The document provides details on the construction of the Metro Route 2020 project in Dubai, which has a budget of $2.9 billion. It includes key project facts such as a route length of 10.5km for viaducts and 4km for tunnels. There will be 7 underground and elevated stations serving a capacity of 46,000 passengers per hour. Construction will involve tunnelling, precast segment erection, bridge and viaduct construction using methods such as diaphragm walls, secant piles and slipforming. The project execution plan outlines the construction process and measures to ensure safety, quality and environmental protection.
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Route 2020 Metro Dubai Construction Details
1. Metro Route 2020 Dubai – Construction $2.9bn
Included
Route, Programme Graphic
Tunnelling, Stations & Viaduct
Details
Lengths
Viaduct 10.5 km
Tunnel 4 km
Stations
Underground 2 Nr.
Elevated 5 Nr.
Capacity 46,000 passengers per hour.
Maximum wait time will be 100 seconds and there
will be 15 trains
Tunnels & Underground Stations
Viaduct
3D image to show Sequence, Method & Plant.
David H Moloney
21st July 2016
ⓒ David H Moloney
Project Execution Plan. Details how the Metro will be
constructed, and how the progress, safety and quality will be
monitored and controlled. Also the measures to ensure that
the site is environmentally friendly
6. Programme Time Chainage
The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
9. Cost Comparisons of various Metro Projects
Dubai Route
2020
UAE
(To Start)
Red Line North
Doha
Qatar
(In Progress)
Red Line South
Doha
Qatar
( In Progress)
Metro North
Dublin
(Proposed)
Dart
Underground
Dublin
(Proposed)
Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million
Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km
Overall Length 15.5 km 13 km 14m 18 km 5 km
Tunnel 4 km
Single Tunnel
11.6 km
Twin Tunnels
14 km
Twin Tunnels
7.5 km
Twin Tunnels
5 km
Twin Tunnel
Cut & Cover 0 2.7 km 0
Elevated 10.5 km 2.2 km 0
Road Level 0 5.5 0
Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr.
Capacity 13,000 Passengers
per hour
19,800 Passengers per
hour
?
ⓒ David H Moloney
10. Advantages of Light Rail Systems Benefits of Metro to commuters
1. Time saving for commuters 4. Reduction in accident
2. Reliable and safe journey 5. Reduced fuel consumption
3. Reduction in atmospheric pollution 6. Reduced traffic congestion
13. Quarry & Aggregate Production
ⓒ David H Moloney
Brief Description
Rock is blasted free from the quarry
face and fragmented so it will fit into
the primary crusher. Any oversized
rock is broken with a excavator and
hydraulic Rockbreaker.
At the Crushing and screening yard
the fragmented rock is crushed and
screened into various size ranges.
14. Concrete Batching Plant David H Moloney
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
The mixing is computer controlled and has
a dynamic screen display, showing the
process. Material storage capacity to
match two days concrete production
15. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
19. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
28. Existing Underground Utilities
ⓒ David H Moloney
Earthworks
Brief Description
Before digging
establish the location
and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
39. Diaphragm Wall Construction - Sequence, Plant & Methods
Diaphragm Wall Grab
ⓒ David H Moloney
Brief Description
Shown is the Sequence,
methods and plant to construct a
diaphragm slurry underground
wall.
45. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
47. Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
BIM 3D Model Shutter Fibreglass
48. Concrete Full Scale Trial Castings of Bridge Deck
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
Fresh Concrete Properties Tests
Air Content, Consistence, Density, Initial and Final Setting Time, Temperature
and Bleeding
Chloride Ion Content
Hardening and Hardened Concrete Properties Tests:
Density and Compressive Strength for 1, 3, 7, 14 and 28 Days
Concrete Core Compressive Strength
Tensile Splitting Strength
Modulus of Elasticity
Heat Development
Chloride Migration Coefficient (28 Days)
Reinforcement Cover Measurement Survey
49. Trial for Waterproofing to Bridge Deck
ⓒ David H Moloney
Brief Description
. The trial for the deck waterproofing
shall demonstrate/document that all
requirements to the waterproofing and
the execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
52. Tunnel Wall Segments Casting
Clean Mould
Lift Precast Segment out of mould
after 18 hours.
Reinforcement
fabricate
Reinforcement
into Mould
Concreting
Segment Storage
Cycle Time
24 hrs
ⓒ David H Moloney
58. Viaduct Segments Casting David H Moloney
Casting Method
The concrete segments are manufactured
using the short-line, match-casting method.
Match-casting is when sequential segments are
poured against the previous cast segment, this
ensures that the segments will fit perfectly on
site.
ⓒ David H Moloney
63. Bridge Construction Sequence
David H Moloney
Piling Surcharge Abutments
Remove Surcharge Abutments
Deck centre
Post-tensioning Fascia & Waterproof deck Complete Bridge
PiersOverview
Deck Ends
Images with Schematic 3D view, Photos & Timeline
ⓒ David H Moloney
70. Cut & Cover Tunnel Construction
Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.
To prevent the faces of the excavation from collapsing, different measures are used –
batter the faces, diaphragm walls, secant piles or a combination of soil nailing and
shotcreting.
71. Ramp Construction
Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.
To prevent the faces of the excavation from collapsing, different measures are used – batter
faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.
ⓒ David H Moloney
88. Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
89. Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Brief Description
Shown is the Sequence,
methods and plant to construct a
secant pile underground wall.
99. Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
100. Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
106. Tunnel Boring Machine (TBM)
Cutting Head rotates to Dig
Excavated material removed
by conveyor belt
Lifting muck to surface
with skip
Placing Concrete
Segments
107. Tunnel Boring Machine (TBM)
Cutting Head rotates
7 nr. Precast segments
form rings that line the
tunnel Excavated material removed
by conveyor belt
ⓒ David H Moloney
111. Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
112. Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
114. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.