province of Waist to connect the
discharge of heavy water network with the carrier to be implemented by the province of
Waist line and passing next to the project site as well as with rain water draining note
that the stadium project was built on the basis of the existence of drainage networks
design but in fact the lack of such networks near the stadium addition to the error by
adopting the design discharge of sewage and rain water draining one network as opposed
to instructions of the Ministry of Health, Environment and Water Resources.
Canceled some of main activates to decrease the cost of project.
4.
5.
3. Problems & Obstacles
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
4. Task Cost Overview
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
5. Resource Work Availability Report
Result Analysis
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
6. Resource Remaining Work Report
Summary
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
 The aim of this analysis was to analyze the factors that influence the success of
construction coming up with of Al kut Olympic sports stadium and delay analysis case
study.
 Before you install with Preconstruction, well planning and procarance of special
constructions immediately before the commencement of part to progress with coming to be
very useful.
 SRM helped come up with throughout the preconstruction that major problem
preconstruction stage a project team was formed and the project completion was
maintained the same team.
 Engineers were trained to become the Manager and who's coming with that it is supported
by the entire project team is able to achieve success can be a way to educate.
Source: https://www.ijsr.net/archive/v5i6/6061607.pdf
Thank You for your
Attention!!

More Related Content

What's hot

Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery MethodPMA Consultants
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution techniqueSaad Ullah
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 

What's hot (20)

Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
claims management framework
 claims management framework claims management framework
claims management framework
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution technique
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 

Similar to A case study of Delay Analysis of construction project: Al Kut Olympic Stadium || Construction Delays || Types of Construction Delays || Effects of Construction Delays

Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...eSAT Publishing House
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationCamella Taylor
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 

Similar to A case study of Delay Analysis of construction project: Al Kut Olympic Stadium || Construction Delays || Types of Construction Delays || Effects of Construction Delays (20)

Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
I0313048051
I0313048051I0313048051
I0313048051
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Project Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And ImplementationProject Management, Perspective, Planning And Implementation
Project Management, Perspective, Planning And Implementation
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 

Recently uploaded

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

A case study of Delay Analysis of construction project: Al Kut Olympic Stadium || Construction Delays || Types of Construction Delays || Effects of Construction Delays

  • 1. A Case Study of Delay Analysis in Construction Project : Al kut Olympic Stadium Gaurav Verma Final Year Civil Engineering, Dayalbagh Educational Institute, Dayalbagh, Agra May, 2021 https://www.linkedin.com/in/ gaurav-verma-5663b0174 gaurav170350@dei.ac.in
  • 2. Outlines  Construction Delays.  Types of Delays in Construction Projects.  Effects of Construction Delays.  Location of Al Kut Olympic Stadium.  Scope of Study.  Objectives of study.  Research Methodology.  Result Analysis.  Summary.
  • 3. Construction Delays  Construction delays are considered as time lag in completion of activities from its specified time as per contract or can be defined as late completion or late start of activities to the baseline schedule, directly affecting specified cost. As a result, there will be extensions of time required which will further result in fine, increased cost due to inflation, termination of contract, court cases etc. or combinations of above stated factors, resulting in delay damages.  Construction delays are often result of a mismanaged event/s and can be seen as a risk for the projects, which if identified, analyzed and managed in a systematic process at inception, could be managed, minimized, shared, mitigated or accepted to give some good results and minimize chances of further delay. Source: https://theconstructor.org/construction/delays-construction-projects/13465/  Delay in construction project has a negative effect on clients, contractors, and consultants in terms of growth in adversarial relationships, mistrust, litigation, arbitration, and cash-flow problems. A construction project may be regarded as a successful endeavor until it satisfies the cost, time, and quality limitations applied to it.
  • 4. Types of Delays in Construction Projects Types of Delays Critical & Non Critical Delays Excusable & Non-Excusable Delays Concurrent Delays Expansable & Non-Expansable Delays Source: https://theconstructor.org/construction/delays-construction-projects/13465/ 4
  • 5. Types of Delays in Construction Projects Source: https://theconstructor.org/construction/delays-construction-projects/13465/  A delay that is responsible for extending project duration is a critical delay. 1. Critical & Non-Critical Delay  Few results are mentioned below: • Extended Field Overhead. • Unabsorbed home office overhead. • Liquidated Damage. • Idle labor & equipment cost. • Labor & Material Cost Escalation and many more.  A delay that is not the cause of extended project duration is a non-critical delay; however, it will have an effect in terms of activities getting completed late than scheduled completion.
  • 6. Types of Delays in Construction Projects Source: https://theconstructor.org/construction/delays-construction-projects/13465/  A delay where the contractor is entitled for extension of time or compensation or both, under the terms & conditions of contract is excusable delay. 2. Excusable & Non-Excusable Delay  In this case, contractor does not have any control on the activity getting delayed. The causes may be: • Force Measure Clause • Natural Calamities • Political/Social Unrest • Terrorist Attacks • Delay from Client (Approvals, Decisions, etc.), etc.
  • 7. Types of Delays in Construction Projects Source: https://theconstructor.org/construction/delays-construction-projects/13465/  A delay where the contractor is fully responsible for the activities getting delayed and resulted in extending project duration (responsible for critical delays) are non-excusable delays. 2. Excusable & Non-Excusable Delay  In this case, the contractor has to bear the risk of cost consequences including the liability to pay damages for itself but possibly for the other parties as well. The causes may be: • Delayed Mobilization • Delayed Procurement • Delayed submission of important documents • Planning & Scheduling • Critical events that were not highlighted to client on right time, etc.
  • 8. Types of Delays in Construction Projects Source: https://theconstructor.org/construction/delays-construction-projects/13465/  A situation where more than one delay event occurs at the same time affecting multiple activities simultaneously/independently affecting the completion is concurrent delay. 3. Concurrent Delays  However, not all those events enable the contractor to be entitled for extension of time & cost claim. Importantly, it is the causes of delay rather the delay themselves, that must overlap.
  • 9. Types of Delays in Construction Projects Source: https://theconstructor.org/construction/delays-construction-projects/13465/  Scenario where contractor is liable for Time Extension & Cost compensation is compensable delays. 4. Compensable & Non-Compensable Delay  All compensable delays fall under excusable delays.  If the contractor is solely at fault for a delay event, it is termed as non- compensable delay.  Non-compensable may fall under critical, non-critical, excusable or non- excusable; depending upon the situation it has created and conditions of contract.
  • 10. Effects of Construction Delays Source: https://www.irjet.net/archives/V3/i10/IRJET-V3I10108.pdf Effects Dispute Cost Overrun Time Overrun Negotiati on Total Desertion Litigatio n Abandon ment Lawsuit
  • 11. Location of Al Kut Olympic Stadium Source:https://www.google.com/maps/place/Al+Kut+Olympic+Stadium/@32.4990045,45.8279046,12z/data=!4m5!3m4!1s0x3fe3bf51d7aa06ff:0xbef5b1f15e30c39b!8m2!3d32.5022143 !4d45.8337427?hl=en
  • 12. Scope of Study Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  This study focuses on a literature review of previous studies of research, published and unpublished papers, books dealing with the subject of delay analysis in construction projects or subjects close to this title as well as field data include reports issued by the competent authorities for projects in Iraq, in particular the project of demolition and rebuilding of Al kut Olympic Stadium with a capacity of 20,000 spectators.  The study identified the main reasons for the delay of this project as well as the effect of this delay and methods to minimize the impact of this delay and avoid delays for similar projects in the future.
  • 13. Objectives of Study Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  The major aim of this research is to identifying the major issues of delay, effect of delay and method of minimizing delay in project of demolition old stadium of Al kut and constructing new stadium in Waist state in Iraq and to giving responsibility amongst the project groups for delays.  Objectives have been identified as following: • To find the general issues of construction delays according to literature survey. • To use the MSP in planning and scheduling activates in Al kut stadium project to minimize delay. • To observe the main issue of construction delay in construction of Al kut stadium project in Waist state in Iraq. • To allocate responsibility amongst the projects parties of construction delay. • To identify the methods of minimizing constructions delay in the Al kut stadium project.
  • 14. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf Collection of Project Data Preparation of Schedule using MSP Software Assigning of Resources Setting of Baseline Tracking a Schedule using MS Project Comparing Schedules Identifying Variances Identifying Revisions
  • 15. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  In the Al kut stadium project, initially all the relevant data has been collected like stadium Drawings, Specifications, types of resources, quantities, planned schedule, photographs, etc.  Al kut project is demolition and removal and the establishment of Al kut Olympic stadium with a capacity of 20,000 spectators on a total area of 73000 square meters. 1. Collection of Project Data 2. Preparation of Schedule using MSP Software  Before preparing the schedule initially different activities are identified with the help of data given by the organization and resources required for the project by rate analysis.  It has been found that in all there are around 250 activities required for this sport facilities. With the help of relevant data from the ministry of youth and sport of Iraq for the project.  Using MSP i.e. by linking all the activities and after linking all the activities, with the help of different linking options, total duration of the project was found i.e. 750 days.
  • 16. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  Assigning of resources is done so that actual cost of project can be known.  After this assignment, project feasibility can be known that if the project is actually within budget and time. 3. Assigning of Resources 4. Setting of Baseline  As the baseline is set for the project, progress for the project could be summarized by comparing it with actual schedule i.e. planned schedule is compared with actual schedule with the help of milestone and by setting baseline to the project.  Baseline is to show that how that project is differing from its planned to actual scenario, and hence one can get their project scenario, if the project is achieving its milestone or not.
  • 17. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  Tracking progress is all about data gathering: tasks completed, hours worked, and costs incurred.  So with the help of tracking, project status can be found out as now baseline is set for the project. Tracking of the project can be done in different ways: 5. Tracking a Schedule with MS Project • Percentage of work complete (% Work Complete). • Actual duration. • Remaining duration. • Actual start. • Actual finish. • Actual work. • Remaining work. • Actual work by time period.
  • 18. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  It is realized that the schedule argument as well as the planned progress and changes to the difference between real progress will be important.  Planned change amendment arguments and schedule durations are to schedule and their status date back to status date to the right will be calculated to take place in the future. 6. Comparing Schedules 7. Identifying Variances  To identify variances in performance, Start Variance and Finish Variance columns can be used.  In addition, trace displays and custom styles in a single view baseline information to schedule updates can make the strip.
  • 19. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  MSP has a Compare Project Versions utility to review differences between two similar MSP schedules. Compare Project Versions utility only compares tasks and resources and resource assignment does not compare.  Implementation of spectators filled the two types: 8. Identifying Revisions • Spectators terraced capacity of 13200 Spectators. • Cabin Terraced capacity of 6785 spectators.  Supplying and erection transformer of electricity with capacity of 1250 kva and electrical generator with capacity of 1259 kva build up on two services buildings: • Outside of field boundaries contain station for pumping and storage for drink water and also for purpose of irrigation and firefighting, this building contain security room and reception. • The second building contain Locker rooms, Warm-up halls, sports hall and its parts, Mosque, sound control rooms, press rooms, kitchen, Cafeteria, etc.
  • 20. Research Methodology Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  Supplying and installation of Electronic screen (6*4 square meters) 2 screens.  Executing parking for 2 and 4 wheels (5 parks). 8. Identifying Revisions  Supplying and installation of seats fixing in the spectator’s positions (750 seats) in VIP area and VVIP (65) also fixed seats (600) and at least the ordinary seats (13200 seats).  Supplying and installation lighting columns in different types.  Construct entrance gates (2) to enter the field and another main gates (2) and a grid of roads inside the boundaries of the stadium.  Constructing pipeline grid for different purpose.
  • 21. Result Analysis Source: https://www.ijsr.net/archive/v5i6/6061607.pdf 1. Additional Days 135 days 10 days 120 days 265 days
  • 22. Result Analysis Source: https://www.ijsr.net/archive/v5i6/6061607.pdf 2. Additional Works  It has been added to work under an order parts no.1 with amount 1,668,025,000 in 1232012.  It has been added to work under an order parts no.2 with amount 18,378,729,000 IQD in 162014.  The condition of the construction until 15/3/2015 is according to the plan submitted by the contractor who was executing the project and ratified by the ministry of youth and sports (client) that the work should be completed till 22/11/2013 but the actual percent of done work is 63.5% in 15/3/2015 so the deviation in the plan is 36.5% until the 15/3/2015.
  • 23. Result Analysis Source: https://www.ijsr.net/archive/v5i6/6061607.pdf 3. Problems & Obstacles  The following are the most important problems that have caused delays: 1. Change the design of the foundation from raft foundation to deep foundation (piles). Based on soil investigations report that stipulated the actual bearing capacity of the soil is not (10 kg/cm2) but it is (4.5 kg/cm2) that would be taken in the primary design. 2. The absence of the design because of the end of the decade, including the Ministry of Youth and Sports, which has affected negatively on the technical solution to the problems facing the design and work through the stages of implementation. 3. Not resolve the issue of the iron structure that holds terrace the stadium cover and make change in the initial design and make new design has more strength than old one.
  • 24. Result Analysis Source: https://www.ijsr.net/archive/v5i6/6061607.pdf A weakness in the integration of the integrated design vision of the project Which impact on the integration of technical and architectural specifications for certain paragraphs of the project An example of such an agreement with the province of Waist to connect the discharge of heavy water network with the carrier to be implemented by the province of Waist line and passing next to the project site as well as with rain water draining note that the stadium project was built on the basis of the existence of drainage networks design but in fact the lack of such networks near the stadium addition to the error by adopting the design discharge of sewage and rain water draining one network as opposed to instructions of the Ministry of Health, Environment and Water Resources. Canceled some of main activates to decrease the cost of project. 4. 5. 3. Problems & Obstacles
  • 28. Summary Source: https://www.ijsr.net/archive/v5i6/6061607.pdf  The aim of this analysis was to analyze the factors that influence the success of construction coming up with of Al kut Olympic sports stadium and delay analysis case study.  Before you install with Preconstruction, well planning and procarance of special constructions immediately before the commencement of part to progress with coming to be very useful.  SRM helped come up with throughout the preconstruction that major problem preconstruction stage a project team was formed and the project completion was maintained the same team.  Engineers were trained to become the Manager and who's coming with that it is supported by the entire project team is able to achieve success can be a way to educate.