SlideShare a Scribd company logo
1 of 29
Smoothness Specifications Moving Forward
Don Matthews, PE
Pavement Recycling Systems, Inc.
Tom Pyle, PE
Caltrans
Why we are here…
• Smoothness is important to
Caltrans
• Continuous improvement
process
• Reduce claims
• Improve California's
pavement
The revised specification re-write
effort is a collaboration between
Caltrans and Industry
1. Agreed on fundamental
improvements needed
2. Agreed on concept for spec
layout and design
3. Partnered on writing of the
specification
4. Joint Industry and Caltrans
concurrent review
5. Joint resolution of comments
Data Driven Changes
Performance based
• Most projects will incentivize
paving
• Full Pay has opened up to a
wider scope
• Options for corrections
• Each 0.1 mile is managed
independently
Caltrans Expectations
• Maximum smoothness
improvements to every project
• Pay incentives for considerable
improvements
• Full pay is now a wider window
• There will be considerably less
pre-paving grinding and
• Pavement will achieve higher
smoothness though continuous
percent improvement of
projects
• Less claims
Specifications Effected and how
Section 36
• Smoothness quality control plan
• Reference points
• Verification testing of contractors
• Conflict resolution
Section 39
• Contractor runs the data
• State runs the Quality Assurance
• Opportunity driven (Discussed later)
• Incentives/Disincentives
• New Data entry sheets to mange every 0.1 mile
Section 40
• Leave outs such as tight ramps
• Considerations for inlays where the shoulder and existing pavement are rough
• Incentives and disincentives
• New Data Entry sheets to manage every 0.1 mile
All roads will be smoother and begin a change
towards shifting California’s roads to among the
smoothest in the country
1. The smoothness ride goals will
be continuously shifting toward
a better ride
2. Incentives will encourage
contractors to achieve better
results
3. Better planned projects will
lead to less claims
THE NEW ASPHALT SMOOTHNESS
SPECIFICATION
Subject to Change for Both Content and
Terminology
NEW CONSTRUCTION
Use the Target HMA 60 MRI Pay Adjustment Table
Target 60 Pay Adjustment
MRIseg(in/mi) Pay Adjustment/0.1 mi Corrective Action
≤ 45.00 + $900.00 None
45.01 – 55.00 + ((55.00 – MRIseg) x $90.00) None
55.01 - 65.00 Full Pay None
65.01 – 80.00 - ((MRIseg – 65.00) x $190.00) Optional
> 80.00 Not Applicable Mandatory
No Areas of Localized Roughness (ALR) Over 160
in/mi
COLD IN-PLACE RECYCLING (CIR)
EXISTING SPEC (NOT DISCUSSED YET)
CIR Finished Surface -
Must have MRI Below 90 in/mi
ALRs Less than 240 in/mi
HMA Overlay Finished Surface -
Use the Target HMA 60 Pay Adjustment Table
ALRs Less than 160 in/mi
FOR CONSTRUCTION ON EXISTING
PAVEMENT SURFACES
Based On:
Number of Smoothness Opportunities
Inertial Profile of the Existing Pavement (MRI of Each Existing
Segment)
Any Prepaving Corrections (Bid Items)
For An Existing Surface - How a Designer May Look At It
Below Line Should Get Smoothness Wanted
Above the Line Can Put in Bid Items for Prepaving Corrections
Dig Outs (Bid by Square Yard and Ton?)
or Leveling Course (Bid by Ton)
Used To Repair Severely Distressed Areas
Locations Should Be Shown on The Plan
STRUCTURAL REPAIRS
SURFACE PROFILING FULL WIDTH
CORRECTIONS
Diamond Grinding or Micro Mill the Entire Pavement Surface
Full Width and Not Required to Be Done in the Same Shift of Paving
Locations Shown on the Plan (Bid By Square Yard)
Should be Used in Large Areas Requiring Profile Corrections
Key: Is Considered a Full Smoothness Opportunity in All MRI Segments
Corrected
PREPAVING PARTIAL WIDTH CORRECTIONS
Should Be Used When a Smaller Percentage of 0.10 Mile MRI Sections Need
Correction
Bid By 0.10 Mile Segments
PREPAVING PARTIAL WIDTH CORRECTIONS
Corrected at Contractors Option:
• Diamond Grinding or Micro Milling Where Contractor Considers Necessary
e.g. Wheel Paths or Cold Planer/Paver Referencing Locations
• Or Maybe Contractor Can Get Final Surface By Using 3D Automatic Machine
Guidance
• Or An Alternative Proposal By Contractor and Approved by the Engineer
Key:
True Performance – Segments Corrected Must Comply with Final HMA
Smoothness Requirements i.e No Percent Improvement
1) Mark the Start and End of the Paving with Semi Permanent
Reference Points (Including any Leave Outs such as Bridges)
2) Inertial Profile the Existing Asphalt Concrete Surface Before
Performing Any Work. Label as EXIST Inertial Profile Data File
3) Notify the Engineer if EXIST MRI Results Vary More Than 10 Percent
From the Prebid MRI
STEP BY STEP OF THE SPECIFICATION
4) Are There Structural Repairs?
Yes –
Make The Structural Repairs and Inertial Profile Again (Label as
BASELINE Data File)
MRI0 is the lower MRI value from the EXIST and BASELINE profiles
for Each 0.1 Mile Segment
No –
Go To Next Step
5) Is There Surface Profiling Full Width Segment Corrections?
Yes –
Conduct Surface Profiling in Areas Shown on Plans
Contractor Can Measure and Additionally Correct Any Areas They
Deem Necessary
Corrected Surface Does Not Need To Be Profiled
MRI0 is the EXIST Profile for Each 0.1 Mile Segment Prior to Surfacing
Profiling
Adds a Smoothness Opportunity in the Areas Corrected
No –
Go To Next Step
6) Are There Prepaving Partial Width Segment Corrections?
Yes –
Contractor Completes Proposed Corrections in 0.10 Mile Segment
Contractor Can Measure and Additionally Correct Any Areas Deemed
Necessary
Corrected Surface Does Not Need To Be Profiled
MRI0 Does Not Apply
For Final HMA => 0.30’ Use Target 60 Pay Adjustment Table
For Final HMA < 0.30’ Use Target 75 Pay Adjustment Table
No –
Go To Next Step
A) HMA => 0.30 and MRI0 <165 in/mi
7) Determine What Pay Adjustment Table To Use
B) HMA < 0.30 and MRI0 <135 in/mi
Does Not Meet A or B Go To C – Percent Improvement
No ALR over
160 in/mi
1 opportunity: MRIt = 0.3 x MRIo + 35 (or 60 MRI whichever is greater)
2 opportunities: MRIt = 0.09 x MRIo + 45.5 (or 60 MRI whichever is greater)
• Single Lift of Asphalt (Overlay)
Note: Number of opportunities is based on the maximum number
of lifts the layer can be broken into:
Maximum Nominal Aggregate Size
Lift Thickness
• Micro Milling or Cold planing Not in the Same Shift as the
Paving (Surface Profiling Full Width Segment Correction
Qualifies Here)
• Mill and Fill in the Same Shift
What is an Opportunity?
Calculate Target MRI of Finished HMA Based Upon MRI0
C) % Improvement
C) % Improvement
Payment adjustment
per 0.10 mile per lane
=> 0.30’
Payment adjustment per
0.10 mile per lane
< 0.30’
Corrective Grinding
PoT ≤ 75% $900.00 $450.00 May only grind ALR
75% < PoT < 90% $900.00 - ((PoT –
75.00) x $60.00
$450.00 - (PoT-75.00) x
$30.00
May only grind ALR
90% < PoT < 110% Full Pay ($0.00) Full Pay ($0.00) May only grind ALR
110% < PoT < 125% -(PoT – 110.00) x
($190.00)
-(PoT – 110.00) x
($135.00)
Corrective grinding
permitted
If MRISEG ≤ 90 in/mi and
PoT > 125%
-(PoT-110.00) x
($190.00)
-(PoT-110.00) x
($135.00)
Corrective grinding
permitted
If MRISEG > 90 in/mi and
PoT > 125%
Not Applicable Not Applicable Mandatory Correction
PoT = (MRISEG / MRIt ) x 100%
ALRmax = 2.1x MRI or 160 in/mi, Whichever is Greater
Example 0.10 Mill and Fill (Where Design Did Not Include Prepaving Corrections)
All 0.10 mile sections above 135 MRI Baseline – Target % Improvement
All 0.10 mile sections at or below 135 MRI Baseline – Target 75 MRI
Target MRI is 83.6 in/mi
Incentives Begin At 75.2
Disincentives Begin At 92.0
Open Grade Friction Course (OGFC)
On New HMA –
Essentially Make As Good or Better Than Underlying Final HMA (Where
Incentives/Disincentives Apply) Or Penalty Applies
On Milled Surface –
Mill and Fill of the OGFC – Use Target 75 Pay Adjustment Table
On Existing Surface –
Use % Improvement
What’s Next: NSSP, Guidelines and Training
• Post NSSPs (36, 39, 40) by Nov 2
• Guidelines have been drafted for Design and Construction. They will
be finished after the spec is complete. Target is late November
• Training will begin in early December Caltrans. CalAPA is also going to
start training very soon
Refine, Refine, Refine
We need data from projects!
Did you find an improvement?
Are the limits appropriate?
Are the targets working?
Thank you!

More Related Content

Similar to Caltrans pavement smoothness specifications moving forward

2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness
2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness
2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement SmoothnessCalifornia Asphalt Pavement Association
 
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...Design World
 
external presentation (final)without videos
external presentation (final)without videosexternal presentation (final)without videos
external presentation (final)without videossai nitish
 
Geometrical Dimensioning and Tolerancing
Geometrical Dimensioning and TolerancingGeometrical Dimensioning and Tolerancing
Geometrical Dimensioning and Tolerancingssuser5670d6
 
GDT CHAPTER 1- Overview and introduction.ppt
GDT CHAPTER 1- Overview and introduction.pptGDT CHAPTER 1- Overview and introduction.ppt
GDT CHAPTER 1- Overview and introduction.pptsyisyi87
 
Brochure FMI - Productos comerciales para espacio
Brochure FMI - Productos comerciales para espacioBrochure FMI - Productos comerciales para espacio
Brochure FMI - Productos comerciales para espacioMarketing Donalba
 
PREDICTING FAILURES_AUGUST2007
PREDICTING FAILURES_AUGUST2007PREDICTING FAILURES_AUGUST2007
PREDICTING FAILURES_AUGUST2007Gan Chun Chet
 

Similar to Caltrans pavement smoothness specifications moving forward (20)

New Caltrans pavement smoothness specifications
New Caltrans pavement smoothness specificationsNew Caltrans pavement smoothness specifications
New Caltrans pavement smoothness specifications
 
2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness
2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness
2019 TRB Annual Meeting Presentation No. P19 21237 - Pavement Smoothness
 
Strategies for Smooth Pavements
Strategies for Smooth PavementsStrategies for Smooth Pavements
Strategies for Smooth Pavements
 
Strategies for Smooth Pavements
Strategies for Smooth PavementsStrategies for Smooth Pavements
Strategies for Smooth Pavements
 
Strategices for Smooth Pavements
Strategices for Smooth PavementsStrategices for Smooth Pavements
Strategices for Smooth Pavements
 
Track
TrackTrack
Track
 
03 adam hand
03 adam hand03 adam hand
03 adam hand
 
Superpave - Low Volume
Superpave - Low VolumeSuperpave - Low Volume
Superpave - Low Volume
 
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...
Applying Stepper Motors: Application Questions You Must Answer & Things to Wa...
 
Superpave - Low Volume
Superpave - Low VolumeSuperpave - Low Volume
Superpave - Low Volume
 
Peter Vacura - Asphalt Pavement Smoothness
Peter Vacura - Asphalt Pavement SmoothnessPeter Vacura - Asphalt Pavement Smoothness
Peter Vacura - Asphalt Pavement Smoothness
 
Update on Pavement Smoothness in California
Update on Pavement Smoothness in CaliforniaUpdate on Pavement Smoothness in California
Update on Pavement Smoothness in California
 
external presentation (final)without videos
external presentation (final)without videosexternal presentation (final)without videos
external presentation (final)without videos
 
Geometrical Dimensioning and Tolerancing
Geometrical Dimensioning and TolerancingGeometrical Dimensioning and Tolerancing
Geometrical Dimensioning and Tolerancing
 
GDT CHAPTER 1- Overview and introduction.ppt
GDT CHAPTER 1- Overview and introduction.pptGDT CHAPTER 1- Overview and introduction.ppt
GDT CHAPTER 1- Overview and introduction.ppt
 
Superpave orientation local agencies
Superpave orientation local agenciesSuperpave orientation local agencies
Superpave orientation local agencies
 
Brochure FMI - Productos comerciales para espacio
Brochure FMI - Productos comerciales para espacioBrochure FMI - Productos comerciales para espacio
Brochure FMI - Productos comerciales para espacio
 
Enacting Changes to the Hamburg Wheel Track Test
Enacting Changes to the Hamburg Wheel Track TestEnacting Changes to the Hamburg Wheel Track Test
Enacting Changes to the Hamburg Wheel Track Test
 
PREDICTING FAILURES_AUGUST2007
PREDICTING FAILURES_AUGUST2007PREDICTING FAILURES_AUGUST2007
PREDICTING FAILURES_AUGUST2007
 
Long Life Asphalt Pavements in California
Long Life Asphalt Pavements in CaliforniaLong Life Asphalt Pavements in California
Long Life Asphalt Pavements in California
 

More from California Asphalt Pavement Association

National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...California Asphalt Pavement Association
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...California Asphalt Pavement Association
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024California Asphalt Pavement Association
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansCalifornia Asphalt Pavement Association
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolCalifornia Asphalt Pavement Association
 

More from California Asphalt Pavement Association (20)

Reducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industryReducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industry
 
Industry perspective on cold in-place recycling
Industry perspective on cold in-place recyclingIndustry perspective on cold in-place recycling
Industry perspective on cold in-place recycling
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Caltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavementsCaltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavements
 
Update on the latest research with regard to RAP
Update on the latest research with regard to RAPUpdate on the latest research with regard to RAP
Update on the latest research with regard to RAP
 
Pavement quality focus for local agencies in California
Pavement quality focus for local agencies in CaliforniaPavement quality focus for local agencies in California
Pavement quality focus for local agencies in California
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...
 
Utilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixesUtilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixes
 
Pavement Maintenance tools and technology update
Pavement Maintenance tools and technology updatePavement Maintenance tools and technology update
Pavement Maintenance tools and technology update
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiative
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industry
 
Asphalt industry EPD benchmarking update 2024
Asphalt industry EPD benchmarking update  2024Asphalt industry EPD benchmarking update  2024
Asphalt industry EPD benchmarking update 2024
 
Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials technicians
 
EPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt PlantEPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt Plant
 
EPD Benchmarks and lessons learned
EPD Benchmarks and lessons learnedEPD Benchmarks and lessons learned
EPD Benchmarks and lessons learned
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD tool
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 

Caltrans pavement smoothness specifications moving forward

  • 1. Smoothness Specifications Moving Forward Don Matthews, PE Pavement Recycling Systems, Inc. Tom Pyle, PE Caltrans
  • 2. Why we are here… • Smoothness is important to Caltrans • Continuous improvement process • Reduce claims • Improve California's pavement
  • 3. The revised specification re-write effort is a collaboration between Caltrans and Industry 1. Agreed on fundamental improvements needed 2. Agreed on concept for spec layout and design 3. Partnered on writing of the specification 4. Joint Industry and Caltrans concurrent review 5. Joint resolution of comments
  • 5. Performance based • Most projects will incentivize paving • Full Pay has opened up to a wider scope • Options for corrections • Each 0.1 mile is managed independently
  • 6. Caltrans Expectations • Maximum smoothness improvements to every project • Pay incentives for considerable improvements • Full pay is now a wider window • There will be considerably less pre-paving grinding and • Pavement will achieve higher smoothness though continuous percent improvement of projects • Less claims
  • 7. Specifications Effected and how Section 36 • Smoothness quality control plan • Reference points • Verification testing of contractors • Conflict resolution Section 39 • Contractor runs the data • State runs the Quality Assurance • Opportunity driven (Discussed later) • Incentives/Disincentives • New Data entry sheets to mange every 0.1 mile Section 40 • Leave outs such as tight ramps • Considerations for inlays where the shoulder and existing pavement are rough • Incentives and disincentives • New Data Entry sheets to manage every 0.1 mile
  • 8. All roads will be smoother and begin a change towards shifting California’s roads to among the smoothest in the country 1. The smoothness ride goals will be continuously shifting toward a better ride 2. Incentives will encourage contractors to achieve better results 3. Better planned projects will lead to less claims
  • 9. THE NEW ASPHALT SMOOTHNESS SPECIFICATION Subject to Change for Both Content and Terminology
  • 10. NEW CONSTRUCTION Use the Target HMA 60 MRI Pay Adjustment Table Target 60 Pay Adjustment MRIseg(in/mi) Pay Adjustment/0.1 mi Corrective Action ≤ 45.00 + $900.00 None 45.01 – 55.00 + ((55.00 – MRIseg) x $90.00) None 55.01 - 65.00 Full Pay None 65.01 – 80.00 - ((MRIseg – 65.00) x $190.00) Optional > 80.00 Not Applicable Mandatory No Areas of Localized Roughness (ALR) Over 160 in/mi
  • 11. COLD IN-PLACE RECYCLING (CIR) EXISTING SPEC (NOT DISCUSSED YET) CIR Finished Surface - Must have MRI Below 90 in/mi ALRs Less than 240 in/mi HMA Overlay Finished Surface - Use the Target HMA 60 Pay Adjustment Table ALRs Less than 160 in/mi
  • 12. FOR CONSTRUCTION ON EXISTING PAVEMENT SURFACES Based On: Number of Smoothness Opportunities Inertial Profile of the Existing Pavement (MRI of Each Existing Segment) Any Prepaving Corrections (Bid Items)
  • 13. For An Existing Surface - How a Designer May Look At It Below Line Should Get Smoothness Wanted Above the Line Can Put in Bid Items for Prepaving Corrections
  • 14. Dig Outs (Bid by Square Yard and Ton?) or Leveling Course (Bid by Ton) Used To Repair Severely Distressed Areas Locations Should Be Shown on The Plan STRUCTURAL REPAIRS
  • 15. SURFACE PROFILING FULL WIDTH CORRECTIONS Diamond Grinding or Micro Mill the Entire Pavement Surface Full Width and Not Required to Be Done in the Same Shift of Paving Locations Shown on the Plan (Bid By Square Yard) Should be Used in Large Areas Requiring Profile Corrections Key: Is Considered a Full Smoothness Opportunity in All MRI Segments Corrected
  • 16. PREPAVING PARTIAL WIDTH CORRECTIONS Should Be Used When a Smaller Percentage of 0.10 Mile MRI Sections Need Correction Bid By 0.10 Mile Segments
  • 17. PREPAVING PARTIAL WIDTH CORRECTIONS Corrected at Contractors Option: • Diamond Grinding or Micro Milling Where Contractor Considers Necessary e.g. Wheel Paths or Cold Planer/Paver Referencing Locations • Or Maybe Contractor Can Get Final Surface By Using 3D Automatic Machine Guidance • Or An Alternative Proposal By Contractor and Approved by the Engineer Key: True Performance – Segments Corrected Must Comply with Final HMA Smoothness Requirements i.e No Percent Improvement
  • 18. 1) Mark the Start and End of the Paving with Semi Permanent Reference Points (Including any Leave Outs such as Bridges) 2) Inertial Profile the Existing Asphalt Concrete Surface Before Performing Any Work. Label as EXIST Inertial Profile Data File 3) Notify the Engineer if EXIST MRI Results Vary More Than 10 Percent From the Prebid MRI STEP BY STEP OF THE SPECIFICATION
  • 19. 4) Are There Structural Repairs? Yes – Make The Structural Repairs and Inertial Profile Again (Label as BASELINE Data File) MRI0 is the lower MRI value from the EXIST and BASELINE profiles for Each 0.1 Mile Segment No – Go To Next Step
  • 20. 5) Is There Surface Profiling Full Width Segment Corrections? Yes – Conduct Surface Profiling in Areas Shown on Plans Contractor Can Measure and Additionally Correct Any Areas They Deem Necessary Corrected Surface Does Not Need To Be Profiled MRI0 is the EXIST Profile for Each 0.1 Mile Segment Prior to Surfacing Profiling Adds a Smoothness Opportunity in the Areas Corrected No – Go To Next Step
  • 21. 6) Are There Prepaving Partial Width Segment Corrections? Yes – Contractor Completes Proposed Corrections in 0.10 Mile Segment Contractor Can Measure and Additionally Correct Any Areas Deemed Necessary Corrected Surface Does Not Need To Be Profiled MRI0 Does Not Apply For Final HMA => 0.30’ Use Target 60 Pay Adjustment Table For Final HMA < 0.30’ Use Target 75 Pay Adjustment Table No – Go To Next Step
  • 22. A) HMA => 0.30 and MRI0 <165 in/mi 7) Determine What Pay Adjustment Table To Use B) HMA < 0.30 and MRI0 <135 in/mi Does Not Meet A or B Go To C – Percent Improvement No ALR over 160 in/mi
  • 23. 1 opportunity: MRIt = 0.3 x MRIo + 35 (or 60 MRI whichever is greater) 2 opportunities: MRIt = 0.09 x MRIo + 45.5 (or 60 MRI whichever is greater) • Single Lift of Asphalt (Overlay) Note: Number of opportunities is based on the maximum number of lifts the layer can be broken into: Maximum Nominal Aggregate Size Lift Thickness • Micro Milling or Cold planing Not in the Same Shift as the Paving (Surface Profiling Full Width Segment Correction Qualifies Here) • Mill and Fill in the Same Shift What is an Opportunity? Calculate Target MRI of Finished HMA Based Upon MRI0 C) % Improvement
  • 24. C) % Improvement Payment adjustment per 0.10 mile per lane => 0.30’ Payment adjustment per 0.10 mile per lane < 0.30’ Corrective Grinding PoT ≤ 75% $900.00 $450.00 May only grind ALR 75% < PoT < 90% $900.00 - ((PoT – 75.00) x $60.00 $450.00 - (PoT-75.00) x $30.00 May only grind ALR 90% < PoT < 110% Full Pay ($0.00) Full Pay ($0.00) May only grind ALR 110% < PoT < 125% -(PoT – 110.00) x ($190.00) -(PoT – 110.00) x ($135.00) Corrective grinding permitted If MRISEG ≤ 90 in/mi and PoT > 125% -(PoT-110.00) x ($190.00) -(PoT-110.00) x ($135.00) Corrective grinding permitted If MRISEG > 90 in/mi and PoT > 125% Not Applicable Not Applicable Mandatory Correction PoT = (MRISEG / MRIt ) x 100% ALRmax = 2.1x MRI or 160 in/mi, Whichever is Greater
  • 25. Example 0.10 Mill and Fill (Where Design Did Not Include Prepaving Corrections) All 0.10 mile sections above 135 MRI Baseline – Target % Improvement All 0.10 mile sections at or below 135 MRI Baseline – Target 75 MRI Target MRI is 83.6 in/mi Incentives Begin At 75.2 Disincentives Begin At 92.0
  • 26. Open Grade Friction Course (OGFC) On New HMA – Essentially Make As Good or Better Than Underlying Final HMA (Where Incentives/Disincentives Apply) Or Penalty Applies On Milled Surface – Mill and Fill of the OGFC – Use Target 75 Pay Adjustment Table On Existing Surface – Use % Improvement
  • 27. What’s Next: NSSP, Guidelines and Training • Post NSSPs (36, 39, 40) by Nov 2 • Guidelines have been drafted for Design and Construction. They will be finished after the spec is complete. Target is late November • Training will begin in early December Caltrans. CalAPA is also going to start training very soon
  • 28. Refine, Refine, Refine We need data from projects! Did you find an improvement? Are the limits appropriate? Are the targets working?

Editor's Notes

  1. Changes were brought about due to contractors not able to meet the requirements. History: There was a target of 60 with pre grinding. There was also a 75 with pre grinding. Your maintenance projects often had more days of grinding than paving. Caltrans and Industry have worked side by side to make significant changes. This is different.