DUBAI- DIAC rules for
- REQUEST FOR ARBITRATION
GESTIÓN/ANÁLISIS DE CONTRATOS EPC/ GESTIÓN DE RECLAMACIONES-VARIACIONES/ARBITRAJE
INTERNACIONAL
CURSO Para SIEMENS-GAMESA Project Manager
Lecturer: César del Riego y de Fuentes- Madrid - Spain
1
DUBAI-DIAC REQUEST
FOR ARBITRATION
1 Introduction
2 Parties
3 Agreement to Arbitrate
4 Description of the Dispute
5 Relief Sought
6 Appointment of the Arbitrator
7 The Statement of Claim
8 Place of Arbitration
9 Language of Arbitration
10 Applicable Rules of Law
11 Reservation of Rights
12 Submission of this Request for Arbitration
2
DUBAI RFA- PORTADA
• CLAIMANT
• RESPONDANT
• REPRESENTATION
• DATE
MR. CLAIMANT SMITH
Represented by
Mr. César del Riego y de Fuentes- Attorney At Law -Madrid Bar Association
C/Avenida de Rotonda, nº4
Madrid (Madrid) 28028 España
Tel: +34 99992222299999
Fax: +34 99990000007777
Claimant
versus
MR. DEFENDANT JONES
Round St.
Dubai U.A.E.
Respondent
_______________________________________________________
REQUEST FOR ARBITRATION
_________________________________________________________
November 26, 2020
3
• Article 4.1 of the DIAC Rules: RFA
• Article 4.1.(a) of DIAC Rules: RFA hereby requests from the
Centre that the dispute be referred to arbitration under DIAC
Rules.
• Article 4.1.(c) of the DIAC Rules: Arbitration Agreement-
invoked by the Claimant, together with a copy of the
contractual documentation.
• Articles 4.3 and 4.4 of the DIAC Rules: Submit 5 copies and
a 5000 UAE security bond.
• Article 23 of the DIAC Rules: CLAIM: The full documents
supporting the Claimant’s claim shall be provided with the
Statement of Claim
• Article 23 of the DIAC Rules: Claim submitted in 30 days.
• Article 8.2 of DIAC Rules: Appointment of the arbitrator.
4
1 Introduction
• 1. This Request for Arbitration is made
under Article 4.1 of the DIAC Rules by MR.
CLAIMANT SMITH , in connection with
disputes arising out of the Construction
Contract for Torero Power Plant dated 15
June 2018, signed between MR. CLAIMANT
SMITH and MR. DEFENDANT JONES, (the
“Contract”).
• 2. MR. CLAIMANT SMITH hereby requests
from the Centre that the dispute be referred
to arbitration under DIAC Rules according to
Article 4.1.(a) of DIAC Rules.
5
2 Parties
• 3. Claimant: The Claimant, MR. CLAIMANT
SMITH , is a company incorporated under
the laws of Dubai, United Arab Emirates.
• 4. MR. CLAIMANT SMITH was the
Contractor under the Contract (hereinafter
referred to as the Contractor or the
Claimant).
• 5. The address of the Claimant is:
• Rapsody St.
• Dubai, United Arab Emirates
• Phone: +971 55555577777
• Fax: +971 788888766666
6
2 Parties
• 6. The Representative of the Claimant is:
• Mr. César del Riego y de Fuentes-Madrid Bar Accredited
• C/Avenida de Rotonda, nº4
• Madrid (Madrid) 28028 España
• Tel: +34 99992222299999
• Fax: +34 99990000007777
• E-mail: cesar.riego@icam.es
• 7. The Claimant requests all communications to be
sent to the Claimant’s representative.
• 8. Respondent: The Respondent is MR. DEFENDANT
JONES located in Dubai, United Arab Emirates.
7
2 Parties
• 9. MR. DEFENDANT JONES was the
Employer under the Contract (hereinafter
referred to as the Employer or the
Respondent).
• 10. The address of the Respondent is:
• Rapsody St.
• Dubai, United Arab Emirates
• Phone: +971 444477777
• Fax: +971 4449999999
8
3 Agreement
to Arbitrate
• 13. Sub-Clause xxxxx of the General Conditions of
the Contract (hereinafter the GCC), amended by the
Conditions of Particular Applications (CPA) refers to
Arbitration for the settlement of disputes:
• Sub-Clause xxxx Conditions of Particular Application
• Any dispute connected with the formation,
performance, interpretation, nullification,
termination or invalidation of this Contract or arising
there from or related thereto in any manner
whatsoever which:
• (a) the decision, if any, of the Employer
Representative has not become final and binding
pursuant to Sub Clause xxxx and
• (b) amicable settlement has not been reached
within the period stated in Sub Clause xxxxx
9
3 Agreement
to Arbitrate
• shall be referred to arbitration in Dubai UAE, in accordance
with the provisions set forth in the rules of Arbitration of the
Dubai International Arbitration Centre (DIAC).
• Neither party shall be limited in the proceedings before the
arbitrator(s) to the evidence or arguments put before the
Employer Representative for the purpose of obtaining his said
decision pursuant to Sub-Clause xxxxx. No such decision shall
disqualify the Employer Representative from being called as
witness and giving evidence before the arbitrator(s) on any
matter whatsoever relevant to the dispute.
• Arbitration may be commenced prior to or after the
completion of the Works, provided that the obligations of the
Employer, the Employer Representative and the Contractor
shall not be altered by reason of the arbitration being
conducted during the progress of the Works.
10
3 Agreement
to Arbitrate
• 18. Article 4.1.(c) of the DIAC Rules. copy of
the Arbitration Agreement invoked by the
Claimant, together with a copy of the
contractual documentation in which the
Arbitration Agreement is contained or in
respect of which the arbitration arises is
attached as C1 to this Request for
Arbitration in accordance with Article 4.1.(c)
of the DIAC Rules.
11
4 Article
4.1.(c) of the
DIAC Rules:
Description
of the
Dispute
• 19. The following is “a brief description of
the nature and circumstances of the dispute
giving rise to the claim” in accordance with
Article 4.1(d) of the DIAC Rules. The
Claimant reserves the right generally to
amend and/or supplement the facts, the
claims, and legal and contractual grounds.
The full documents supporting the
Claimant’s claim shall be provided with the
Statement of Claim under Article 23 of the
DIAC Rules and further submissions during
the arbitration proceedings.
12
5 Relief
Sought
• 20. In consideration of all of the above, the Claimant
respectfully requests the Arbitral Tribunal to:
• 1. declare that the termination of the Contract Torero
CCPP, dated 15 June 2018 by the Claimant was valid and
justified;
• 2. declare that the Respondent's purported
termination of the Contract Torero Power Plant, dated 15
June 2018 was invalid, unjustified and or unlawful;
• 3. declare that the Claimant is entitled to an
Extension of Time for Completion to the Termination of
the Works being 26 September 2018;
• 4. order that the Respondent return the Performance
Security Bond to the Claimant within 10 days following
the receipt of the Award;
13
5 Relief
Sought
• 5. order that the Respondent pay the
Claimant AED XXXXXXX for the sums of;
• a- Contract Works and General Requirements
• b- Materials on Site
• c- Variations and Additional Works
• d- Loss of Overheads and Profit
• e- Prolongation Claimed Costs
• f- Interest Charges on Delayed Payment up to
31 July 2011
• g- Damages due to the Advance Payment
Guarantee being called in
14
5 Relief
Sought
• h- Subcontractor’s Claims
• i- Non productive Manpower Claim
• 6. order that the Respondent pay the Claimant
interest on all amounts it is ordered to pay pursuant
to these proceedings, from the date of the event
giving rise to the claim;
• 7. order that the Respondent pay the Claimant all
costs and expenses (including, but not limited to,
costs payable to DIAC, legal fees and expenses and
fees and expenses of experts, consultants and
others) incurred by the Claimant in connection with
the preparation for and conduct of this arbitration;
15
5 Relief
Sought
• 8. order that the Respondent pay the Claimant
post-award interest on all amounts it is ordered to
pay pursuant to these proceedings, from the date of
the Award until receipt of payment of such amount
by the Claimant;
• 9. order that the Respondent pay the Claimant
such other relief as the Arbitral Tribunal deems
appropriate under the circumstances;
• 11. For the purpose of computation of the
arbitration fees, and without prejudice to its rights
in law or equity, the Claimant estimates its total
claim to amount to AED XXXXXX and in a separate
Statement of Claim, will detail the heads of claim
outlined above and will denominate each in figures,
supported by evidence.
16
6 Article
8.2 of DIAC
Rules
:Appointment
of the
Arbitrator
• 12. There is no determination on the
number of the arbitrators in the Arbitration
Agreements between the Parties.
• 13. Article 8.2 of DIAC Rules provides that:
• 8.2 Where the parties have not agreed on
the number of arbitrators, the Tribunal shall
consist of a sole arbitrator, except where the
Centre in its discretion determines that, in
view of all the circumstances of the dispute,
a Tribunal composed of three members is
appropriate.
•
17
6 Article
8.2 of DIAC
Rules
:Appointment
of the
Arbitrator
1. In view of all the circumstances, the amount
and the complicated nature of the dispute
explained above, the Claimant requests
from the Centre that a tribunal of three
members is to be composed.
2. The Claimant hereby nominates Mr
Guillaume Chavaliere, as party arbitrator for
the Claimant, who is located at:
• 5 Rue St. Honorée
• Montreal
• Quebecq- Canada.
18
7 Article
23 of the
DIAC Rules:
The
Statement of
Claim
• 16. The Statement of Claim referred will be
submitted in accordance with Article 23 of
the DIAC Rules, within 30 days of receipt of
notification from the Centre of the
establishment of the Tribunal or such later
time limit as the Tribunal may allow.
19
(B) ASPECTOS
REGULADOS POR EL
CONVENIO ARBITRAL:
20
8 Regulado
por Cláusula
Arbitral:
Place of
Arbitration
• 17. Clause XXX of the General Conditions of
the Contract provides for the place of the
arbitration as Dubai:
• Sub-Clause XXXX Law and Procedure:
• The law governing the procedure and
administration of any arbitration instituted
pursuant to Clause XXX shall be the law of
the United Arab Emirates and of Dubai. The
language of arbitration shall be English and
the place of arbitration shall be Dubai.
21
9 Regulado
por Cláusula
Arbitral:
Language of
Arbitration
• 18. Clause XXXX of the GCC provides for the
language of the arbitration. According to
Clause XXXX the language of the Arbitration
shall be English (see above Section 8).
22
10 Regulado
por Cláusula
Arbitral:
Applicable
Rules of Law
• 19. Clause XXXX of the GCC provides the law
governing, the procedure and administration of
any arbitration instituted pursuant to Clause
XXXX as the law of the United Arab Emirates and
of Dubai.
• 20. The Contracts at Clause XXXX states that:
• The Contract shall be governed by and
construed according to the laws in force in the
U.A.E. and in Dubai.
• 21. Consequently, the law applicable to the
merits and the procedure of the arbitration shall
be the laws in force in UAE and in Dubai.
23
11 Reservation
of Rights
• 22. The Claimant reserves its right generally
to amend and/or supplement this Request,
and among other issues, to request other
relief, including damages, as the Claimant
may consider necessary or appropriate to
enforce and/or defend its rights.
24
12 Articles 4.3
and 4.4 of the
DIAC Rules
:Submission of
this Request for
Arbitration
• 23. In accordance with Articles 4.3 and 4.4
of the DIAC Rules, the Claimant is submitting
five copies of this Request for Arbitration,
along with a cash receipt in the amount of
5000 AED, as required by the DIAC Rules.
• Respectfully submitted on behalf of
• MR. CLAIMANT SMITH
• Mr. César del Riego- Attorney At Law-
Madrid Bar
25
26
CÉSAR DEL RIEGO : abogado
especialista en contratación
fiscalidad y corporate; en los
marcos regulatorios de
Turquía CEI y EMEA; de los
sectores de Construcción,
Energía e Ingeniería.
✓ Especializado en los aspectos Contractuales,
marco regulatorio y de licitación y Corporativos
de proyectos internacionales de Construcción,
Energía e Ingeniería derivados de Concesiones y
contratos EPC-EPCM en Oriente Medio, Norte de
África (EMEA), Asia Central (CEI) y Europa del
Este. Gestión de proyecto y seguimiento de
variaciones, reclamaciones, DB- DAB art. 20 FIDIC,
arbitraje.
✓ Track record: firmas jurídicas Turquía- España.
Pekin&Pekin Law Firm (legal 500 tier 1 en
Corporate &Tax en Turquía, socio único de Uría y
Menendez- Lex Mundi. Akinci Law única
representante Turca en GAR Arbitraje, y top Legal
500 en ADR Construcción y Energía. Lambal,FIDIC-
arbitration law firm en España. Subinspector de
Hacienda en España. Secretaría del Consejo de
Administración de sociedad cotizada en España.
Legal Counsel para capital jordano- saudí, oil&
gas group of companies, Luxembourg based
investment group .

More Related Content

What's hot

Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contractsHafizul Mukhlis
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..Rajesh Prasad
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paidBarry Hembling
 

What's hot (20)

Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Progress and delay_
Progress and delay_Progress and delay_
Progress and delay_
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contracts
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Construction law cl3 (completed)
Construction law cl3 (completed)Construction law cl3 (completed)
Construction law cl3 (completed)
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
tendering
 tendering tendering
tendering
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Nit55
Nit55Nit55
Nit55
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
 
Contract Management
Contract Management Contract Management
Contract Management
 
Site possession
Site possessionSite possession
Site possession
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Retention fund
Retention fundRetention fund
Retention fund
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 

Similar to DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real Case)

AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016Avinash Kumar Gupta
 
Summary proceedingS- An Overview
Summary proceedingS- An OverviewSummary proceedingS- An Overview
Summary proceedingS- An OverviewPriyanka Agarwal
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsResolution Institute
 
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoHow to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoMadisonWilliamson2
 
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART I
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART IADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART I
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART Icmmindia2017
 
Bar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxBar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxphilipjamero
 
The Patents County Court Small Claims Track
The Patents County Court Small Claims TrackThe Patents County Court Small Claims Track
The Patents County Court Small Claims TrackJane Lambert
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentationDoreen Yeo
 
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfDispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfANKITGUPTA592329
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Laina Chan
 
15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.Andrew Downie
 
2017 04-07 ytio hockema cle slidedeck
2017 04-07 ytio hockema cle slidedeck2017 04-07 ytio hockema cle slidedeck
2017 04-07 ytio hockema cle slidedeckD. Todd Smith
 
SMALL CLAIM TRACK
SMALL CLAIM TRACK SMALL CLAIM TRACK
SMALL CLAIM TRACK ACID_SLIDES
 
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatory
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatoryICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatory
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatoryCésar del Riego y Fuentes
 

Similar to DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real Case) (20)

AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
 
Summary proceedingS- An Overview
Summary proceedingS- An OverviewSummary proceedingS- An Overview
Summary proceedingS- An Overview
 
Adr
AdrAdr
Adr
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution Boards
 
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San DiegoHow to Prepare for Small Claims Court to Collect Rental Debt in San Diego
How to Prepare for Small Claims Court to Collect Rental Debt in San Diego
 
Fast track procedure
Fast track procedureFast track procedure
Fast track procedure
 
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART I
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART IADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART I
ADR - 6TH May Cpt. BHATIA (F) - 7TH LECTURE PART I
 
Bar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptxBar-Workshop-11-November-2019.FINAL_.pptx
Bar-Workshop-11-November-2019.FINAL_.pptx
 
The Patents County Court Small Claims Track
The Patents County Court Small Claims TrackThe Patents County Court Small Claims Track
The Patents County Court Small Claims Track
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfDispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
 
15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.15 March 2016 - Law Institute of Victoria conference presentation.
15 March 2016 - Law Institute of Victoria conference presentation.
 
Exparte injunction
Exparte injunctionExparte injunction
Exparte injunction
 
CIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptxCIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptx
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
O. XXXVII OF CPC,1908 [SUMMARY PROCEDURE]
 
2017 04-07 ytio hockema cle slidedeck
2017 04-07 ytio hockema cle slidedeck2017 04-07 ytio hockema cle slidedeck
2017 04-07 ytio hockema cle slidedeck
 
SMALL CLAIM TRACK
SMALL CLAIM TRACK SMALL CLAIM TRACK
SMALL CLAIM TRACK
 
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatory
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatoryICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatory
ICC ARBITRATION upon FIDIC- DISPUTE BOARD as mandatory
 

Recently uploaded

Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791BlayneRush1
 
Sports Writing for PISAYyyyyyyyyyyyyyy.pptx
Sports Writing for PISAYyyyyyyyyyyyyyy.pptxSports Writing for PISAYyyyyyyyyyyyyyy.pptx
Sports Writing for PISAYyyyyyyyyyyyyyy.pptxmarielouisetulaytay
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一st Las
 
Succession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeSuccession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeMelvinPernez2
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaAbheet Mangleek
 
Difference between LLP, Partnership, and Company
Difference between LLP, Partnership, and CompanyDifference between LLP, Partnership, and Company
Difference between LLP, Partnership, and Companyaneesashraf6
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书SD DS
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsAbdul-Hakim Shabazz
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementShubhiSharma858417
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书SD DS
 
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis Lee
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis LeeAlexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis Lee
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis LeeBlayneRush1
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxsrikarna235
 
The Prevention Of Corruption Act Presentation.pptx
The Prevention Of Corruption Act Presentation.pptxThe Prevention Of Corruption Act Presentation.pptx
The Prevention Of Corruption Act Presentation.pptxNeeteshKumar71
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书FS LS
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxKUHANARASARATNAM1
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionNilamPadekar1
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 

Recently uploaded (20)

Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791Alexis O'Connell Lexileeyogi 512-840-8791
Alexis O'Connell Lexileeyogi 512-840-8791
 
Sports Writing for PISAYyyyyyyyyyyyyyy.pptx
Sports Writing for PISAYyyyyyyyyyyyyyy.pptxSports Writing for PISAYyyyyyyyyyyyyyy.pptx
Sports Writing for PISAYyyyyyyyyyyyyyy.pptx
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
 
Succession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil CodeSuccession (Articles 774-1116 Civil Code
Succession (Articles 774-1116 Civil Code
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in India
 
Difference between LLP, Partnership, and Company
Difference between LLP, Partnership, and CompanyDifference between LLP, Partnership, and Company
Difference between LLP, Partnership, and Company
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
 
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 ShopsVanderburgh County Sheriff says he will Not Raid Delta 8 Shops
Vanderburgh County Sheriff says he will Not Raid Delta 8 Shops
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreement
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
 
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis Lee
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis LeeAlexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis Lee
Alexis O'Connell lexileeyogi Bond revocation for drug arrest Alexis Lee
 
Test Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptxTest Identification Parade & Dying Declaration.pptx
Test Identification Parade & Dying Declaration.pptx
 
The Prevention Of Corruption Act Presentation.pptx
The Prevention Of Corruption Act Presentation.pptxThe Prevention Of Corruption Act Presentation.pptx
The Prevention Of Corruption Act Presentation.pptx
 
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
如何办理伦敦南岸大学毕业证(本硕)LSBU学位证书
 
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptxAn Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
An Introduction guidance of the European Union Law 2020_EU Seminar 4.pptx
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 sedition
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 

DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real Case)

  • 1. DUBAI- DIAC rules for - REQUEST FOR ARBITRATION GESTIÓN/ANÁLISIS DE CONTRATOS EPC/ GESTIÓN DE RECLAMACIONES-VARIACIONES/ARBITRAJE INTERNACIONAL CURSO Para SIEMENS-GAMESA Project Manager Lecturer: César del Riego y de Fuentes- Madrid - Spain 1
  • 2. DUBAI-DIAC REQUEST FOR ARBITRATION 1 Introduction 2 Parties 3 Agreement to Arbitrate 4 Description of the Dispute 5 Relief Sought 6 Appointment of the Arbitrator 7 The Statement of Claim 8 Place of Arbitration 9 Language of Arbitration 10 Applicable Rules of Law 11 Reservation of Rights 12 Submission of this Request for Arbitration 2
  • 3. DUBAI RFA- PORTADA • CLAIMANT • RESPONDANT • REPRESENTATION • DATE MR. CLAIMANT SMITH Represented by Mr. César del Riego y de Fuentes- Attorney At Law -Madrid Bar Association C/Avenida de Rotonda, nº4 Madrid (Madrid) 28028 España Tel: +34 99992222299999 Fax: +34 99990000007777 Claimant versus MR. DEFENDANT JONES Round St. Dubai U.A.E. Respondent _______________________________________________________ REQUEST FOR ARBITRATION _________________________________________________________ November 26, 2020 3
  • 4. • Article 4.1 of the DIAC Rules: RFA • Article 4.1.(a) of DIAC Rules: RFA hereby requests from the Centre that the dispute be referred to arbitration under DIAC Rules. • Article 4.1.(c) of the DIAC Rules: Arbitration Agreement- invoked by the Claimant, together with a copy of the contractual documentation. • Articles 4.3 and 4.4 of the DIAC Rules: Submit 5 copies and a 5000 UAE security bond. • Article 23 of the DIAC Rules: CLAIM: The full documents supporting the Claimant’s claim shall be provided with the Statement of Claim • Article 23 of the DIAC Rules: Claim submitted in 30 days. • Article 8.2 of DIAC Rules: Appointment of the arbitrator. 4
  • 5. 1 Introduction • 1. This Request for Arbitration is made under Article 4.1 of the DIAC Rules by MR. CLAIMANT SMITH , in connection with disputes arising out of the Construction Contract for Torero Power Plant dated 15 June 2018, signed between MR. CLAIMANT SMITH and MR. DEFENDANT JONES, (the “Contract”). • 2. MR. CLAIMANT SMITH hereby requests from the Centre that the dispute be referred to arbitration under DIAC Rules according to Article 4.1.(a) of DIAC Rules. 5
  • 6. 2 Parties • 3. Claimant: The Claimant, MR. CLAIMANT SMITH , is a company incorporated under the laws of Dubai, United Arab Emirates. • 4. MR. CLAIMANT SMITH was the Contractor under the Contract (hereinafter referred to as the Contractor or the Claimant). • 5. The address of the Claimant is: • Rapsody St. • Dubai, United Arab Emirates • Phone: +971 55555577777 • Fax: +971 788888766666 6
  • 7. 2 Parties • 6. The Representative of the Claimant is: • Mr. César del Riego y de Fuentes-Madrid Bar Accredited • C/Avenida de Rotonda, nº4 • Madrid (Madrid) 28028 España • Tel: +34 99992222299999 • Fax: +34 99990000007777 • E-mail: cesar.riego@icam.es • 7. The Claimant requests all communications to be sent to the Claimant’s representative. • 8. Respondent: The Respondent is MR. DEFENDANT JONES located in Dubai, United Arab Emirates. 7
  • 8. 2 Parties • 9. MR. DEFENDANT JONES was the Employer under the Contract (hereinafter referred to as the Employer or the Respondent). • 10. The address of the Respondent is: • Rapsody St. • Dubai, United Arab Emirates • Phone: +971 444477777 • Fax: +971 4449999999 8
  • 9. 3 Agreement to Arbitrate • 13. Sub-Clause xxxxx of the General Conditions of the Contract (hereinafter the GCC), amended by the Conditions of Particular Applications (CPA) refers to Arbitration for the settlement of disputes: • Sub-Clause xxxx Conditions of Particular Application • Any dispute connected with the formation, performance, interpretation, nullification, termination or invalidation of this Contract or arising there from or related thereto in any manner whatsoever which: • (a) the decision, if any, of the Employer Representative has not become final and binding pursuant to Sub Clause xxxx and • (b) amicable settlement has not been reached within the period stated in Sub Clause xxxxx 9
  • 10. 3 Agreement to Arbitrate • shall be referred to arbitration in Dubai UAE, in accordance with the provisions set forth in the rules of Arbitration of the Dubai International Arbitration Centre (DIAC). • Neither party shall be limited in the proceedings before the arbitrator(s) to the evidence or arguments put before the Employer Representative for the purpose of obtaining his said decision pursuant to Sub-Clause xxxxx. No such decision shall disqualify the Employer Representative from being called as witness and giving evidence before the arbitrator(s) on any matter whatsoever relevant to the dispute. • Arbitration may be commenced prior to or after the completion of the Works, provided that the obligations of the Employer, the Employer Representative and the Contractor shall not be altered by reason of the arbitration being conducted during the progress of the Works. 10
  • 11. 3 Agreement to Arbitrate • 18. Article 4.1.(c) of the DIAC Rules. copy of the Arbitration Agreement invoked by the Claimant, together with a copy of the contractual documentation in which the Arbitration Agreement is contained or in respect of which the arbitration arises is attached as C1 to this Request for Arbitration in accordance with Article 4.1.(c) of the DIAC Rules. 11
  • 12. 4 Article 4.1.(c) of the DIAC Rules: Description of the Dispute • 19. The following is “a brief description of the nature and circumstances of the dispute giving rise to the claim” in accordance with Article 4.1(d) of the DIAC Rules. The Claimant reserves the right generally to amend and/or supplement the facts, the claims, and legal and contractual grounds. The full documents supporting the Claimant’s claim shall be provided with the Statement of Claim under Article 23 of the DIAC Rules and further submissions during the arbitration proceedings. 12
  • 13. 5 Relief Sought • 20. In consideration of all of the above, the Claimant respectfully requests the Arbitral Tribunal to: • 1. declare that the termination of the Contract Torero CCPP, dated 15 June 2018 by the Claimant was valid and justified; • 2. declare that the Respondent's purported termination of the Contract Torero Power Plant, dated 15 June 2018 was invalid, unjustified and or unlawful; • 3. declare that the Claimant is entitled to an Extension of Time for Completion to the Termination of the Works being 26 September 2018; • 4. order that the Respondent return the Performance Security Bond to the Claimant within 10 days following the receipt of the Award; 13
  • 14. 5 Relief Sought • 5. order that the Respondent pay the Claimant AED XXXXXXX for the sums of; • a- Contract Works and General Requirements • b- Materials on Site • c- Variations and Additional Works • d- Loss of Overheads and Profit • e- Prolongation Claimed Costs • f- Interest Charges on Delayed Payment up to 31 July 2011 • g- Damages due to the Advance Payment Guarantee being called in 14
  • 15. 5 Relief Sought • h- Subcontractor’s Claims • i- Non productive Manpower Claim • 6. order that the Respondent pay the Claimant interest on all amounts it is ordered to pay pursuant to these proceedings, from the date of the event giving rise to the claim; • 7. order that the Respondent pay the Claimant all costs and expenses (including, but not limited to, costs payable to DIAC, legal fees and expenses and fees and expenses of experts, consultants and others) incurred by the Claimant in connection with the preparation for and conduct of this arbitration; 15
  • 16. 5 Relief Sought • 8. order that the Respondent pay the Claimant post-award interest on all amounts it is ordered to pay pursuant to these proceedings, from the date of the Award until receipt of payment of such amount by the Claimant; • 9. order that the Respondent pay the Claimant such other relief as the Arbitral Tribunal deems appropriate under the circumstances; • 11. For the purpose of computation of the arbitration fees, and without prejudice to its rights in law or equity, the Claimant estimates its total claim to amount to AED XXXXXX and in a separate Statement of Claim, will detail the heads of claim outlined above and will denominate each in figures, supported by evidence. 16
  • 17. 6 Article 8.2 of DIAC Rules :Appointment of the Arbitrator • 12. There is no determination on the number of the arbitrators in the Arbitration Agreements between the Parties. • 13. Article 8.2 of DIAC Rules provides that: • 8.2 Where the parties have not agreed on the number of arbitrators, the Tribunal shall consist of a sole arbitrator, except where the Centre in its discretion determines that, in view of all the circumstances of the dispute, a Tribunal composed of three members is appropriate. • 17
  • 18. 6 Article 8.2 of DIAC Rules :Appointment of the Arbitrator 1. In view of all the circumstances, the amount and the complicated nature of the dispute explained above, the Claimant requests from the Centre that a tribunal of three members is to be composed. 2. The Claimant hereby nominates Mr Guillaume Chavaliere, as party arbitrator for the Claimant, who is located at: • 5 Rue St. Honorée • Montreal • Quebecq- Canada. 18
  • 19. 7 Article 23 of the DIAC Rules: The Statement of Claim • 16. The Statement of Claim referred will be submitted in accordance with Article 23 of the DIAC Rules, within 30 days of receipt of notification from the Centre of the establishment of the Tribunal or such later time limit as the Tribunal may allow. 19
  • 20. (B) ASPECTOS REGULADOS POR EL CONVENIO ARBITRAL: 20
  • 21. 8 Regulado por Cláusula Arbitral: Place of Arbitration • 17. Clause XXX of the General Conditions of the Contract provides for the place of the arbitration as Dubai: • Sub-Clause XXXX Law and Procedure: • The law governing the procedure and administration of any arbitration instituted pursuant to Clause XXX shall be the law of the United Arab Emirates and of Dubai. The language of arbitration shall be English and the place of arbitration shall be Dubai. 21
  • 22. 9 Regulado por Cláusula Arbitral: Language of Arbitration • 18. Clause XXXX of the GCC provides for the language of the arbitration. According to Clause XXXX the language of the Arbitration shall be English (see above Section 8). 22
  • 23. 10 Regulado por Cláusula Arbitral: Applicable Rules of Law • 19. Clause XXXX of the GCC provides the law governing, the procedure and administration of any arbitration instituted pursuant to Clause XXXX as the law of the United Arab Emirates and of Dubai. • 20. The Contracts at Clause XXXX states that: • The Contract shall be governed by and construed according to the laws in force in the U.A.E. and in Dubai. • 21. Consequently, the law applicable to the merits and the procedure of the arbitration shall be the laws in force in UAE and in Dubai. 23
  • 24. 11 Reservation of Rights • 22. The Claimant reserves its right generally to amend and/or supplement this Request, and among other issues, to request other relief, including damages, as the Claimant may consider necessary or appropriate to enforce and/or defend its rights. 24
  • 25. 12 Articles 4.3 and 4.4 of the DIAC Rules :Submission of this Request for Arbitration • 23. In accordance with Articles 4.3 and 4.4 of the DIAC Rules, the Claimant is submitting five copies of this Request for Arbitration, along with a cash receipt in the amount of 5000 AED, as required by the DIAC Rules. • Respectfully submitted on behalf of • MR. CLAIMANT SMITH • Mr. César del Riego- Attorney At Law- Madrid Bar 25
  • 26. 26 CÉSAR DEL RIEGO : abogado especialista en contratación fiscalidad y corporate; en los marcos regulatorios de Turquía CEI y EMEA; de los sectores de Construcción, Energía e Ingeniería. ✓ Especializado en los aspectos Contractuales, marco regulatorio y de licitación y Corporativos de proyectos internacionales de Construcción, Energía e Ingeniería derivados de Concesiones y contratos EPC-EPCM en Oriente Medio, Norte de África (EMEA), Asia Central (CEI) y Europa del Este. Gestión de proyecto y seguimiento de variaciones, reclamaciones, DB- DAB art. 20 FIDIC, arbitraje. ✓ Track record: firmas jurídicas Turquía- España. Pekin&Pekin Law Firm (legal 500 tier 1 en Corporate &Tax en Turquía, socio único de Uría y Menendez- Lex Mundi. Akinci Law única representante Turca en GAR Arbitraje, y top Legal 500 en ADR Construcción y Energía. Lambal,FIDIC- arbitration law firm en España. Subinspector de Hacienda en España. Secretaría del Consejo de Administración de sociedad cotizada en España. Legal Counsel para capital jordano- saudí, oil& gas group of companies, Luxembourg based investment group .